Well Details

Well ID: 34-081-20746
Loading map...
Country: United States
State: Ohio
County: Jefferson
Municipality: Cross Creek Township
Operator Name: ASCENT RESOURCES UTICA LLC
Well Pad ID: US-OH-001521
Farm/Lease Name: MINGO S CRC JF
License Status: Producing
License Date: 2017-11-21
Spud Date: 2017-10-31
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2018-06-01
Well Total Depth: 23431.00 ft
Configuration: Horizontal
Latitude: 40.320000
Longitude: -80.740000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2017-11-21 Proposed Formations:UTICA/POINT PLEASANT, Issued Date:11/21/2017, Expired Date:11/21/2019 12:00:00 PM, Drilling unit acres:310.806, Proposed Well Type:OG, Proposed Well Class:EOUT
Correction to Well 2017-12-15 CORRECTION TO CASING PROGRAM.
Correction to Well 2018-03-09 CHANGE TO UNIT SIZE AND TARGET INFORMATION.
Reached Total Depth 2018-06-01
Correction to Well 2018-09-07 TAKE TARGET AS-DRILLED
Construction Permit Expires 2018-11-21
Record Last Modified 2019-06-05

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 08/13/2018 10/02/2018 9662 17,214,200.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Unihib G UPP Acid inhibitor Butyl diglycol 112-34-5 75 0.0002977 483.113
Methanol 67-56-1 5 0.00001985 32.208
Alcohols, C10-16, ethoxylated 68002-97-1 50 0.000198467 322.075
Formaldehyde 50-00-0 1 0.00000397 6.442
Thiourea 62-56-6 1 0.00000397 6.442
Unislick CST-LA UPP Friction reducer Oleic Acid Diethanolamide 93-83-4 3 0.00161095 2614.28
Hydrotreated Petroleum Distillate 64742-47-8 25 0.0134246 21785.7
Water 7732-18-5 55 0.0295341 47928.5
Sodium Chloride 7647-14-5 15 0.00805476 13071.4
CHEMPLEX-Polymer_00019 Trade Secret 25 0.0134246 21785.7
Ammonium Chloride 12125-02-9 2 0.00107397 1742.85
Polyoxyethylene Sorbitan Monoleate 9005-65-6 1 0.000536984 871.427
Alcohol Ethoxylate Surfactants 68551-12-2 3 0.00161095 2614.28
Scale Hib PE-18 UPP Scale Inhibitor Proprietary Scale Inhibitor Proprietary 30 0.0138515 22478.4
Other Chemical(s) Listed Above See Trade Name(s) List Ethylene glycol 107-21-1 20 0.00053052 860.937
Polyoxyethylene Sorbitan Monoleate 9005-65-6 1 0.000536984 871.427
Ammonium Chloride 12125-02-9 2 0.00107397 1742.85
Oleic Acid Diethanolamide 93-83-4 3 0.00161095 2614.28
Sodium Chloride 7647-14-5 15 0.00805476 13071.4
Thiourea 62-56-6 1 0.00000397 6.442
Hydroxyacetic acid 79-14-1 5 0.00013263 215.234
Hydrotreated Petroleum Distillate 64742-47-8 25 0.0134246 21785.7
Water 7732-18-5 55 0.0295341 47928.5
Alcohols, C10-16, ethoxylated 68002-97-1 50 0.000198467 322.075
Water 7732-18-5 44.3 0.00610172 9901.97
Polyethylene glycol 7732-18-5 50 0.00688682 11176
Methanol 67-56-1 5 0.00001985 32.208
Alcohol Ethoxylate Surfactants 68551-12-2 3 0.00161095 2614.28
Formaldehyde 50-00-0 1 0.00000397 6.442
HCL Acid (7.5%) UPP Acidizing Hydrochloric Acid 7647-01-0 7.5 0.0377531 61266.4
Sand UPP Proppant Crystalline Silica in the form of Quartz 14808-60-7 99.9 10.8484 17,604,900.0
Water Ascent Carrier/Base Fluid Water 7732-18-5 100 88.5207 143,653,000.0
K-Bac 1005 UPP Biocide Polyethylene glycol 7732-18-5 50 0.00688682 11176
2,2-Dibromo-3-nitrilopropionamide 10222-01-2 5.8 0.000793361 1287.48
Water 7732-18-5 44.3 0.00610172 9901.97
I-7L UPP Iron Control Ethylene glycol 107-21-1 20 0.00053052 860.937
Hydroxyacetic acid 79-14-1 5 0.00013263 215.234
Ammonium glycolate 35249-89-9 20 0.00053052 860.937

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2018-08-12 H2O 0 6947 Bbl 230000 Universal Well Services Inc. On the day of my inspection I witnessed Universal frac crew on location. ID to company men Brady and Wendall. Stage 1 was this well was completed on 8/12. Bottom perforation at 23289 and top perforation at 23182. Average rate was 76 barrels per minute and average pressure was 10600 with a maximum pressure of 11700. Breakdown pressure was 9625. ISIP was 5953 and 5 minute ISIP was 5516. 6947 barrels total fluid pumped. 36 barrels of 7.5% HCl. 230000 lbs of total sand. 50000 lbs 100 mesh and 18000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 ASCENT RESOURCES UTICA LLC 1328681 0 51
2019 ASCENT RESOURCES UTICA LLC 2932086 0 90

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 ASCENT RESOURCES UTICA LLC Brine 19838 51
2019 ASCENT RESOURCES UTICA LLC Brine 13005 90

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1127164516 2018-10-22 0:00 CT No Violations 1.00
-1164210043 2018-7-18 0:00: CT No Violations 1.00
-1422031380 2018-8-14 0:00: CT No Violations 1.00
-1491007610 2018-1-12 0:00: CS No Violations 6.00
-1539525082 2018-9-12 0:00: CT No Violations 1.00
-178861617 2018-9-18 0:00: CT No Violations 1.00
-182666666 2018-5-22 0:00: DD No Violations 1.00
-2129707828 2019-12-10 0:00 UL No Violations
-628296304 2018-8-7 0:00:0 CT No Violations 1.00
-772943949 2018-2-23 0:00: PL No Violations 1.00
-800788659 2018-5-8 0:00:0 DD No Violations 1.00
0178861617 2018-09-18 Completion Testing No Violations On the day of my inspection I witnessed Universal frac crew on location. This well is on stage 42/77. Stage 42 frac plug is at 16163, bottom perforation at 16152, and top perforation at 16011. Intermediate annualr pressure is 680 psi. Surface gauge not viewed as there was pressure on the lines for frac.
0182666666 2018-05-22 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Xtreme 802 drilling an 8.5 inch diameter hole at 13500 feet in the lateral section. No flare during my inspection. Mud weight is 13.6 ppg and company man anticipates it will be above 14 ppg before they reach total depth. Walk around location revealed no spills. Containment is functioning and pad drains are closed.
0329556620 2018-10-04 Completion Testing No Violations On the day of my inspection I identified myself to company man Justin. Frac crew has moved off of location and they are cleaning up the containment in preperation for drill out. 2 kill plugs set in well at 9000 and 9150. Surface annular pressure is 0 and intermediate annular pressure is 1500.
0566468178 2018-08-22 Completion Testing No Violations On the day of my inspection I witnessed Universal has a frac crew on location. ID to company man Chris Telford. Wireline is in this well currently and will set stage 19 frac plug at 20188 feet, bottom perforation at 20176 feet, and top perforation at 20037 feet. They are running 5 guns with 4 shots on 36 foot spacing. Surface annular pressure is 0 and intermediate annular pressure is 500.
0628296304 2018-08-07 Completion Testing No Violations On the day of my inspection I witnessed Universal frac crew moving onto location. ID to Company Man Bub Ruckert. Mr. Ruckert believes they will likely start stimulation operations on Saturday. There is an above ground storage tank onsite. Not all equipment is onsite this date. Surface annular pressure is 0 and intermediate annular pressure is 950. Company an said he would have the pressure bleed off when they get all rigged up.
0697015597 2018-07-26 Completion Testing No Violations On the day of my inspection I met with Company man Duke Landry. No frac crew is onsite yet. Miscellaneous equipment onsite such as aboveground storage tank and several frac tanks. Surface annular pressure is 0 and intermediate annular is 650.
0772943949 2018-02-23 Preliminary Restoration No Violations On the day of my inspection I found this pad containg four labeled wells. Wells have surface casing set in them and are awaiting a larger rig to finish. The pad is fenced, gated, and locked. All disturbed area is heavily mulched and doing well with all the rain the area has received over the past 2 weeks. Leas road also in good shape. Pad drains are shut. Site meets requirements of ORC 1509.072A for preliminary restoration.
0800788659 2018-05-08 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Xtreme 802 has skidded to the 4H but has yet to spud. Company man Heath was notified of oil off containment that I located. He stated that it was from a cement truck from the production casing job that blew a hose and they thought it was all cleaned up in the night. He stated he would make sure it was completely cleaned up.
0900363886 2018-05-16 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Xtreme 802 was on location but was not drilling due to top drive issues. 9.625 inch diameter casing was cemented and they have yet to drill out DV tool or casing shoe. Walk around of location revealed no issues with containment.
1004007775 2018-08-28 Completion Testing No Violations On the day of my inspection I witnessed a Universal frac crew on location. Identified myslef to company men Wendall Brady and Chris Telford. Stage 40 has been stimulated. There are 77 total stages. Plug was set at 16513, bottom perforations at 16502, and top perforations at 16361. Surface annular pressure is 0 and intermediate annular pressure is 700. 1000 gallons of 7.5% HCL pumped. Breakdown pressure was 7940 at 15 bpm. ISIP was 7129. Average pressure was 10408 with max pressure of 11715. Average rate was 70 bpm. Total clean volume pumped was 3091 barrels. 165630 lbs of sand pumped and it screened off. I did not witness this stage.
1127164516 2018-10-22 Completion Testing No Violations On the day of my inspection I found Deep Well snub #11 onsite. I identified myself to company man James Edwards. This well has had frac plugs drilled out and is awaiting flowback. Surface annular pressure is 400 and intermediate is 550. Production casing pressure was 3300 after drill out. James anticipates moving off of this pad late in the week.
1164210043 2018-07-18 Completion Testing No Violations On the day of my inspection I met with Company man Duke Landry. Frack stacks are on wells, an aboveground storage tank, and two frac tanks are onsite. Universal will be coming to this location after finishing the Elite pad. Surface annular pressure is 0 and the intermediate annular pressure is 500.
1422031380 2018-08-14 Completion Testing No Violations On the day of my inspection I witnessed Universal frac crew on location. ID to company men Brady and Wendall. Stage 1 on this well was completed on 8/12. Bottom perforation at 23289 and top perforation at 23182. Average rate was 76 barrels per minute and average pressure was 10600 with a maximum pressure of 11700. Breakdown pressure was 9625. ISIP was 5953 and 5 minute ISIP was 5516. 6947 barrels total fluid pumped. 36 barrels of 7.5% HCl. 230000 lbs of total sand. 50000 lbs 100 mesh and 180000 lbs 40/70 mesh. Stage 2 plug at 23162. Bottom perforation at 23152 and top perforation at 23011. Surface annular pressure is 0 and intermediate annular pressure is 730.
1491007610 2018-01-12 Casing String Witnessed No Violations On the day of my inspection I witnessed the surface casing cement job. Falcon 26 drilled a 17.5 inch diameter open hole to a depth of 1448 feet. Previous casing set and cemented was 30 inch diameter conductor casing to a depth of 100 feet. Wyoming casing ran 1441 feet of 13.375 inch diameter casing, j-55, 61 lbs/foot and a 3 foot stickup. Casing was centralized with 12 centralizers. Shoe track is 43 feet long. Halliburton was onsite with 1466 sacks of class H Neocem cement. Cement weighed with mudscale at 15.8 ppg and yield of 1.241. 50% excess ran in open hole. Cement displaced with 213 barrels of fresh water. 10 barrels of water pumped ahead of cement. 80 barrels of cement returned to surface, and floats held with 1 barrel back to truck.
1539525082 2018-09-12 Completion Testing No Violations On the day of my inspection I witnessed a Universal frac crew on location. Identified myself to company man Gonzo.No changes have occurred on this well since my last inspection on 8/28. Stage 40 was shut down early due to pressurring up. Surface annular pressure is 0 and intermediate is 600 psi.
1701812653 2018-09-25 Completion Testing No Violations On the day of my inspection I witnessed a Universal frac crew on location. Identified myself to company men David and Gonzo. This well is on stage 59/77. Stage 59 was just perforated and wireline is coming out of the well. Plug set at 13188, bottom perforation at 13176, and top perforation at 13036. Surface annular pressure is 0 and intermediate is 600.
329556620 2018-10-4 0:00: CT No Violations 1.00
566468178 2018-8-22 0:00: CT No Violations 1.00
697015597 2018-7-26 0:00: CT No Violations 1.00
900363886 2018-5-16 0:00: DD No Violations 1.00

For data sources see[9]