Well ID: 34-151-25878
Loading map...
Country: United States
State: Ohio
County: Stark
Municipality: Perry Township
Operator Name: DISCOVERY OIL AND GAS
Well Pad ID:
Farm/Lease Name: JIM KLICK
License Status: Producing
License Date: 2014-12-18
Spud Date: 2014-12-20
Spud Drilling Contractor: WILDCAT DRILLING
Final Drill Date: 2015-01-15
Well Total Depth: 7067.00 ft
Configuration: Vertical
Latitude: 40.750000
Longitude: -81.480000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-12-18 Proposed Formations:ORISKANY THRU KNOX (MAY NOT PRODUCE PARKER SHELL), Issued Date:12/18/2014, Expired Date:12/17/2016 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:EDPW
Reached Total Depth 2015-01-15 Rose Run plugged back to Utica.
Plugged Back 2015-05-22 Rose Run plugged back to Utica.
Completion Report Received 2015-09-22 Rose Run plugged back to Utica.
Construction Permit Expires 2015-12-18 Rose Run plugged back to Utica.
Record Last Modified 2017-10-23 Rose Run plugged back to Utica.

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2015-09-23 5910 6026 70
2015-09-23 6866 6878 48
5910 6026 70
6866 6878 48
5910 6026 70

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 08/26/2015 08/26/2015 7011 243516 0
2 05/15/2015 05/15/2015 7011 6150 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Unislick ST50 CESI Friction Reducer Alcohols, ethoxylated 68002-97-1 5 0.00446773 96.86
Alcohols, ethoxylated 68439-50-9 5 0.00446773 96.86
Alcohols, ethoxylated 68551-12-2 5 0.00446773 96.86
Petroleum Distillates, Hydrotreated Light 64742-47-8 30 0.0268064 581.162
Ammonium Acetate 631-61-8 13 0.0116161 251.837
Water Hilcorp Carrier/Base Fluid Water 7732-18-5 100 93.7333 2,032,140.0
Cla Check G Shrieve Clay Stablizer Water 7732-18-5 15 0.00767793 166.458
Propietary non-harardous salt NA 75 0.0383896 832.289
K-Bac 1020 WST Biocide 2,2-Dibromo-3-nitrilopropionamide 10222-01-2 20 0.00480376 104.146
Polyethylene Glycol 25322-68-3 50 0.0120094 260.364
Water 7732-18-5 30 0.00720564 156.218
Sand (Proppant) Sargent Proppant Silica 14808-60-7 99.9 6.06403 131468
Scale Hib A Nalco Scale Inhibitor Triethanolamine Tri(Phosphate Ester), Sodium Salt 68171-29-9 30 0.00960751 208.291
Ethylene Glycol 107-21-1 30 0.00960751 208.291
2 NDL-100 UWS Fluid Loss Additive Toluene 108-88-3 60 0.380702 247.847
Xylene 1330-20-7 60 0.380702 247.847
Isopropyl alcohol 67-63-0 40 0.253802 165.231
Ethylbenzene 100-41-4 30 0.190351 123.923
Water Hilcorp Carrier/Base Fluid Water 7732-18-5 100 78.8323 51321.8
Unihib G GeoSafe Acid Inhibitor Ethoxylated alcohol 68002-97-1 35 0.012517 8.149
Thiourea 62-56-6 1 0.00035763 0.233
Formaldehyde 50-00-0 1 0.00035763 0.233
Methanol 67-56-1 5 0.00178815 1.164
Short chained glycol ether 112-34-5 60 0.0214578 13.97
Acetophenone 98-86-2 1 0.00035763 0.233
Hydrochloric Acid (20%) Axiall Acidizing Hydrogen Chloride 7647-01-0 20 3.9993 2603.64
Acid Pensurf UWS Acid Penetrant Dodecylbenzenesulfonate isopropanolamine 42504-46-1 20 0.00481967 3.138
Other components below reportable levels NA 40 0.00963933 6.275
2-ethylhexanol 104-76-7 60 0.014459 9.413
I-7L UWS Iron Control Agent Ethylene Glycol 107-21-1 20 0.0953679 62.087
Triethenolamine hyrdoxyacetate 68299-02-5 20 0.0953679 62.087
Glycolic Acid 79-14-1 2.5 0.011921 7.761

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2015-08-26 H2O 0 5908 Bbl 139800 Universal Well Services Inc. Universal Well Services was the frac company for this stimulation. 1000 gallons of 15% HCl acid was spotted on this well the day before. Breakdown was achieved at 2602psi and the average treating pressure was 3469psi at 54.1 barrels per minute (bpm) with a maximum of 58.4bpm. A volume of 5908bbls were pumped in the job, 4897 barrels of which were for treatment. The instant shut in pressure was 1335psi, 5 minute 1254psi and 10 min shut in pressure 1214psi. The well was shut in and will be flowed

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2015 DISCOVERY OIL AND GAS 0.00 92.00 60
2016 DISCOVERY OIL AND GAS 2128.00 606.00 200
2017 DISCOVERY OIL AND GAS 0.00 454.00 120
2018 DISCOVERY OIL AND GAS 0.00 490.00 120

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2015 DISCOVERY OIL AND GAS Brine 1496 60
2016 DISCOVERY OIL AND GAS Brine 540 200
2017 DISCOVERY OIL AND GAS Brine 320 120
2018 DISCOVERY OIL AND GAS Brine 100 120

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1367814780 2015-1-27 0:00: PL No Violations 2.00
-1449681918 2015-9-14 0:00: PW No Violations 2.00
-1626995112 2015-3-18 0:00: SC No Violations 1.00
-1660216861 2014-12-29 0:00 DD No Violations 1.00
-273604465 2015-5-22 0:00: PB No Violations 4.00
-615861161 2015-1-14 0:00: UD No Violations 2.50
0014727221 2015-01-28 Preliminary Restoration No Violations I was on location to witness the final solidification of the drilling pits. 2 loads of solidification material have been brought on location and mixed by Daley Excavating in the blowing pits. There were a total of 6 loads used to solidify the pits. The pits are firm and have no free liquid on them. The pits will be fully closed tomorrow.
0183966504 2015-08-26 Completion Testing No Violations I was on location to witness the slick water hydraulic fracturing of the Point Pleasant/Utica formation for this well. Universal Well Services was the frac company for this stimulation. 1000 gallons of 15% HCl acid was spotted on this well the day before. Breakdown was achieved at 2602psi and the average treating pressure was 3469psi at 54.1 barrels per minute (bpm) with a maximum of 58.4bpm. A volume of 5908bbls were pumped in the job, 4897 barrels of which were for treatment. The instant shut in pressure was 1335psi, 5 minute 1254psi and 10 min shut in pressure 1214psi. The well was shut in and will be flowed back on 8/27/2015 when the Universal frac equipment has been removed from location. Please see stimulation report for more details.
0273604465 2015-05-22 Plug / Plug Back No Violations I was on location to witness the plugging back of this well from the Rose Run formation to the Utica/Point Pleasant formation. J Well Service Inc was on site to plug--
0615861161 2015-01-14 Urban Drill / Deepen / Reopen No Violations I was on location to check the status of the Wildcat drilling the 7.875 hole. The rig switched to drilling on 9.5ppg fluid at 5400 due to the significant gas shows that have occurred. Urban drilling requires the switch to the fluid drilling when significant gas shows are encountered. The rig will drill on fluid until the rig reaches total depth.
0733401240 2015-01-05 Surface Facility Construction No Violations I was on location to check the status of digging the pits. The heavy rain that occurred during the new year holiday has flooded the location. Currently several pumps are pumping the location dry of the fresh water that has accumulated on location. The water will continue to be pumped off location until the location is dry and the pits can be lined. Once this has occurred the rig will drill the mouse hole and start drilling their 22 diameter hole to 120.
0783401965 2015-02-05 Preliminary Restoration No Violations I was on location to check the status of closing the pits. The pits have been fully solidified and dirt has been graded over the location. Full restoration will be completed when the location thaws out and complete dirt work can be completed.
1367814780 2015-01-27 Preliminary Restoration No Violations I was on location to check the status of the closing of the pits for this well. Daley Excavating is on location mixing the pits. Chemtech has brought in 4 loads of solidification materials. The working pit has been solidified, but the blowing pits will need an additional 2 loads of material brought in for solidification. These loads will be brought in tomorrow and solidification will be complete.
1381896878 2015-04-15 Preliminary Restoration No Violations I was on location to check the status of reclaiming this location and preparing it for stimulation. The location is not flooded but is wet at this time. The silt fencing is intact on location and there are no signs of erosion. The well is shut in and a 500bbl tank is on location. Discovery is waiting for the location to be dry before the well will be stimulated.
1420561061 2015-01-06 Casing String Witnessed No Violations I was on location to witness the cementing of the conductor casing. The Wildcat rig drilled a 22 diameter hole to 117 and installed 115 of 16diameter casing. Petroset pumped 365sks of Class A cement with 3% CaCl and .5 lb/sk celloflake. It was displaced with 25bbls of freshwater and circulation was established during the entire job. Cement returns to surface were not obtained. Sakrete was brought onto location and the conductor hole was topped off until the water was displaced and the sakrete was brought to surface. The rig will wait on cement for 8 hours before drilling the 11 diameter hole.
1420643383 2015-01-07 Urban Drill / Deepen / Reopen Violations Noted I was on location to witness the cementing of the 11.75 diameter surface casing for this well. The Wildcat drilling rig drilled a 14.75 diameter hole to 462 and installed 445 of 11.75 diameter casing into the wellbore with 4 centralizers. At 9:30am, while the drilling rig was circulating the casing bottoms up with the mud pump using fluid from the drilling pits to condition the hole for cementing the surface casing, I took a sample of the fluid circulating through the casing and from the borehole. I field tested the sample using a Hach Quantab, bottle #4190, and the chloride level was above the detection range of the Quantab (over 6396 ppm). I also field tested the pH with a test strip, and noted a pH of approximately 9.0. I contacted Regional Supervisor Tom Hill to discuss my findings. Discovery Oil and Gas was allowed to cement the surface casing as soon as possible and use the Class A cement to displace the brine out of the hole. Petroset pumped 340sks of Class A with 3% CaCl and 0.5 lb/sk celloflake. The cement slurry was displaced with 52bbls of water, and 10bbls of cement returned to surface. The rig will wait on cement 8 hours before drilling the 11 diameter hole. Surface holes drilled into the USDW (underground source of drinking water) shall only be drilled on air, fresh water or freshwater based mud, per OAC 1501:9-1-08(C)(1). Consequently, a compliance notice is issued under ORC 1509.22(A). The samples taken of the circulating fluid have been submitted to the ODNR Environmental Laboratory for analysis.
1421084373 2015-01-08 Casing String Witnessed No Violations I was on location to witness the cementing of the intermediate casing. The Wildcat drilling rig drilled a 11 diameter hole to 1045 and installed 1025 of 8.625 diameter casing with 6 centralizers. Petroset pumped 335sks of Class A cement with 3% CaCl and .5 lb/sk celloflake. It was displaced with 63bbls of freshwater and 8bbls of cement were returned to surface. The rig will wait on cement for 8 hours before drilling the 7.875 diameter hole.
1421938080 2015-01-17 Casing String Witnessed No Violations I was on location to witness the cementing of the 4.5 diameter production casing. Wildcat drilled a 7.875 diameter hole to a depth of 7025 and installed 7011 of 11.6 lb/ft 4.5 diameter casing to 7011. A two stage DV tool was installed in the casing at 4456 and 30 centralizers were installed on the casing. For stage 1 Universal pumped a lead cement slurry of 200sks Unipro 171 and a 150sk slurry of Special Rose Run Cement. The cement was displaced with 108bbls of brine. The bomb was dropped to open the 2 stage DV tool and waited on for 30 min for it to engage. The DV tool was pressured up to 1500psi to open the ports. For stage 2 Universal pumped a 300sk 50/50 poz cement slurry with 2% gel, 10% salt, .5% TI-2, .5% CFL-2. The cement was displaced with 69bbls of brine. The Wildcat rig will be heading to the yard to have work completed on it.
1449681918 2015-09-14 Production Wells No Violations I was on location to check the status of putting this well into production. The 2.375 diameter tubing has been swabbed and the well has had rods installed. The wellhead and polishing have been installed and the well is shut in. Six frac tanks are on location and have been cleaned and are awaiting removal. A pumpjack will be installed on the well and the Utica Point/Pleasant formation will be produced. There are no violations at this time.
14727221 2015-1-28 0:00: PL No Violations 2.00
1626995112 2015-03-18 Surface Facility Construction No Violations I was on location to check the progress of preparing the location for stimulation. The location is currently flooded and drainage ditches are being dug to allow water to flow from the location. The flow lines for the well have been currently installed to the tank battery and are awaiting completion of the well. There are no violations a this time.
1660216861 2014-12-29 Drill / Deepen / Reopen No Violations I was on location to check the status of this well drilling. The rig has spudded the well but is not going to continue drilling until after the new year. The pits have not been dug and the crew is currently working on the rotary table. There are no violations at this time.
183966504 2015-8-26 0:00: CT No Violations 5.00
733401240 2015-1-5 0:00:0 SC No Violations 1.50
783401965 2015-2-5 0:00:0 PL No Violations 1.00

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1420643383 US-OH-112295 2016-07-26 9-1-07 Drilling operation causing pollution and contamination
1420643383 US-OH-112296 2015-03-04 Well operation causing pollution and contamination

For data sources see[10]