34-055-22094

Well Details

Well ID: 34-055-22094
Loading map...
Country: United States
State: Ohio
County: Geauga
Municipality: Parkman Township
Operator Name: EXCALIBUR EXPLORATION INC
Well Pad ID:
Farm/Lease Name: CAMPELLONE
License Status: Producing
License Date: 2009-06-08
Spud Date: 2010-06-03
Spud Drilling Contractor: CAPSTAR DRILLING
Final Drill Date: 2010-06-08
Well Total Depth: 4351.00 ft
Configuration: Vertical
Latitude: 41.370000
Longitude: -81.090000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2009-06-08 Proposed Formations:NEWBURG-ORISKANY-CLINTON, Issued Date:6/8/2009, Expired Date:6/8/2010 6:00:00 AM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:POOL
Construction Permit Expires 2010-06-08
Reached Total Depth 2010-06-08
Completion Report Received 2010-07-19
Record Last Modified 2017-10-24

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2010-09-27 4141 4207 34
4141 4207 34
4141 4207 34

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 15 76559 Gal 50000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2010 EXCALIBUR EXPLORATION INC 0.00 0.00 0
2011 EXCALIBUR EXPLORATION INC 2089.00 324.00 334
2012 EXCALIBUR EXPLORATION INC 1729.00 207.00 366
2013 EXCALIBUR EXPLORATION INC 1285.00 222.00 365
2014 EXCALIBUR EXPLORATION INC 1384.00 243.00 365
2015 EXCALIBUR EXPLORATION INC 1515.00 168.00 365
2016 EXCALIBUR EXPLORATION INC 1715.00 118.00 365
2017 EXCALIBUR EXPLORATION INC 1202.00 96.00 365
2018 EXCALIBUR EXPLORATION INC 821.00 159.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2010 EXCALIBUR EXPLORATION INC Brine 468 0
2011 EXCALIBUR EXPLORATION INC Brine 886 334
2012 EXCALIBUR EXPLORATION INC Brine 366 366
2013 EXCALIBUR EXPLORATION INC Brine 513 365
2014 EXCALIBUR EXPLORATION INC Brine 422 365
2015 EXCALIBUR EXPLORATION INC Brine 371 365
2016 EXCALIBUR EXPLORATION INC Brine 200 365
2017 EXCALIBUR EXPLORATION INC Brine 281 365
2018 EXCALIBUR EXPLORATION INC Brine 255 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1109794292 2010-7-12 0:00: DD No Violations
-1778593731 2019-9-3 0:00:0 PW No Violations 0.70
-323216431 2011-7-26 0:00: PL No Violations
-829307504 2013-4-3 0:00:0 PW No Violations
-855829888 2010-6-4 0:00:0 DD No Violations
0323216431 2011-07-26 Preliminary Restoration No Violations There is a 1/2bbl of brine free adjacent to the wellhead. Brine is coming from the open annulus. Operator has been contacted; annulus needs a pop-off installed to prevent water from flowing from annulus. Brine needs removed from site. Brine tested had 6808ppm Cl-. Area needs repair seeding completed before preliminary restoration can be passed.
0829307504 2013-04-03 Production Wells No Violations My inspection found the well to be equipped with a pump jack. The annulus valve was closed. The well and tank battery are in good repair. The tank battery consists of four 210 BBL production tanks, four 100 BBL brine tanks, and four mechanical separators. The proper identification is located on the tank battery. The lease road is in stable condition. The lease road and tank battery are shared with permit numbers 2-2092, 2-2047, and 2-2048.
0855829888 2010-06-04 Drill / Deepen / Reopen No Violations On site for BOP test. Pits were in good repair. Lease road is soft but stable. Drainage controls along lease road are in place. Operator has placed silt fence and straw bails per my request at drainage discharge points along the lease road. BOP test: Start time 1427, 800 psi on BOP 200 psi on the hole. Test end time 1445, zero loss of pressure. Per Jim Dixon source of fresh water was hauled in.
1109794292 2010-07-12 Drill / Deepen / Reopen No Violations Pits have been filled. Annulus is open. Well has been fractured. Site has been rough graded. Drainage controls are in place along the service road.
1274402370 2010-06-08 Urban Drill / Deepen / Reopen No Violations The production casing was cemented. Cement operation and site conditions were acceptable.
1275925211 2010-06-04 Drill / Deepen / Reopen No Violations On site for surface cement. Hole #2: TD at 508 11 inch. Surface pipe: 8.625 new R-3 20lb pipe set open ended, 463 of pipe set at 475, 12 landing joint. No issues running pipe. Operator broke circulation ran 200lb of gel and one bag of hauls ahead of cement. 175 sacks of Class A 3% CaCl cement ran, 6 BBLs of good cement returned to surface. Cementing of CND was waived bedrock was at 20 feet. Operator did set 38 of New R-3 32lb pipe. Pipe was cemented during surface. Pits were in good repair. Lease road was stable. Operator has installed drainage controls along lease road. Fire extinguishers on the rig were in the green, but two years past inspection. Advised Jim Dixon to have extinguishers inspected. Hand rails around rig were up. Safety signs posted on the dog house.
1275937683 2010-06-02 Drill / Deepen / Reopen No Violations Site is under construction. Pits were clay with a shale bottom, had operator pack clay on the bottom of the pit to prevent cutting of the liner. Requested drainage controls be installed along the lease road and location to prevent off site erosion and sedimentation. First 300 of the lease is rocked and stable, remainder of the lease road is raw clay. Permit was in the dog house.

For data sources see[9]

References