34-055-22112

Well Details

Well ID: 34-055-22112
Loading map...
Country: United States
State: Ohio
County: Geauga
Municipality: Russell Township
Operator Name: CUTTER EXPLORATION INC
Well Pad ID:
Farm/Lease Name: PULJIC/EGER
License Status: Producing
License Date: 2009-11-06
Spud Date: 2009-12-18
Spud Drilling Contractor: POULSON DRILLING
Final Drill Date: 2009-12-30
Well Total Depth: 3850.00 ft
Configuration: Vertical
Latitude: 41.480000
Longitude: -81.350000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2009-11-06 Proposed Formations:CLINTON, Issued Date:11/6/2009, Expired Date:11/6/2010 6:00:00 AM, Drilling unit acres:41, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2009-12-30
Completion Report Received 2010-02-08
Construction Permit Expires 2010-11-06
Record Last Modified 2017-10-24

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2010-04-27 3659 3713 28
3659 3713 28
3659 3713 28

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 15 65000 Gal 45000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2010 CUTTER EXPLORATION INC 3731.00 852.00 365
2011 CUTTER EXPLORATION INC 6172.00 969.00 0
2012 CUTTER EXPLORATION INC 16127.00 962.00 366
2013 CUTTER EXPLORATION INC 6605.00 382.00 365
2014 CUTTER EXPLORATION INC 4115.00 434.00 365
2015 CUTTER EXPLORATION INC 2171.00 175.00 365
2016 CUTTER EXPLORATION INC 4828.00 498.00 365
2017 CUTTER EXPLORATION INC 274.00 4331.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2010 CUTTER EXPLORATION INC Brine 1588 365
2011 CUTTER EXPLORATION INC Brine 123
2012 CUTTER EXPLORATION INC Brine 197 366
2013 CUTTER EXPLORATION INC Brine 216 365
2014 CUTTER EXPLORATION INC Brine 25 365
2015 CUTTER EXPLORATION INC Brine 0 365
2016 CUTTER EXPLORATION INC Brine 48 365
2017 CUTTER EXPLORATION INC Brine 68 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1453213502 2010-1-7 0:00:0 DD No Violations
-1740090466 2013-7-12 0:00: UP No Violations
0378590049 2011-07-06 Preliminary Restoration No Violations Well head is a rabbit well. Man door to the well was locked. Fence is board on board. Tank battery is fenced with board on board. Spacing 35 inches between production tanks. Separator spacing is correct. Two 100Bbl, one poly tank and mechincal separator are in the battery. Dike is in good repair. Man door needs an extension there is a 23 inch gap between the bottom of the door and ground level. Fence has been painted green and the bottom board painted black. The well and the tank battery need an identification sign. Identification sign for the well is inside the fence on the ground. The tank is on an adjacent property owner. Company will be contacted, regarding repairs. Affected area from drilling has been reclaimed. Lease roads are stable. Both drives are private residential drives, no gates required.
0673702642 2009-12-28 Drill / Deepen / Reopen No Violations Drill depth 3526. Permit is posted in the dog house. Safety fence is up. Operator is losing pressure on the drill string. Eric Poulson was preparing to run a test to see if drill string has a crack in it. Eric was tying knots in pieces of twin, he said he will put them into the drill string the leak will cause the string to be sucked into it. If he sees an increase in pressure he will know that there is a crack in string. If crack is located, string will need to be tripped out and cracked drill collar replaced. Lease road was stable and in good repair. Operator was drilling on fluid. Pits were in good repair.
1054598502 2009-12-20 Drill / Deepen / Reopen No Violations On site for BOP test. Operator was tripping into the hole at the time of arrival. New 7 & 7/8 Smith bit is going to be used for the hole. Eric Poulson on site for BOP test, Eric reviewed system with me. Eric closed BOP and pressured to 800psi. Operator pressured drill string and hole to 350 psi, pressure held for 15min. BOP test pass. Silt fence is up. Safety fence is up. Operator is going to drill into the lime and shut down for holiday.
1061441738 2014-10-20 UrbanProduction Wells No Violations My inspection found no changes since my last inspection. No violations found.
1261161225 2009-12-18 Drill / Deepen / Reopen No Violations On site for pit construction and rig move on. Pits were dug into hard clay. No ground water encountered during digging of pits. Surface pit was completed, operator was preparing to line pit. Permit was in the dog house. Lease road is rock to the site. Location has had stone added for stability. Permit sign was at the entrance of the site. Drainage controls are not up. Walked property with Mr. Bajaksouzian property owner to the east of the well and part of the unit. He has a pond down slope of the site, minor amount of sediment has entered his pond from the site. Sediment plum 10x5 at the inlet of pond was noted. Drainage swales on Mr. Bajaksouzians property are starting to be cut by drainage from his property, also contributing to erosion. Mr. Bajaksouzian also stated the pond needs dipped. Mr. Bajaksouzian was concerned about drainage controls. I informed Mr. Bajaksouzian that drainage controls should already be in place. Spoke to Hugh Palmer reminded Hugh that drainage controls need to be up during the cutting of the site. Not after the rig has moved on. Reviewed drainage control plan with Hugh and landowner. Drainage controls will be installed today. Contacted Warren from J.R. Smail reminded him of the same thing.
1261500185 2009-12-19 Drill / Deepen / Reopen No Violations On site for surface cement, operator tripping drill string out at the time of arrival. Pits are in good repair. Permit is posted in the dog house. Fire extinguishers are in place. Safety fence is up on the west side of the pits. Lease road is stable and in good repair. Operator TD hole at 329 hole is 11 inch. Operator ran 310 of new 20lb 8 5/8 inch pipe, pipe set at 320 with landing joint. Operator broke circulation ran 1 bag of cotton seed hauls and 1 bag of gel ahead. Mixed cement and ran cement, during cementing pump pressured up to 500psi. Checked hole good circulation no explanation for pressure at this time. Operator displaced cement 6 bbl of good cement returned to surface. Surface hole was drilled on fresh water, source was the Chagrin River. No Berea drift was 209
1329240989 2012-02-07 UrbanProduction Wells No Violations The tank battery equipment spacing is correct. The well owner is adding on to the tank battery to be able to produce the Puljic #2 into this battery. I reminded them that the tank battery will need two man doors now that there are multiple wells and multiple production tanks in the battery. The operator is using high pressure fittings for the construction and installation of the new separator.
1453213502 2010-01-07 Drill / Deepen / Reopen No Violations Pits are in good repair. Safety fence is up around the pits. Pits will be closed Friday of this week. 25psi on the annulus.
1656510984 2011-01-05 UrbanPreliminary Restoration No Violations Well is a rabbit well. Well is fenced with board of board, man door was locked. Annulus is open. Lease road is stone, stable and erosion controlled. Landscaping is up around the well head. Tank battery; two 100Bbl production tanks, one 1500 gal poly tank and a mechanical separator. Charcoal filter, spark arrestors and pressure relief valves are in place. Four evergreen trees are planted on the east side of the battery. Lease road is stable, man door is locked. Additional board on board needs added to the bottom of the man door, there is a 15 inch gap between the bottom of the door and the ground. Board on board has been painted. Spacing is correct. No gate installed on the battery lease road, road is primary drive for home.
1740090466 2013-07-12 UrbanProduction Wells No Violations My inspection found the well to be equipped with a plunger lift unit. The annulus valve is open to a pop off valve and plumbed into the production tank. The well and tank battery are in good repair and are surrounded by a locked wooden fence. The tank battery consists of three 200 BBL production tanks, a 100 BBL production tank, two 50 BBL poly tanks, and two mechanical separators. The production tanks are vented through two 55 gallon charcoal filters and into spark arrestors. The proper identification is located on the tank battery and the wellhead. The lease road is in stable condition. The lease road and tank battery are being shared by permit number 2-2139.
1761343567 2009-12-09 Drill / Deepen / Reopen No Violations Mud and gravel has been cleaned off of the road.
1879053194 2016-07-15 UrbanProduction Wells No Violations I conducted an inspection on this well. The well is equipped with a plunger lift unit and the valves on the wellhead are open. The well is fenced but needs a new lock on the man door. The well also needs signage. The tank battery consisted of four, 100 BBL production tanks, two, 50 BBL poly brine tanks, and two mechanical separators. Production tanks had lightning protection and charcoal filters. The tank battery is diked and fenced. The tank battery is shared with well 22139. There is signage at the entrance to the wellsite, however signage should also be added at the well and tank battery. The lease access is stable. I called Mark Torpak of Cutter with regards to installation of additional signage at the well and tank battery.
2015242310 2009-12-09 Drill / Deepen / Reopen No Violations Operator is cutting and constructing site. Requested to Hugh Palmer and Warren road needs cleaned. Gravel and mud was on Fairmont road.
2017523439 2009-12-22 Drill / Deepen / Reopen No Violations No one on site at the time of inspection. Safety fence was up around pits and west side of the rig. Lease road was blocked with a dozer. Hole appeared static. Warren called after inspection. Drill depth is 2060 they are in the lime. Will be shut down till Dec. 26, 2009. He stated no gas at the end of the blow line.
378590049 2011-7-6 0:00:0 PL No Violations
673702642 2009-12-28 0:00 DD No Violations

For data sources see[9]

References