Well Details

Well ID: 34-035-22084
Loading map...
Country: United States
State: Ohio
County: <County>
Municipality:
Operator Name: EOS ENERGY LLC
Well Pad ID:
Farm/Lease Name: CALLAS
License Status: Producing
License Date: 2008-11-24
Spud Date: 2008-12-16
Spud Drilling Contractor: H A D INC
Final Drill Date: 2008-12-21
Well Total Depth: 3661.00 ft
Configuration: Vertical
Latitude: 41.320000
Longitude: -81.710000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2008-11-24 Proposed Formations:OHIO SHALE TO CLINTON, Issued Date:11/24/2008, Expired Date:11/24/2009 6:00:00 AM, Drilling unit acres:27.1361, Proposed Well Type:OG, Proposed Well Class:
Reached Total Depth 2008-12-21
Completion Report Received 2009-09-08
Construction Permit Expires 2009-11-24
Correction to Well 2010-02-19 UNIT SIZE DECREASED TO 20.0146 ACRES.
Change of Owner 2018-07-31 Operator changed from 1249, CUTTER OIL COMPANY to 10185, EOS ENERGY LLC
Record Last Modified 2018-07-31

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2009-10-27 3407 3439 48
3407 3439 48
3407 3439 48

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
N2 0 200 Mscf 60000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2008 CUTTER OIL COMPANY 0.00 0.00 0
2009 CUTTER OIL COMPANY 5228.00 7882.00 321
2010 CUTTER OIL COMPANY 18695.00 10888.00 365
2011 CUTTER OIL COMPANY 27076.00 6747.00 365
2012 CUTTER OIL COMPANY 21190.00 3338.00 366
2013 CUTTER OIL COMPANY 18731.00 2738.00 365
2014 CUTTER OIL COMPANY 12879.00 1802.00 365
2015 CUTTER OIL COMPANY 7736.00 906.00 365
2016 CUTTER OIL COMPANY 5983.00 622.00 365
2017 CUTTER OIL COMPANY 5421.00 832.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2008 CUTTER OIL COMPANY Brine 785 0
2009 CUTTER OIL COMPANY Brine 848 321
2010 CUTTER OIL COMPANY Brine 197 365
2011 CUTTER OIL COMPANY Brine 995 365
2012 CUTTER OIL COMPANY Brine 103 366
2013 CUTTER OIL COMPANY Brine 75 365
2014 CUTTER OIL COMPANY Brine 107 365
2015 CUTTER OIL COMPANY Brine 81 365
2016 CUTTER OIL COMPANY Brine 93 365
2017 CUTTER OIL COMPANY Brine 41 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1150924309 2011-9-13 0:00: UP No Violations
-1163667383 2008-12-18 0:00 DD No Violations
-120189963 2015-2-10 0:00: UP No Violations 0.50
-1217489707 2014-7-10 0:00: UP No Violations
-1311830956 2017-11-8 0:00: UP No Violations 0.50
-1504966434 2018-3-22 0:00: UP No Violations 0.50
-1795397732 2011-8-30 0:00: UP No Violations
-1889410541 2020-2-6 0:00:0 UP No Violations
-1923575270 2019-5-1 0:00:0 UP No Violations
-293628551 2009-12-17 0:00 PL No Violations
-668862104 2017-4-27 0:00: UP No Violations 0.50
-705579455 2011-9-14 0:00: UP No Violations
-919928165 2011-9-9 0:00:0 UP No Violations
-973916699 2011-9-7 0:00:0 UP No Violations
0120189963 2015-02-10 UrbanProduction Wells No Violations I inspected this producing unit as part of routine inspection activity. The well and battery are located at the terminus of Mercury Drive. Theres is a short dedicated access road which travel west from the end of Mercury Drive, and curves slightly northward. The Callas 2 (#2-2084 is co-located with the Zilich (#2-2159) and share a common tank battery. The wellhead pump jack and battery are located in separate board-on-board enclosures. The enclosure gates are locked and signage is present. Observable fittings and connections are secure and free from signs of leakage. At the time of this inspection there is 12 to 15 inches of snow cover which limits my ability to inspect the condition of the lease road, interior of the battery containment, and other surficial features.
0293628551 2009-12-17 Preliminary Restoration No Violations on site with supervisor Cheslock. Checking area for permit conditions.
0616234565 2008-12-01 Drill / Deepen / Reopen No Violations crew working on location
0668862104 2017-04-27 UrbanProduction Wells No Violations I inspected this producing well location as part of routine inspection activity. At the time of this inspection, I noted the following: a wellhead with pump-jack system and associated tank battery in separate board-on-board enclosures. The battery is shared with the Zilich #2D, located on the same parcel. The enclosure gates were locked and secure. Fittings and connections at the wellhead were secure. The surface casing pressure was being monitored and showed no pressure. The electrical panel box w as locked and secure. Fittings and connections at the battery were secure. The load-line valves were plugged and locked. The tank lids were closed and sealed. The secondary containment drain was secure. The dedicated gravel-paved access road was level and dry. I did note some landscaping fabric debris in the parking area and I notified CJ Cutter about the need for removal of the debris. The entry gate was locked. I walked the areas surrounding the well and battery systems and observed the natural soils and vegetation to be free from signs of leaks, spills, or other adverse impact from the on-going production activity.
0705579455 2011-09-14 UrbanProduction Wells Violations Noted The excavation has water in the base of excavation no oil visable floating. Oil absobent pad floating on fluid all white.
Advised company to start to fill in the excavation with pea gravel then larger gravel.
0919928165 2011-09-09 UrbanProduction Wells Violations Noted Crew continued to keep oil absorbent booms replaced with new. Continued to work at the tank battery excavation keeping it free of water getting flow line cleaned. So the elbow can be replaced and additional rust protection along the flow line.
0973916699 2011-09-07 UrbanProduction Wells Violations Noted Cutters crew working at tank battery site vacuun out fluid in the excavation and changing the oil absorbent booms placed in creek to the east and the storm water basins along mercury drive .
1093996266 2018-01-26 UrbanProduction Wells No Violations I inspected this well as part of routine inspection. Fittings and connections at the well and battery (shared with the Zillich 2D) were secure and free from leakage or problems. Load lines were plugged and locked. Tank lids were closed. The secondary containment was intact and free from standing water, or signs of leakage of petroleum fluids. The individual enclosure gates were locked. Bonding and insurance were current. Production reports were current and up-to-date. The well was in production with active chart record. The shared-use access road was in good condition. I walked and inspected the areas surrounding the wellhead and battery and found the natural greenscape to be free from signs of impact or degradation.
1150924309 2011-09-13 UrbanProduction Wells Violations Noted inspected site to check site fluid (water) no oil floating on fluid.
1163667383 2008-12-18 Drill / Deepen / Reopen No Violations surface cementing
1217489707 2014-07-10 UrbanProduction Wells No Violations I inspected this producing unit as part of routine inspection activities. The wellhead which is currently fitted with a pump jack system is in operation. Production reports are current. System operation at the above-ground storage tank (AST) battery appears normal. Safety apparatus are present and I observed no signs of leaks, spills, or problems.
1311830956 2017-11-08 UrbanProduction Wells No Violations I inspected this well location as part of routine inspection activity. The well and associated battery are located on an otherwise undeveloped parcel at the end of Mercury Drive, and the battery is shared with the Zilich 2D well located on the same parcel. At the time of my inspection, the fittings and connections at the well were secure. The tank lids were closed and secure. The load-line valves were plugged and locked. The secondary containment was intact, with some water from recent rains. There was no signs of leakage (floating oil or sheen) visible. I walked and inspected the areas surrounding the wellhead and battery and found no signs or evidence of impacts or degradation. The access point was gated and locked with signage present. The access road was in good condition.
1315916607 2011-09-12 UrbanProduction Wells No Violations Witnessed pressure test on flowlines. Well pressured up to 1100 psi for 1 hour with no evidence of leakage from the flowlines or joints. Well to be put in production.
1316380792 2011-09-08 UrbanProduction Wells No Violations Crew continued to keep oil absorbent booms replaced with new. Continued to work at the tank battery excavation keeping it free of water getting flow line cleaned. So the elbow can be replaced and additional rust protection along the flow line.
1316437135 2011-09-04 Production Wells No Violations I received a call from CJ Cutter at 17:00 reporting oil on a creek just north of his Butcher well (PN 2180). Cutter checked his wells in the area and could not identify a source. I advised him to contact OEPA-DERR since water had been impacted. I met Cutter at the Butcher tank battery. The oil accumulated behind a debris dam (which acted like a siphon dam) located north of Butcher but appears to have originated upstream. We traced the oil upstream to a storm water drain discharge. The storm drains would need to be checked for impact to identify the source. Cutter called in employees and Moore Well Service to assist in containing and recovering the oil on the creek. Kurt Kollar with OEPA-DERR arrived on site and continued with the recovery and identifying sources which led to the Callas tank battery. Several week ago, oil was discovered outside of this tank battery and was being recovered with sump pumps placed in two recovery points. By this time, darkness had set in and it was agreed that source confirmation and recovery would continue in the morning with excavating and removing impacted material between the wells and the tank battery. A passing thunderstorm assisted in flushing the impacted creek. Product recover will continue into the night. Inspector Lowder will respond in the morning and will issue or extend the Compliance Notice for this well.
1340633025 2011-11-17 UrbanProduction Wells No Violations My inspection on this date was to conduct a final resolution to the previous report of 10/31/2011. Well site has been restored to requirements of 1501-9-9-05. All equipment and tanks have been removed. Well site is in compliance with laws and rules and this case file should be considered closed as of this date.
1354301864 2012-11-30 UrbanProduction Wells No Violations My visit to the well today was to witness replacement of pump due to insufficient pressure. Hagen Well Service pulled rods and tubing, replaced pump and reinstalled rods and tubing. Job began at 8:00 Am and was completed at 12:30 PM. ODNR did not witness total operation but was present at beginning and end of project. Cutter Oil to complete construction of protective fence next week and place well back in service.
1361723915 2013-10-28 UrbanProduction Wells No Violations The producing unit consists of a wellhead with pump jack and above-ground storage tank (AST) battery. The battery is comprised of 4 140-barrel steel production tanks, 2 50-barrel brine tanks and 2 separator units with Dominion metering run. The battery is shared with the #2159 unit. Both the wellhead and battery are enclosed in separate board-on-board fences. The gates and load-outs are locked. ID placard and secondary containment are good. Process safety gear (spark arrestor, low-pressure relief valve, carbon filter) is present. No problems noted.
1431609213 2015-05-06 UrbanProduction Wells Violations Noted I inspected the Callas # 2 on 5/6/2015. The well commenced production on 2/10/2009 and is current in reporting production to RBDMS. The access road is off of Mercury Rd. and has a cable gate restricting access. The lease road is graveled and affords adequate access. The required signage at the gate does not comply with 1501-9-9:05 OAC. The well is operated as a electrified pumping well. The well is fenced with a wooden plank fence. There is an earthen dike present. The required signage for the well head, again does not meet 1501-9-9:05 OAC. The door was locked and secure. The electrical control panel was unlocked as required by 1501-9-9:05. There is a chemical injection pump and supply drum located below the Sampsons post which is disconnected and is not being utilized at the time of this inspection. If the equipment will not be functional and essential for the production of the well the Operator shall removed it. The stuffing box had previously leaked and contaminated the ground below. There was not a access to the 8.625 annular space as required in the Special Permit Conditions attached to the drilling permit. Another permit condition was to log the entire wellbore, but the Big Lime interval was absent. There is a five (5) gallon bucket of oil and water located near the casing that needs to either be removed or emptied and covered to prevent accumulation. The tank battery ( shared with Zillich # 2-D ) takes up an area of 50 X 50 and is surrounded by a wooden plank fence and earthen dike. The signage on the tank battery is not compliant. The tank battery is void of the second access door. The equipment for the Callas # 2 included two (2) 140 barrel oil tanks, a 50 barrel poly brine tank, a horizontal mechanical separator, a Dom/ EOG gas measurement station and a electric powered natural gas compressor. The oil and brine load lines and electrical boxes were not locked. The oil storage tanks were equipped with tank lids with seals, but not fastened down to make
1435250514 2015-06-25 UrbanProduction Wells No Violations I inspected this well as a follow-up to a previous Compliance Notice. Load lines are now lock-protected. Tank lids are sealed and secure. Electrical boxes are locked and secure. Process safety gear, including spark arrestor is present. Secondary containment at the well and battery are intact. Oil containers have been removed. The low area of the containment berm have been corrected. Leakage at the brine leakage and oil staining have been corrected and mitigated. Update of signage is in progess. There have been reported complaints that storm drainage from the gravel-paved cul-de-sac at the end of Mercury Drive is causing gravel to wash into the local storm sewer. Reportedly, the cul-de-sac is part of the Callas property. Ive advised Cutter Oil to establish a management solution for the drainage. This work is in progress.
1476241895 2011-08-29 UrbanProduction Wells Violations Noted Phone call from Mayor Stefanik of oil deposits along the northern edge of graveled parking area of tank battery for two wells P#2059 callas and P# 2159 Zillich owned by CJ Cutter Oil Company. Met Fire Chief Mike Fabish at site found two areas 1) approximately 1 wide and 3long of dark stained soil and 2) a small patch of leafs coated with oil. Called company they arrived within the hour to remove these area. Excavated into the gravel approximately 18 the gravel was coated with oil. This material was removed and disposed of properly. With flow line exposed approximately 100-150 gallons of fluid was removed by a vacuum truck and put into the water tank inside the tank battery. The excavation was temporarily backfilled area with bark mulch with a sump pipe installed for access to evacuate any fluids that accumulated in excavation. will monitor site for any additional remediation needed.
1504966434 2018-03-22 UrbanProduction Wells No Violations I inspected this well location as part of routine inspection activity. The well and battery are located on an otherwise undeveloped parcel . At the time of my inspection, I found the following: wellhead with pump jack system and associated battery in separate board-on-board enclosures. The enclosure gates were locked and secure. The fittings and connections at the wellhead and battery were secure and free from problems. The tank lids were closed and secure. The interior of the battery, including secondary containment was free from free oil, staining, or other indications of spills, leaks, or problems. The battery is shared with the Zilich 2D. The electrical panels and load line valves were locked and secure. I walked and inspected the areas surrounding the well and battery and found no indications of impacts or problems relating to the on-going production activity. The shared-use access road was snow-covered by accessible.
1622556872 2011-10-11 UrbanProduction Wells No Violations My inspection on this date found the following: The tank battery and well head area have been repaired and no further leakage is detected. The overflow inspection pipe, located at the northwest corner of the tank battery, remains in place for observation purposes. The dike surrounding the well site has been restored to the requirements of 1501-9-9-05. The monitoring casing, located at 3694 Mercury Drive, remains in place. The sump system, located at the storm sewer in front of 3664 Mercury Drive, remains in place per the agreement between Cutter Oil and the City of North Royalton. Once the equipment and sump drains are removed, ODNR will do a preliminary restoration inspection of the well site per 1501-9-9-05 requirements.
1625518751 2011-09-06 UrbanProduction Wells Violations Noted Met with Kurt Kollar of OEPA he showed me what work was completed on Sunday 09-04-11 and Monday 09-05-11. Then proceed to meeting with City of North Royalton and OEPA to discuss the plans for remediation of the site.( Run a camera into the Storm Water Line along Mercury Drive. and to set up an Oil Separator in on tree lawn between address 3674 and 3664 Mercury Drive and to re-excavation that was excavated on 08-29-11to recheck the flow lines for leaks). Returned to site work started at the graveled parking area of the tank battery. CJ Cutter made a phone called to get a solid material vacuum truck to remove rock ,gravel, soil and fluids from the flow line excavation. Once flow lines were exposed Mr. Cutter performed a pressure test on Flow line used 1000PSI on lines a failure at an elbow was observed no other leaks were observed.
1795397732 2011-08-30 UrbanProduction Wells No Violations Found two areas approximately 12 diameter of oil stained mulch between the tank battery and sump. Advised the clean up crew to remove these areas an to pump out the fluids from the sumps. The two excavated areas were filled in with bark mulch and saw dust.
1804240682 2011-08-31 UrbanProduction Wells No Violations Cutter Cleanup crew started by pumping fluid from sump 10-20 gallons into the water tank inside tank battery more water than oil. Small area approximately 18 between the sump and tank battery was removed and sawdust was replaced.
1993084548 2018-10-17 UrbanProduction Wells No Violations I inspected this well location as part of routine inspection and evaluation of current condition following recent change in ownership. At the time of this inspection, I met with EOS Energy Representative Mike Corp and North Royalton Fire Chief Chegan. I noted that the well was in active production. The enclosure gates were locked and secure. The identification was current and accurate. The load-line valves were plugged and locked. Tank lids were closed and sealed. I walked the areas surrounding the well and battery and found no signs of problems or indications of impact. I noted the following maintenance items that required attention: I noted that there were some discarded wiring in the battery enclosure which require removal and disposal. I advised Mike to have these items remedied as soon as possible. I also noted that the gate at the access road was not secure and required proper signage. He indicated that he would have the issues addressed as soon as possible.
616234565 2008-12-1 0:00: DD No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
0705579455 US-OH-127966 2011-09-18 Well operation causing pollution and contamination
0919928165 US-OH-130507 2011-09-18 Well operation causing pollution and contamination
0973916699 US-OH-131177 2011-09-18 Well operation causing pollution and contamination
1150924309 US-OH-103921 2011-09-18 Well operation causing pollution and contamination
1431609213 US-OH-112616 2015-07-13 LOCKS
1431609213 US-OH-112617 2015-07-13 TANKS (a-i)
1431609213 US-OH-112618 2015-07-13 Well operation causing pollution and contamination
1476241895 US-OH-113625 2011-09-18 Well operation causing pollution and contamination
1625518751 US-OH-115988 2011-09-18 Well operation causing pollution and contamination

For data sources see[9]