Well Details

Well ID: 34-055-22103
Loading map...
Country: United States
State: Ohio
County: Geauga
Municipality: Russell Township
Operator Name: PIN OAK ENERGY PARTNERS LLC
Well Pad ID:
Farm/Lease Name: RATAJCZAK UNIT
License Status: Producing
License Date: 2009-08-24
Spud Date: 2009-09-12
Spud Drilling Contractor: POULSON DRILLING
Final Drill Date: 2009-09-17
Well Total Depth: 3845.00 ft
Configuration: Vertical
Latitude: 41.480000
Longitude: -81.350000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2009-08-24 Proposed Formations:CLINTON, Issued Date:8/24/2009, Expired Date:8/24/2010 6:00:00 AM, Drilling unit acres:21.13, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2009-09-17

-28-09

Completion Report Received 2009-11-02

-28-09

Construction Permit Expires 2010-08-24

-28-09

Change of Owner 2019-04-29 Operator changed from 169, JAMES R SMAIL INC to 9722, PIN OAK ENERGY PARTNERS LLC
Record Last Modified 2019-04-29

-28-09

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2010-01-11 3648 3699 34
3648 3699 34
3648 3699 34

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 64000 Gal 50000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2010 CUTTER EXPLORATION INC 12244.00 135.00 365
2011 CUTTER EXPLORATION INC 9744.00 179.00 0
2012 JAMES R SMAIL INC 10094.00 114.00 366
2013 JAMES R SMAIL INC 5329.00 58.00 365
2014 JAMES R SMAIL INC 6638.00 57.00 365
2015 JAMES R SMAIL INC 7213.00 118.00 365
2016 JAMES R SMAIL INC 8296.00 123.00 365
2017 JAMES R SMAIL INC 8166.00 56.00 365
2018 JAMES R SMAIL INC 7541.00 119.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2010 CUTTER EXPLORATION INC Brine 146 365
2011 CUTTER EXPLORATION INC Brine 155
2012 JAMES R SMAIL INC Brine 40 366
2013 JAMES R SMAIL INC Brine 0 365
2014 JAMES R SMAIL INC Brine 66 365
2015 JAMES R SMAIL INC Brine 155 365
2016 JAMES R SMAIL INC Brine 157 365
2017 JAMES R SMAIL INC Brine 138 365
2018 JAMES R SMAIL INC Brine 152 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1208592689 2019-8-22 0:00: UP No Violations 2.80
-219522331 2009-9-24 0:00: DD No Violations
-746970715 2013-7-15 0:00: UP No Violations
-929149426 2011-7-6 0:00:0 PL No Violations
-947047047 2017-5-15 0:00: UP No Violations
0219522331 2009-09-24 Drill / Deepen / Reopen No Violations On site for status of pit solidification. Operator has added 3 loads of cement fines to the pits. Front pit has been backfilled and excavator was working on top of it, to complete solidification of back pit. Back pit was starting to firm up. Operator was finishing mixing 3rd load into it. Lease road was stable.
0339574608 2009-09-15 Drill / Deepen / Reopen No Violations Drill depth 2760 top of the salt, no show of gas during drilling, per driller Eric Poulson. Pits are in good repair. Silt fence is up and in good repair. Lease road is stable, site is dry. Safety fence is up around pits. Topsoil has been saved and stockpiled around site.
0746970715 2013-07-15 UrbanProduction Wells No Violations My inspection found the well to be equipped with a plunger lift unit. The annulus valve is open to a pop off valve. The well and tank battery are in good repair and are surrounded by a chain link fence. The tank battery consists of a 100 BBL production tank, a 35 BBL poly brine tank, and a mechanical separator. The production tank is vented through a 5 gallon charcoal filter and up into a spark arrestor. The proper identification is located on the tank battery and the wellhead. The lease road is in stable condition.
0929149426 2011-07-06 Preliminary Restoration No Violations Lease road is stable and made out of durable material. Fencing around tank battery and wellhead is correct. Spacing in tank battery is correct. Identification signs are posted on the tank battery and the wellhead. Man doors are locked. Landscaping is installed. Affected area from drilling has been reclaimed. Vegetation is established. 100Bbl, 1500 gallon poly and a mechincal separator are in the battery. Lease road is a primary residence driveway, no gate required. Zero psi on the annulus, 25psi pop off on the annulus.
0947047047 2017-05-15 UrbanProduction Wells No Violations During this inspection, the well was equipped with a plunger lift assembly and the valves on the wellhead were open. The well was fenced and had a locked man door. The production records for this well were up to date. The tank battery consisted of one 100 BBL production tank, one 35 BBL poly brine tank and a mechanical separator. Valves on the separator were open and the chart dated 5/9/17 showed production. The tank valves were equipped with flat plugs and the vent stack on the production tank was plumbed into a 5 gallon charcoal filte and topped with a spark arrestor. The tank battery was diked and fenced with a locked man door. Proper, legible signage was located at the well and tank battery. The lease access was stable. No violations observed.
1135612969 2009-12-29 Administrative Inspection No Violations E-mail from Warren Shoenfelt 5 day annulus test on the Ratajczak #1 = 0#
1294243125 2011-01-05 UrbanPreliminary Restoration No Violations Well is a rabbit well. Fence is 8 foot chain link with plastic slates, three strands of barbed wire on top of fence. Man door was locked. Annulus has 25psi pop-off on it and a pressure gauge, 2 psi on gauge. Tank battery 100Bbl production tank, 1500 gal poly tank and mechanical separator. Tank battery fence with 8 foot chain link and three strands of barbed wire. Dike is in good repair. Man door was locked. Lease road is stable and constructed out of rock. Landscape screening has been installed. Identification sign is at the entrance of the location and on the wellhead fence. Silt fence can be removed at this time. Site has been graded, seeded and vegetation is established. Lease road gate has not been installed, drive is primary drive for home. Lock on load line off of the 100Bbl tank. Charcoal filter, spark arrestor and low pressure relief valve have been installed.
1430168333 2019-9-5 0:00:0 PW No Violations 2.50
2093450475 2009-09-12 Drill / Deepen / Reopen No Violations On site for pit construction. Soil that pits were constructed in was hard clay, clay was dry. Operator was reminded to slope sides when constructing pits. Pits slope was near vertical. Lease road was stable. Drilling permit was in the dog house. Operator spudded well, at 60 operator was still in drift. Fresh water was being delivered onto site and pumped into fresh water tanks. Safety signs for no smoking, hard hat area were up. Permit sign was posted at the entrance to the site. Roy and Eric Poulson on site.
339574608 2009-9-15 0:00: DD No Violations

For data sources see[9]