If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-133-24113 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.05,"lon":-81.17,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Portage | |
Municipality: Atwater Township | |
Operator Name: PIN OAK ENERGY PARTNERS LLC | |
Well Pad ID: | |
Farm/Lease Name: MCKNIGHT # 2-RR | |
License Status: Producing | |
License Date: 1997-04-21 | |
Spud Date: 1997-04-28 | |
Spud Drilling Contractor: PEP DRLG | |
Final Drill Date: 1997-05-09 | |
Well Total Depth: 7477.00 ft | |
Configuration: Vertical | |
Latitude: 41.050000 | |
Longitude: -81.170000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
Oil and Gas | 1997-04-21 | Issued Date 4/21/97 Expired Date 4/21/98 Acres 0040000 Tool Type RTAF Proposed Formation ROSE RUN Proposed Depth Proposed Drill Depth |
Original Spud | 1997-04-28 | RBDMS Rec |
Completed | 1997-05-09 | RBDMS Rec |
Reached Total Depth | 1997-05-09 | RBDMS Rec |
Completion Report Received | 1997-06-16 | RBDMS Rec |
Change of Owner | 2016-10-07 | Operator changed from 2050, ORION PETRO CORP to 9722, PIN OAK ENERGY PARTNERS LLC |
Record Last Modified | 2017-02-15 | RBDMS Rec |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
1997-08-18 | 7356 | 7362 | 3 |
7356 | 7362 | 3 | |
7366 | 7374 | 3 | |
7382 | 7388 | 3 | |
7392 | 7404 | 4 | |
1997-08-18 | 7382 | 7388 | 3 |
7356 | 7362 | 3 | |
1997-08-18 | 7392 | 7404 | 4 |
1997-08-18 | 7366 | 7374 | 3 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
H2O | 15 | 59220 Gal | 30300 | 1000 gal 15% HCL acid |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
1997 | ORION PETRO CORP | 49336.00 | 27358.00 | 0 |
1998 | ORION PETRO CORP | 21844.00 | 15990.00 | 365 |
1999 | ORION PETRO CORP | 22487.00 | 7648.00 | 365 |
2000 | ORION PETRO CORP | 14420.00 | 3717.00 | 365 |
2001 | ORION PETRO CORP | 8494.00 | 2323.00 | 365 |
2002 | ORION PETRO CORP | 12162.00 | 2097.00 | 365 |
2003 | ORION PETRO CORP | 14806.00 | 2084.00 | 365 |
2004 | ORION PETRO CORP | 16286.00 | 1608.00 | 365 |
2005 | ORION PETRO CORP | 11694.00 | 1126.00 | 365 |
2006 | ORION PETRO CORP | 9613.00 | 804.00 | 365 |
2007 | ORION PETRO CORP | 10272.00 | 750.00 | 365 |
2008 | ORION PETRO CORP | 7675.00 | 656.00 | 365 |
2009 | ORION PETRO CORP | 7366.00 | 764.00 | 365 |
2010 | ORION PETRO CORP | 5445.00 | 433.00 | 0 |
2011 | ORION PETRO CORP | 5598.00 | 457.00 | 0 |
2012 | ORION PETRO CORP | 4743.00 | 350.00 | 366 |
2014 | ORION PETRO CORP | 3530.00 | 224.00 | 365 |
2015 | ORION PETRO CORP | 3587.00 | 377.00 | 365 |
2016 | ORION PETRO CORP | 2127.00 | 143.00 | 273 |
2017 | PIN OAK ENERGY PARTNERS LLC | 370.00 | 0.00 | 365 |
2018 | PIN OAK ENERGY PARTNERS LLC | 354.00 | 0.00 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
1997 | ORION PETRO CORP | Brine | 4516 | |
1998 | ORION PETRO CORP | Brine | 3667 | 365 |
1999 | ORION PETRO CORP | Brine | 2844 | 365 |
2000 | ORION PETRO CORP | Brine | 2289 | 365 |
2001 | ORION PETRO CORP | Brine | 2033 | 365 |
2002 | ORION PETRO CORP | Brine | 3069 | 365 |
2003 | ORION PETRO CORP | Brine | 2673 | 365 |
2004 | ORION PETRO CORP | Brine | 2500 | 365 |
2005 | ORION PETRO CORP | Brine | 1907 | 365 |
2006 | ORION PETRO CORP | Brine | 1983 | 365 |
2007 | ORION PETRO CORP | Brine | 1706 | 365 |
2008 | ORION PETRO CORP | Brine | 1445 | 365 |
2009 | ORION PETRO CORP | Brine | 1692 | 365 |
2010 | ORION PETRO CORP | Brine | 1483 | 0 |
2011 | ORION PETRO CORP | Brine | 1546 | |
2012 | ORION PETRO CORP | Brine | 1344 | 366 |
2014 | ORION PETRO CORP | Brine | 1670 | 365 |
2015 | ORION PETRO CORP | Brine | 2200 | 365 |
2016 | PIN OAK ENERGY PARTNERS LLC | Brine | 0 | 365 |
2017 | PIN OAK ENERGY PARTNERS LLC | Brine | 50 | 365 |
2018 | PIN OAK ENERGY PARTNERS LLC | Brine | 18 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1449524817 | 2017-9-26 0:00: | PW | No Violations | 2.00 |
-1581424210 | 2005-3-14 0:00: | PW | No Violations | |
-1904592371 | 2017-9-19 0:00: | PW | No Violations | 1.30 |
-1942129359 | 2017-8-22 0:00: | PW | No Violations | 3.00 |
-1955951383 | 2017-9-20 0:00: | PW | No Violations | 0.90 |
-553393502 | 2017-10-20 0:00 | PW | No Violations | 0.60 |
-572267958 | 2017-8-28 0:00: | AM | No Violations | 0.50 |
0150689981 | 2003-04-01 | Production Wells | Violations Noted | Status check inspection - the well operation is causing pollution around the wellhead. The cause may have been stuffing box leak. There does appear to have been some attempt to clean up the spill. There is still impacted soil north and east of the wellhead. The tank battery for this well is in good condition. I contacted Buzz West with Orion to discuss the operation of this well. |
0209490726 | 2017-09-25 | Production Wells | No Violations | I was on location with DOGRM District Supervisor Steve Ochs to follow-up on Compliance Notice #-1942129359. A load of clean fill dirt has been dumped southwest of the tank battery. The two (2) 50 barrel, steel tanks have been steamed and are lying on their sides inside the tank battery. The 210 barrel tank has been steam cleaned and the vent stack has been removed. The well continues to sell natural gas and the chart at the sales meter was changed today. There is currently no activity on location. This violation continues. |
0380351055 | 2003-04-18 | Production Wells | No Violations | Pollution violation corrected. No other violations at this time. |
0426077298 | 2017-09-06 | Production Wells | No Violations | Follow-up to Compliance Notice #-1942129359. I extended the compliance date to 9/11/17 on 8/28/17 to accommodate the time required for soil testing to determine the proper disposal procedure. My inspection today found the location stable and no further migration of brine or oil away from containment. I will check back next week to see if remedial operations have commenced. This violation continues. |
0553393502 | 2017-10-20 | Production Wells | No Violations | Follow-up to Compliance Notice #-1942129359. My inspection found the tank battery has been rebuilt. The dump line from the separator has been plumbed to a 50 barrel tank. The dike walls on the west and north side of the battery have been rebuilt and the scalded areas outside of the dike have been remediated and seeded. New grass is beginning to re-establish in these areas. All the affected material has been removed and disposed of at Waste Managements American Landfill. This violation has been resolved. |
0572267958 | 2017-08-28 | Administrative Inspection | No Violations | I spoke with Pin Oak Operations Manager Ted Lawver today (8/28/17) concerning this well location and the time line for remedial activities. Ted told me that Lakeside would be taking soil samples this week for analysis to determine proper disposal procedures. He said that it would probably be 1-2 weeks before they receive the test results at which time they would proceed with clean-up operations. I have extended the remedy required date to 9/11/17. |
1051658821 | 2019-12-23 0:00 | PW | No Violations | 0.30 |
1449524817 | 2017-09-26 | Production Wells | No Violations | Follow-up to Compliance Notice #-1942129359. Lakeside Oilfield (Ron Hammen) was on location continuing with clean-up operations. The good 50 barrel tank was spotted on the other side of the lease road for later use. The bad 50 barrel tank was placed in the back of a dump truck and the 210 barrel tank was strapped to the trailer. Both tanks were removed for disposal at a scrap yard. They are going to steam the rock in the tank battery and push it to a sump where it will be vacuumed out tomorrow. This violation continues. |
1506531218 | 2017-09-27 | Production Wells | No Violations | I was on location to oversee clean-up operations in reference to Compliance Notice #-1942129359. Lakeside Oilfield was on location and dug a sump at the west end of the battery and steamed the rock with 250 gallons of freshwater. J. Hawk Water Hauling was sucking the fluid out of the sump with their water truck. I tested the water in the sump with a Quantab and found it was over 1000ppm chlorides. I requested that steaming continue with the remaining 250 gallons of water. After flushing again, I tested the water and found it below 300ppm chlorides and excavation and removal of saturated materials began in and outside of the containment dike. Lime was spread on all of the excavated areas to buffer any residual chlorides and clean top soil was replaced where the saturated materials had been removed. The dike walls were rebuilt and the foot print of the battery was shrunk down. I will check back later on progress. This violation continues. |
150689981 | 2003-4-1 0:00:0 | PW | No Violations | |
1525877287 | 2018-05-09 | Production Wells | No Violations | Status check inspection of this Rose Run Sandstone well. My inspection found the wellhead equipped with 2.375 tubing and rods and a natural gas powered pumping unit. The tubing valve is currently closed and the 4.5 production casing valve is open. This well produces to a diked tank battery to the north that was remediated in the fall of 2017 and vegetation has been well established around the perimeter of the battery that was previously impacted by salt water. The battery contains one (1) 50 barrel tank, a vertical separator, and an associated meter run. There is a line heater between the wellhead and tank battery that is no longer in use and a domestic tap and meter is plumbed to the flow line at this point. A gauge on the line heater indicates a pressure of 140psi. The required ID is posted at the tank battery. No violations. |
1581424210 | 2005-03-14 | Production Wells | No Violations | Status check inspection - no vioaltions at this time. |
1598979068 | 2020-9-1 0:00:0 | PW | No Violations | 0.50 |
1904592371 | 2017-09-19 | Production Wells | No Violations | Follow-up to Compliance Notice #-1942129359. My inspection today found that remedial activities have not yet been undertaken by Pin Oak Energy. The situation is static and there has been no further migration of the brine scald or oil inside containment. I spoke with operations manager Ted Lawver on Friday 9/15/17 and he told me that they finally received the results of the material testing and that they would begin remedial operations today or Wednesday 9/20/17. I will check back tomorrow to see if activities have started. This violation continues. |
1942129359 | 2017-08-22 | Production Wells | Violations Noted | Status check inspection of this Rose Run Sandstone well. My inspection found the wellhead equipped with a natural gas powered pumping unit. The well produces to a diked tank battery that contains one (1) 210 barrel tank, two (2) 50 barrel tanks, a vertical separator, drip bottle, and the associated meter run. There is a line heater between the wellhead and tank battery that is not in use. My inspection of the tank battery found an area measuring 18 wide and 30 long inside the central and north sides of the containment area that has been impacted by crude oil and brine. The rock is stained red and black and the staining reaches one (1) foot up the interior dike wall. There is coagulated crude oil sludge throughout and around the interior perimeter of the containment area. The western side of the containment area has standing water and thick, coagulated sludge. I ran a high range Quantab (Lot #5243) on a sample of the water. The Quantab unit value indicated 4.8 which corresponds to a chloride level of 1037ppm. Brine has migrated through and under the containment wall and impacted a 20x6 area on the north side, and 10x6 areas on the northwest and southwest corners. These areas have been scalded and are primarily devoid of vegetation. I spoke with Mark Van Tyne (Pin Oak Energy Partners), at 2:10pm, and informed him of my findings. I requested that the contaminated material be excavated and removed for disposal and the impacted areas be remediated. He said he is sending someone out to assess what remedial work will need to be done. Based on the appearance of the material inside the containment area and impact of the brine scalding damage, this was not a recent release and has been impacting the area in and around the tank battery for some time. DOGRM Emergency Response Coordinator Fred Rome arrived on location to assist me with the assessment. It had just rained and a high range Quantab was run in the standing water of a deer footprint in the 20x6 impact |
1955951383 | 2017-09-20 | Production Wells | No Violations | Follow-up to Compliance Notice #-1942129359. My inspection today found that remedial activities have not yet been undertaken by Pin Oak Energy. Ron Hammen from Lakeside Oilfield called this morning at 7:30am about starting clean-up operations at this location and the call was lost. They excavator is currently on location and the lease road has been graded and widened. I spoke with Ron again at 2:10pm and he will be in with the water truck in the morning to get the tank steamed out before moving it. I will check back on operations tomorrow (8/21/17). This violation continues. |
209490726 | 2017-9-25 0:00: | PW | No Violations | 0.50 |
380351055 | 2003-4-18 0:00: | PW | No Violations | |
426077298 | 2017-9-6 0:00:0 | PW | No Violations |
Inspection ID | Violation ID | Violation Date | Violation Code | Violation Comments |
---|---|---|---|---|
0150689981 | US-OH-114213 | 2003-04-06 | Well operation causing pollution and contamination | |
1942129359 | US-OH-119555 | 2017-09-14 | Well operation causing pollution and contamination |
For data sources see[9]