34-067-21310

Well Details

Well ID: 34-067-21310
Loading map...
Country: United States
State: Ohio
County: Harrison
Municipality: Cadiz Township
Operator Name: ASCENT RESOURCES UTICA LLC
Well Pad ID: US-OH-000890
Farm/Lease Name: COBRA CDZ HR
License Status: Producing
License Date: 2014-03-12
Spud Date: 2014-04-01
Spud Drilling Contractor: NABORS DRILLING
Final Drill Date: 2015-08-01
Well Total Depth: 17621.00 ft
Configuration: Horizontal
Latitude: 40.280000
Longitude: -81.010000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-03-12 Proposed Formations:POINT PLEASANT, Issued Date:3/12/2014, Expired Date:3/11/2016 12:00:00 PM, Drilling unit acres:919.192, Proposed Well Type:OG, Proposed Well Class:
Reached Total Depth 2015-08-01
Correction to Well 2015-11-13 UPDATE TO TARGET AND TAKE-POINT INFORMATION FROM NEW PLAT.
Construction Permit Expires 2016-03-11
Completion Report Received 2016-04-11
Change of Owner 2018-10-15 Operator changed from 8870, HESS OHIO DEVELOPMENTS LLC to 9520, ASCENT RESOURCES UTICA LLC
Correction to Well 2018-10-19 CHANGE IN WELL NAME AND NUMBER (PREVIOUS NAME: CADIZ C #3H-11)
Record Last Modified 2018-10-19

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 12/27/2015 01/12/2016 8533 12,540,600.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 AP One U.S. Well Services, LLC Gel Breakers Ammonium Persulfate 7727-54-0 100 0.00064 748
Water Hess Corporation Base Fluid Water 7732-18-5 100 90.1432 104,588,000.0
HCL Acid (3% to 7.5%) U.S. Well Services, LLC Bulk Acid Water 7732-18-5 97 0.93324 1,082,790.0
Hydrogen Chloride 7647-01-0 7.5 0.08379 97213.2
WFRA-405 U.S. Well Services, LLC Friction Reducer Ethoxylated alcohol blend Proprietary 5 0.00608 7049.39
Anionic Polyacrylamide Proprietary 40 0.04861 56395.1
Sodium Chloride 7647-14-5 20 0.0243 28197.5
Water 7732-18-5 40 0.04861 56395.1
Petroleum Distillates 64742-47-8 20 0.01956 22699
Sand U.S. Well Services, LLC Proppant Crystalline Silica, quartz 14808-60-7 100 8.57609 9,950,380.0
SI-1100 U.S. Well Services, LLC Scale Inhibitor bis (hexamethylene) tramine penta

(methylene phosphonic acid) - phosphate acid

40623-75-4 10 0.00074 860.792
Copolymer of Maleic and Acrylic acid 26677-99-6 10 0.0003 353.299
hexamethylenediamine tetra (methylene phosphonic acid) 38820-59-6 10 0.00161 1871.29
Di Water 7732-18-5 80 0.01032 11976.2
2-Phosphonobutane 1,2,4 tricarboxylic salt 37971-36-1 10 0.00125 1448.38
Ethylene Glycol 107-21-1 40 0.00365 4229.11
Potassium salt of diethylene triamine

penta (methylene phosphonic acid)

15827-60-8 10 0.00087 1010.5
AI-301 U.S. Well Services, LLC Acid Corrosion Inhibitors Hydrogen Chloride 7647-01-0 10 0.00015 178.009
Coco amine 61791-14-8 5 0.00006000 70.5898
Methenamine 100-97-0 20 0.00035 408.193
Diethylene Glycol 111-46-6 30 0.00044 515.152
Polyethylene polyamine 68603-67-8 10 0.00013 154.53
K-BAC 1020 U.S. Well Services, LLC Anti-Bacterial Agent Deionized Water 7732-18-5 28 0.00247 2869.96
2,2-dibromo-3-nitrilopropionamide 10222-01-2 20 0.00433 5024.48
HVFR-Bx3 U.S. Well Services, LLC Friction Reducer Petroleum Distillate 64742-47-8 50 0.02855 33125.1
Suspending Agent 14808-60-7 3 0.00338 3925.94
Polyacrylamide 9003-05-8 50 0.05287 61342.8
Ethoxylated Alcohol Blend Proprietary 6 0.00444 5152.79

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 HESS OHIO DEVELOPMENTS LLC 1748731 20978 286
2017 HESS OHIO DEVELOPMENTS LLC 1328748 4876 364
2018 ASCENT RESOURCES UTICA LLC 641154 1225 335
2019 ASCENT RESOURCES UTICA LLC 148198 47 90

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 HESS OHIO DEVELOPMENTS LLC Brine 13430 286
2017 HESS OHIO DEVELOPMENTS LLC Brine 5462 364
2018 ASCENT RESOURCES UTICA LLC Brine 2573 335
2019 ASCENT RESOURCES UTICA LLC Brine 546 90

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1206446196 2014-7-17 0:00: CS No Violations 8.50
-1686202143 2019-9-5 0:00:0 PW No Violations 1.00
-1912063210 2014-7-30 0:00: DD No Violations 1.50
-676158812 2018-11-7 0:00: PW No Violations 1.00
-848987429 2014-7-28 0:00: DD No Violations 3.00
0119820909 2014-07-10 Casing String Witnessed No Violations I am on site today to witness the running and the cementing of the 24 inch diameter casing string. HAD Drilling Rig # 690 drilled a 28.5 inch diameter hole to 340 ft and set 312 ft of 186.44 lb casing. Halliburton Energy Service is on site to cement the casing with 515 sacks of class A cement at 15.6 lb and a yield of 1.20 circulated cement to surface.
0156723233 2016-05-06 Production Wells No Violations I arrived on location, were I witnessed the lease road gate was locked and the lease road in adequate condition. The pad is fenced and all man doors were locked. The permitted well is producing off of natural reservoir pressure. RBDMS production records indicate that the well is in producing order.
The production equipment on the pad consists of the following:

4 400 bbl. Production tanks 4 Producing wells 4 Sand separators

1 Combustor 1 Compressor

0240730871 2017-09-22 Preliminary Restoration No Violations On the day of my inspection I found the Cadiz C pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface casing pressure and 600 psi on intermediate casing. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Site passes preliminary restoration according to ORC 1509.072A.
0422470025 2014-07-29 Drill / Deepen / Reopen No Violations I am on site to witness the bond log on the bottom section of the Mine String which has just been installed. The log truck is late and could arrive any time over the next few hours or days. I advised that I needed a copy of the cement bond log if I did not witness it.
0526049221 2014-07-25 Drill / Deepen / Reopen No Violations I am on site today to meet with Kevin Toothman Company Man for Hess Ohio and Mike Roberts Drilling Superintendent. We are meeting today to talk about the best way to make sure that the bottom 50 ft of the Mine String be re- cemented. After conducting a pressure test after cementing the casing on 07/17/2014 it was discovered that the bottom 50 ft of cement was missing. It occurred after the casing could not be placed on bottom to shut of the u-tube effect when the valve was opened after cementing. The cement was moved up with the hydraulic pressure into the open mine void. The meeting today is to talk about using tubing to spot the bottom plug and increase the odds of it staying in place. The problem is not if the plug would be placed correctly but if the rig can run the tubing. It is not set up to run something that small.
0676158812 2018-11-07 Production Wells No Violations On the day of my inspection I found this pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface casing pressure and 300 psi on intermediate casing. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Pad is now owned by Ascent resources and named has changed to Ace.
0848987429 2014-07-28 Drill / Deepen / Reopen No Violations HAD Drilling Rig # 618 drilled out the cement from 420 ft. to 460 ft. and found it open to 645 ft. Halliburton Well Service is on site today to conduct a pressure test of the Mine String Casing cement from 0 to 660 ft. The well has been pumped up to 300 PSI and it has held. I am not sure that the cement which has been drilled out has not blocked off the bottom of this shoe. Because I am not sure that there is cement on both the top annulus and the bottom annulus space between the casing a cement bond log will need to be completed to show cement has covered this section and that the mine water has been contained.
1186539838 2014-04-03 Drill / Deepen / Reopen No Violations HAD Drilling Rig # 680 is drilling at 80 feet and are down for repairs. They plan to drill and set casing at 100 ft..
119820909 2014-7-10 0:00: CS No Violations 4.00
1206446196 2014-07-17 Casing String Witnessed No Violations Onsite this date with Inspectors Mark Moreland, Randy Akins and Brandon Trigg to witness a mine string. HAD drilling has drilled a 22 open hole to a depth of 660 and set 660 of 18 5/8 casing on bottom. Mine void is from 600-610. Halliburton is onsite to cement the mine string. 150 sacks of class A (15.6 ppg; 1.21 yield) was used to cement below the mine leaving 40-50 of cement in the casing. Operator let the cement set up for 1 hour and began grouting the above the mine void using 420 sacks of cement. Casing was centralized and two cement baskets were on the casing at 590 and 570. Cement was viewed on the surface.
1208858844 2020-3-3 0:00:0 PW No Violations 1.00
1405604102 2014-07-17 Casing String Witnessed No Violations I am on site today to witness the running and cementing of the 18-5/8 inch diameter casing string. HAD Drilling Rig # 618 drilled a 22 inch diameter hole to 660 ft after hitting a mine shaft at 600 to 610 ft. Set casing with float shoe 50 ft below the bottom of the mine. Halliburton Energy will cement the bottom 50 ft with 150 sacks of class A cement at 15.6 lb and a yield of 1.21. There are 15 centralizers on the casing string and two cement baskets. The cement baskets are at 570 ft and at 590 ft. Used pea gravel to open cement baskets then Halliburton cemented the annular space from 590 ft to surface and cemented with 420 sacks of class A which had good returns to surface
1405963695 2014-07-17 Casing String Witnessed No Violations On the date of inspection I accompanied ODNR Inspector Mark Moreland to witness the cementing of a mine string. Refer to Mark Morelands report for further details.
1406550273 2014-07-28 Casing String Witnessed No Violations I am on site today to witness a pressure test on the 18-5/8 inch diameter casing string which was installed as a Mine String after hitting a shaft at 600 ft and the bottom of 610 ft. The casing has been cemented 07-17-2014 and after drilling out the cement the pressure test failed 07-18-2014. It was then cemented again 07-18-2014 and the cement was drilled out and the pressure test failed. Then it was cemented again 07-19-2014 and the cement drilled out and tested again today 07-28-2014 and the test did pass. I advised that a cement bond log be completed and verify that there is cement across this 50 ft section below the mine. After the cement bond log has been completed and the cement verified then drilling can continue. If cement is not in the 50 ft section below the mine then remedial cementing will be conducted until that section is cemented.
1438914176 2015-08-06 Casing String Witnessed No Violations I am on site tonight to witness the running and the cementing of the 9-5/8inch diameter casing string. Nabors Drilling Rig # 36 drilled a 12-1/4 inch diameter hole to 4799 ft. and set 4784 ft. of 40 lb. casing. Schlumberger Cementing Service cemented with 740 sacks of class H lead cement at 12 lb. and a yield of 1.91 and 340 sacks of 15.6 lb. class H cement with a 1.22 yield of tail cement and had 30 bbl. Of good cement returns to surface.
156723233 2016-5-6 0:00:0 PW No Violations 0.50
1912063210 2014-07-30 Drill / Deepen / Reopen No Violations HAD Drilling Rig # 618 has drilled out the cement from the 3 rd. cement job done on the bottom section of the Mine String 07/19/2014. They drilled out 10 ft. below the bottom of the casing which was set at 660 ft. to 610 ft. A cement bond log will need to be completed on that section before drilling can continue. A log truck is scheduled for today.
240730871 2017-9-22 0:00: PL No Violations 1.00
422470025 2014-7-29 0:00: DD No Violations 1.50
526049221 2014-7-25 0:00: DD No Violations 2.00

For data sources see[8]

References