X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

34-105-23676

Well Details

Well ID: 34-105-23676
Loading map...
Country: United States
State: Ohio
County: Meigs
Municipality: Orange Township
Operator Name: MOUNTAINEER STATE OPERATIONS L
Well Pad ID:
Farm/Lease Name: BERNARD JAMES & ELNORA
License Status: Producing
License Date: 2011-03-02
Spud Date: 2011-09-12
Spud Drilling Contractor: MONROE DRILLING OPERATION, LLC
Final Drill Date: 2011-11-01
Well Total Depth: 1999.00 ft
Configuration: Vertical
Latitude: 39.130000
Longitude: -81.910000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2011-03-02 Proposed Formations:BEREA, Issued Date:3/2/2011, Expired Date:3/1/2013 12:00:00 PM, Drilling unit acres:10, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2011-11-01
Construction Permit Expires 2013-03-01
Completion Report Received 2015-10-08
Record Last Modified 2017-10-23

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2015-10-09 1840 1850 0
1840 1850 0
1840 1850 0

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 1200 Bbl 0 Universal Well Services Inc.

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2012 MOUNTAINEER STATE OPERATIONS L 919.00 1029.00 366
2013 MOUNTAINEER STATE OPERATIONS L 986.00 986.00 365
2014 MOUNTAINEER STATE OPERATIONS L 1933.00 900.00 365
2015 MOUNTAINEER STATE OPERATIONS L 283.00 186.00 365
2016 MOUNTAINEER STATE OPERATIONS L 440.00 162.00 365
2017 MOUNTAINEER STATE OPERATIONS L 1.00 0.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2012 MOUNTAINEER STATE OPERATIONS L Brine 1000 366
2013 MOUNTAINEER STATE OPERATIONS L Brine 9601 365
2014 MOUNTAINEER STATE OPERATIONS L Brine 5790 365
2015 MOUNTAINEER STATE OPERATIONS L Brine 0 365
2016 MOUNTAINEER STATE OPERATIONS L Brine 0 365
2017 MOUNTAINEER STATE OPERATIONS L Brine 0 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1066939574 2017-3-15 0:00: PW No Violations 1.00
-1151136903 2012-1-27 0:00: PW No Violations 0.50
-1213877429 2011-9-13 0:00: DD No Violations 3.50
-1853011790 2011-9-13 0:00: DD No Violations 3.50
-1996475733 2012-1-23 0:00: DD No Violations
-2064669775 2012-6-11 0:00: PL No Violations 0.50
-356720151 2011-9-19 0:00: DD No Violations 0.50
-878328239 2012-2-2 0:00:0 PW No Violations 1.00
0039964713 2011-09-07 Drill / Deepen / Reopen No Violations Predrilling site review with Tom Stone of Mountaineer State Oper LLC. Well appx 150 feet from driveway and 100 feet from barn.
0140602922 2012-02-23 Preliminary Restoration No Violations The pit is still open but being drained.
0193578895 2012-03-02 Preliminary Restoration No Violations The pits have been closed. The dozers are being moved to the next restoration.
0194341475 2012-02-13 Preliminary Restoration No Violations The pit is still open.
0356720151 2011-09-19 Drill / Deepen / Reopen No Violations Checking on pit level. Close to top due to rain, spoke with Tom Stone of Mountaineer State and will drain soon.
0745062078 2012-01-24 Production Wells No Violations Inspected well site with Josh Garland MRI and Gene Chini Oil and Gas Supervisor. Drill pit is open. Pit liner has fell into pit in multiple places. A 2 inch black plastic line has been installed between the drill pit and a 100 barrel steel production tank drain. The tank drain is equipped with a 2 inch valve, a 2 inch 90 degree elbow, a 2 inch clear plastic nipple, 2 inch steel hammer union connected to the 2 inch black plastic line that extends to the drill pit. Water was discharging from the 2 inch line into the pit. A sample was taken and sent to the lab for analysis. A High Range Quantab was placed in the discharge water and the brine exceeded 6797 parts per million chloride. Informed Tom Stone and John Kent of Mountaineer to stop discharging brine into the pit and to disconnect the 2 inch line. Also told Tom and John to pump out the pit and take the fluids to an approved salt water injection well for disposal. Then close the pit.
0878328239 2012-02-02 Preliminary Restoration No Violations The Frac Tank has been removed, the pits are still open, a water knock-out has been installed, and a second saltwater tank has been installed.
0911389177 2011-09-13 Annular Disposal No Violations John Kent called and scheduled a Annular Disposal Mechanical Integrity Test (Fresh Water Test) on the surface casing. Test pressure 365 psi. Tested three times and test failed each time. Last test had bubbles around casing at the surface. Last test lost 70 psi in 15 minutes.
0947368407 2012-02-27 Preliminary Restoration No Violations The smaller pit has been removed. The larger pit has been drained and is being closed.
1066939574 2017-03-15 Production Wells No Violations Well is equipped with pumping unit, tubing, rods and an electric motor. The valves on the tubing string were closed and the polish rod had a haze on it from lack of recent activity. There is a domestic meter at the wellhead. The tank battery consists of 3-100 barrel steel tanks, a vertical separator, chart and meter.
1149252533 2012-01-24 Preliminary Restoration Violations Noted Preliminary restoration inspection. The pit was full of water and the liner had fallen down in places. The liner shall immediately be pulled up back into place. All pits used for drilling shall be closed two months after completion of the well. A two inch line was being run from the 210 barrel salt water tank into the pit. At the time of inspection a small amount of fluid was draining from the line and samples were taken. A high range Quan-tab test strip was used to test for Chloride levels in the water coming diectly fro the line and 6797+ parts per million Chlorides were noted. The line running from the salt water tanks to the pit shall immediately be disconnected and removed.
1151136903 2012-01-27 Preliminary Restoration No Violations The lines are disconnected, the ball valves on the bottom of the tanks are closed, and the frac tank is going to be removed.
1213877429 2011-09-13 Drill / Deepen / Reopen No Violations Administer BOP test for Bernard 167. 500 psi required, hold pressure and loose no more than 5% pressure over 15 minuets. Three tests administered and each failed. BOP not a permit condition, owner running BOP voluntarily, so drilling will continue. Blowline only 30 feet, so I suggested lengthening it. 10 extra feet there on site, so line was extended.
1315845200 2011-09-12 Drill / Deepen / Reopen No Violations Drilling status check. Currently at 270 feet, 12 1/4 surface casing borehole. Pit liner in good shape and pit of sufficient size to hold anticipated water. Mud pump also on site.
1315939254 2011-09-13 Drill / Deepen / Reopen No Violations Met with J. Scott to administer fresh water surface casing test. 365 psi required to hold for 15 minuets. Failed test 3 times.
1316125020 2011-09-15 Drill / Deepen / Reopen No Violations Witnessed Longstring cement job. 85 sacks of class A with 200 lb gel, 25 lb flake, and 2 qt. polymer. 7 inch casing inside 8 3/4 borehole. Note: well is permited to 1900, TD was 1999. Spoke with Steve Opritza and allowed company to continue.
1329504836 2012-02-17 Preliminary Restoration No Violations The pit is being emptied by the operator.
1373987895 2012-02-06 Preliminary Restoration No Violations The pits have not been emptied.
140602922 2012-2-23 0:00: PL No Violations 0.50
1853011790 2011-09-13 Drill / Deepen / Reopen No Violations Witnessed surface cement job. 727 feet of new 9 5/8 cemented in 740 feet of 12 1/4 borehole. 100 sacks of 1 % gel ran ahead and 180 sacks of neat ran behind. 400 lb gel, 700 lb accelerator, 180lb LCM, and 2 qt. polymer. Circulation established, good cement returns, cement level stayed at top.
193578895 2012-3-2 0:00:0 PL No Violations 1.00
194341475 2012-2-13 0:00: PL No Violations 0.30
1996475733 2012-01-23 Drill / Deepen / Reopen No Violations Drill pit is open. Pit liner has fell into pit in multiple places. A 2 inch black plastic line has been installed between the drill pit and a 100 barrel steel production tank drain. The tank drain is equipped with a 2 inch valve, a 2 inch 90 degree elbow, a 2 inch clear plastic nipple, 2 inch steel hammer union connected to the 2 inch black plastic line that extends to the drill pit. Oil and Gas Supervisor Gene Chini is scheduled to see well site on 1-24-12.
2064669775 2012-06-11 Preliminary Restoration No Violations Area graded, seeded and mulcted, the pits are closed, and there is no erosion on site.
2105829179 2012-04-27 Preliminary Restoration Violations Noted Area has not been graded and vegetative cover has not been established. Area shall be graded and vegetative cover shall be established in order to prevent erosion.
39964713 2011-9-7 0:00:0 DD No Violations 0.50
745062078 2012-1-24 0:00: PW No Violations
911389177 2011-9-13 0:00: AD No Violations
947368407 2012-2-27 0:00: PL No Violations 0.80

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1149252533 US-OH-103886 2012-01-25 Failure to close drilling pits within two months
1149252533 US-OH-103887 2012-01-25 Unlawful use of pit for temporary storage of brine or other wastes
2105829179 US-OH-121535 2012-04-27 Failure to restore within six months

For data sources see[9]

References