Well Details

Well ID: 34-067-21057
Loading map...
Country: United States
State: Ohio
County: Harrison
Municipality: Archer Township
Operator Name: CHESAPEAKE EXPLORATION LLC
Well Pad ID: US-OH-000597
Farm/Lease Name: NORTH AMERICAN COAL ROYALTY CO BUELL
License Status: Plugged Back
License Date: 2010-11-17
Spud Date: 2010-12-14
Spud Drilling Contractor: NOMAC DRILLING CORP
Final Drill Date: 2011-01-24
Well Total Depth: 8845.00 ft
Configuration: Vertical
Latitude: 40.350000
Longitude: -81.010000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2010-11-17 Proposed Formations:TRENTON-BLACK RIVER, Issued Date:11/17/2010, Expired Date:11/16/2012 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:O
Correction to Well 2010-12-23 CORRECTION TO FOOTAGE, SHOULD BE "1427'NL & 1786'WL OF SEC. 10".
Reached Total Depth 2011-01-24
Completion Report Received 2011-05-05
Change of Owner 2011-12-22 Operator changed from 8705, OHIO BUCKEYE ENERGY LLC to 8756, CHESAPEAKE EXPLORATION LLC
End of Confidential Data 2012-01-24
Construction Permit Expires 2012-11-16
Record Last Modified 2015-09-24

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2011-11-21 10818 11120 60
2011-11-21 14058 14360 60
2011-11-21 13702 14000 60
2011-11-21 14778 15080 60
2011-11-21 14418 14720 120
2011-11-21 13338 13640 60
2011-11-21 12258 12560 60
2011-11-21 11898 12204 120
2011-11-21 12978 13280 60
2011-11-21 12624 12920 60
2011-11-21 10458 10756 60
14778 15080 60
14058 14360 60
14418 14720 120
13702 14000 60
13338 13640 60
12978 13280 60
12624 12920 60
12258 12560 60
11898 12204 120
11538 11840 60
11184 11480 60
10818 11120 60
10458 10756 60
10098 10400 60
9734 10040 60
9378 9680 60
9018 9326 60
8662 8960 60
8662 8960 60
2011-11-21 11538 11840 60
2011-11-21 11184 11480 60
2011-11-21 10098 10400 60
2011-11-21 9018 9326 60
2011-11-21 8662 8960 60
2011-11-21 9734 10040 60
2011-11-21 9378 9680 60

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
0 0 0

For data sources see[4]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2011 CHESAPEAKE APPALACHIA LLC Brine 8937 198
2012 CHESAPEAKE EXPLORATION LLC Brine 3597 341
2013 CHESAPEAKE EXPLORATION LLC Brine 1825 296
2014 CHESAPEAKE EXPLORATION LLC Brine 1699 257
2015 CHESAPEAKE EXPLORATION LLC Brine 892 185
2016 CHESAPEAKE EXPLORATION LLC Brine 1984 366
2017 CHESAPEAKE EXPLORATION LLC Brine 1218 339
2018 CHESAPEAKE EXPLORATION LLC Brine 11513 112
2019 CHESAPEAKE EXPLORATION LLC Brine 4564 90

For data sources see[5] [6]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1130930142 2010-12-8 0:00: DD No Violations 2.00
-1716749415 2020-7-21 0:00: PW No Violations 1.00
-203622287 2016-2-10 0:00: PW No Violations 1.50
-400252182 2016-2-24 0:00: PL No Violations 0.50
-575373905 2017-9-22 0:00: PW No Violations 1.00
0203622287 2016-02-10 Production Wells No Violations On the day of my inspection, I witnessed the well head is equipped with a production tree that is tied into a flow line going to the production equipment. Production equipment for the well bore consisted of a line heater, sand trap and a gas production unit. Production equipment that was shared with permitted well numbers 34067213780000, 34067213790000, 3406721380000 and 34067213810000 included one gas compressor, a vapor recovery system, a gas combustor and 6 400bbl. production tanks. While I was on site I performed a visual inspection, were I found no signs of pollution or contamination.
0343873693 2014-01-17 Preliminary Restoration No Violations On the day of my inspection the site passed preliminary restoration according to 1509.072A.
0400252182 2016-02-24 Preliminary Restoration No Violations I arrived on location accompanied by inspector Mark Moreland, were I witnessed the lease road gate was locked and the lease road in adequate condition. The pad is fenced and all man doors were locked. The permitted well 34067213780000 34067213790000 34067213800000 34067213810000 and 34067210570000 are producing off of natural reservoir pressure. RBDMS production records indicate that the well is in producing order. Permitted well number 34067210670000 has not been drilled.
The production equipment on the pad consists of the following:

6 400 bbl. Production tanks 5 Producing wells 5 Sand separators

1 Horizontal heater-treater 1 combustor 1 low pressure separator/ Vapor recovery system 1 compressor The site passed preliminary restoration in accordance with ORC 1509.072 A.

0575373905 2017-09-22 Production Wells No Violations On the day of my inspection I found the Buell pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface or intermediate casing pressure. Production equipment on the pad includes five vertical seperators with gas production units, one heater treater, four line heaters, three 400 barrel steel condensate tanks, three 400 barrel steel produced water tanks,a compressor, vapor recovery system and a combustor. Tanks are in their own steel containment. Production records current in RBDMS.
1130930142 2010-12-08 Drill / Deepen / Reopen No Violations Inspection revealed that Nomac Drilling is moving on location and starting to rig up. They advised that the derrick should be on site tomorrow and should be finished rigging up sometime on Friday. They are hoping to be spudded late Friday night sometime. No violations at this time.
1535037705 2018-08-23 Production Wells No Violations On the day of my inspection I was checking on the well for idle well complaint number 5938. Well is currently shut in for SIMOPS. ID myself to facilities foreman Trevor Joilet. Current activity on pad is production equipment construction and installation. Drilling of 4 new wells on this pad started in december of 2017. The new wells have been stimulated and plugs drilled out. They have not been flowed back yet. Call to Chris Huey production foreman stated that flowback should start on 8-30 and he hopes to bring the 5 existing wells back online around mid september. I contacted Bobbye Grubich (330-325-1890) and informed her of the status. Complaint can be closed. This well does not appear to have a surface annular gauge and intermediate annualr pressure is 0.
1571684483 2019-10-11 0:00 PW No Violations 1.00
1827662996 2012-07-11 Preliminary Restoration No Violations DNR Inspector Mark Moreland and I were on site to conduct a preliminary restoration inspection of this production well. Our inspection revealed that the affected areas, not being utilized for the production of the well, have been successfully revegetated and there is no substantial erosion and sedimentation noted during this inspection. The Preliminary Restoration can be approved at this time. Note: Under restoration comments Pits Filled was not checked because there were no earthen pits used during the drilling and fracking of this well.
343873693 2014-1-17 0:00: PL No Violations 1.00
969553014 2020-7-21 0:00: PB No Violations 0.50

For data sources see[7]

References