Well Details

Well ID: 34-031-26548
Loading map...
Country: United States
State: Ohio
County: Coshocton
Municipality: Keene Township
Operator Name: NORTHWOOD ENERGY CORP
Well Pad ID:
Farm/Lease Name: MCCOY UNIT
License Status: Producing
License Date: 2013-04-01
Spud Date: 1995-08-01
Spud Drilling Contractor: CUBBY DRLG
Final Drill Date: 1995-08-10
Well Total Depth: 6158.00 ft
Configuration: Vertical
Latitude: 40.350000
Longitude: -81.840000

For data sources see[1]

Well History

Well Status Well Status Date Comment
Oil and Gas 1994-10-26 Issued Date 10/26/94 Expired Date 10/26/95 Acres 0471323 Tool Type RTAF Proposed Formation CLINTON/ROSE RUN Proposed Depth 06158 Proposed Drill Depth 06158
Original Spud 1995-08-01 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
Completed 1995-08-10 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
Reached Total Depth 1995-08-10 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
CO 1995-09-03 124 MOORE JERRY INC GeoDate 10/26/94
Change of Owner 2003-03-20 Operator changed from 4884, EASTERN STATES OIL & GAS INC to 1634, NORTHWOOD ENERGY CORP
APP 2013-04-01 Proposed Formations:, Issued Date:4/1/2013, Expired Date:4/1/2015 12:00:00 PM, Drilling unit acres:471.323, Proposed Well Type:OG, Proposed Well Class:POOL
Plugged Back 2014-09-17 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
Construction Permit Expires 2015-04-01 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
Completion Report Received 2015-06-02 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95
Record Last Modified 2019-06-11 PLUG BACK FORMATION IS UTICA SHALE Previous Form 8 12/20/95

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2014-02-19 5338 5366 80
6080 0
1997-06-29 6080 0
5338 5366 80
5338 5366 80

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2013-08-28 H2O 15 9326 Bbl 225000 Producers Service Corporation
2013-08-28 H2O 15 9326 Bbl 9326

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1995 JERRY MOORE INC 9968.00 75.00 365
1996 JERRY MOORE INC 22376.00 105.00 365
1997 EASTERN STATES OIL & GAS INC 2600.00 158.00 365
1998 EASTERN STATES OIL & GAS INC 0.00 0.00 365
1999 EASTERN STATES OIL & GAS INC 1024.00 0.00 365
2000 EASTERN STATES OIL & GAS INC 1228.00 0.00 365
2001 EASTERN STATES OIL & GAS INC 361.00 1540.00 365
2002 EASTERN STATES OIL & GAS INC 364.00 20.00 365
2003 EASTERN STATES OIL & GAS INC 2371.00 2.00 59
2004 NORTHWOOD ENERGY CORP 2124.00 136.00 365
2005 NORTHWOOD ENERGY CORP 697.00 153.00 365
2006 NORTHWOOD ENERGY CORP 1704.00 118.00 365
2007 NORTHWOOD ENERGY CORP 1484.00 86.00 365
2008 NORTHWOOD ENERGY CORP 1378.00 94.00 365
2009 NORTHWOOD ENERGY CORP 1062.00 52.00 365
2010 NORTHWOOD ENERGY CORP 1061.00 26.00 365
2011 NORTHWOOD ENERGY CORP 959.00 67.00 0
2012 NORTHWOOD ENERGY CORP 914.00 53.00 366
2013 NORTHWOOD ENERGY CORP 1002.00 75.00 365
2014 NORTHWOOD ENERGY CORP 867.00 39.00 365
2015 NORTHWOOD ENERGY CORP 1473.00 219.00 365
2016 NORTHWOOD ENERGY CORP 1342.00 104.00 365
2017 NORTHWOOD ENERGY CORP 1020.00 118.00 365
2018 NORTHWOOD ENERGY CORP 1035.00 59.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1995 JERRY MOORE INC Brine 990 365
1996 JERRY MOORE INC Brine 0 365
1997 EASTERN STATES OIL & GAS INC Brine 365
1998 EASTERN STATES OIL & GAS INC Brine 15 365
1999 EASTERN STATES OIL & GAS INC Brine 3 365
2000 EASTERN STATES OIL & GAS INC Brine 4 365
2001 EASTERN STATES OIL & GAS INC Brine 0 365
2002 EASTERN STATES OIL & GAS INC Brine 0 365
2003 NORTHWOOD ENERGY CORP Brine 0 365
2004 NORTHWOOD ENERGY CORP Brine 0 365
2005 NORTHWOOD ENERGY CORP Brine 22 365
2006 NORTHWOOD ENERGY CORP Brine 24 365
2007 NORTHWOOD ENERGY CORP Brine 3 365
2008 NORTHWOOD ENERGY CORP Brine 11 365
2009 NORTHWOOD ENERGY CORP Brine 7 365
2010 NORTHWOOD ENERGY CORP Brine 12 365
2011 NORTHWOOD ENERGY CORP Brine 28
2012 NORTHWOOD ENERGY CORP Brine 184 366
2013 NORTHWOOD ENERGY CORP Brine 436 365
2014 NORTHWOOD ENERGY CORP Brine 288 365
2015 NORTHWOOD ENERGY CORP Brine 102 365
2016 NORTHWOOD ENERGY CORP Brine 27 365
2017 NORTHWOOD ENERGY CORP Brine 24 365
2018 NORTHWOOD ENERGY CORP Brine 1 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1669089934 2013-5-17 0:00: PB No Violations
-1800384799 2016-8-8 0:00:0 PW No Violations 0.50
-1857571445 2014-9-15 0:00: PB No Violations
-208568323 2016-6-20 0:00: PW No Violations 1.00
-484027667 2016-2-1 0:00:0 PW No Violations 0.70
0000009689 Preliminary Restoration No Violations PASSED Y WITNESSED 11/9/95 INSPECTOR DATE 11/0919/95 DATA FROM OLD VAX INFO
0208568323 2016-06-20 Production Wells No Violations On the day of my inspection I found that the bare areas running downhill from the wellhead had been graded out, seeded and covered in straw. Approximately 60% of the grass was growing. Mark Fluharty met me at the site and he said that he would re-seed the area. The other area that was wet, sludgy clay and soil had been graded out and the exposed plastic material had been removed. The material was road fabric rather than pit liner. The dike had been cleared of all contaminated soil and filled in with new gravel. Identification had not been posted at the wellhead yet. Mark will contact me to inspect once he has the ID posted and the vegetation is growing.
0484027667 2016-02-01 Production Wells No Violations On the day of my inspection I found that the wellhead was equipped with a pumping unit. The engine was intact and the valves were open. The tank battery consisted of two 100 barrel tanks, one separator and an earthen dike. Identification was posted and I found no leaks or spills. The tank battery is shared with permit 5797.
0784909817 2013-05-14 Plug / Plug Back No Violations On the day of my inspection Davis Well Service ran tubing to 6088. Cemenco broke circulation and pumped a 300 plug in the 4.5 casing from 6088 to 5788. Good circulation was maintained throughout the job and there were no leaks or spills.
0851136184 2016-02-22 Production Wells Violations Noted This inspection was conducted in response to a complaint of alleged pollution and contamination. I was joined by SE Regional Supervisor Brent Bear and NE Regional Emergency Operations Manager Terry Whitehair. On the day of our inspection we found that the well was being produced with a natural gas powered pumping unit. Mark Fluharty, pumper for Northwood, was on location to start the pumping unit. There was no identification posted at the wellhead. There was bare soil and erosion ruts leading downhill from the wellhead to an approximate 20 x 20 bare area that was heavily tracked by deer. There was a larger disturbed area approximately 50 feet from the wellhead that was bare of vegetation and very wet. We found patches of a thick grey substance that resembled plugging clay and we found exposed pieces of pit liner. The tank battery consisted of two 100 barrel steel tanks and one horizontal separator. An earthen containment dike was in place around the production equipment. The tank battery is shared with permit 5797. Identification was posted at the tanks. There was an area of oil/brine impacted soil mixed with sawdust under the load valves on one of the 100 barrel tanks. There was also a pile of oily sludge lying on the outside of the dike wall. The issues needing addressed at this well to bring it into compliance include: posting identification at the wellhead, removing and properly disposing of the impacted soil inside of the dike, removing and disposing of the oily sludge pile outside the dike, bio-remediate the impacted soils at the wellhead and establish vegetative cover.
0933583251 2013-05-13 Plug / Plug Back No Violations On the day of my inspection Davis Well Service pulled 6080 of tubing. The permit was on location and there were no leaks or spills.
1012280073 2011-09-13 Work Over Reconditioning No Violations R & B Drilling rig changing pump.
1236959815 2009-03-13 Production Wells Violations Noted Call from Dennis Devers @ 3:15 pm w/ OEPA 3/12/09 notified Rocky King of oil spill . Call from Bill Arnolt @ 4:30 pm w/ Northwood Energy 3/12/09 . 3/13/09 inspection of oil spill at well site . 210 bl. Storage tank inside dike , the dike contained all but 0.5 bls. Oil ran into drain tile at well site and came out down hill approximately 100 covering a area of 40 by 70 . Oil and contaminated soil have been removed from this area oil spill clean up is on going at this time . Storage tank is 25 from well head . Storage tank is in violation of spacing . Tank will need to at a minimum of 50 from well head & diked to contain 110 % of storage tank . No identification at well or tank . Called Bill Arnolt this date and notified of violations .
1237224595 2009-03-16 Production Wells No Violations Meet with landowner ( Ester Mathis ) and Mark Fluharty with Northwood energy at well site went over clean up of oil spill . Storage tank pad is built tank ready to be moved 50 from well head . All but storage old storage tank area cleaned up and ready for seeding . Soil is being removed from oil tank area this inspection .
1243353594 2009-05-26 Production Wells No Violations Oil spill in compliance .
1368720576 2013-05-15 Plug / Plug Back No Violations On the day of my inspection Appalachian Well Surveys ran a neutron and gamma log in cased hole. Then they ran a bond log to determine the top of the production string cement. The cement top was at 5274.
1368799957 2013-05-16 Administrative Inspection No Violations Appalachian Well Surveys set a cast iron bridge plug at 5500 and a drillable bridge plug at 5266 Then they perforated the 4.5 casing with 6 shots at 5262.
1369404838 2013-05-24 Plug / Plug Back No Violations On the day of my inspection Davis Well Service was running 2.375 tubing into the well to drill out the cement and bridge plug.
1410804565 2014-09-12 Plug / Plug Back No Violations On the day of my inspection I found that RB Drilling had 1.5 tubing ran to a depth of 5335. Cemenco broke circulation and pumped 30 sacks of cement inside of 4.5 casing for a 400 plug through the Utica shale. Good circulation was maintained throughout the job.
1410958859 2014-09-17 Plug / Plug Back No Violations On the day of my inspection Appalachian Well Surveys ran a bond log on the squeeze job. They found that there was good cement bond from 4090 to 3380.
1574597965 2016-10-11 Production Wells No Violations On the day of my inspection I found that bare area below the wellhead was completely covered in grass. All of the actions listed in the compliance notice have been taken to bring this well into compliance.
1669089934 2013-05-17 Plug / Plug Back No Violations On the day of my inspection Cemenco hooked up to the 4.5 casing to circulate through perforations. The pressure increased rapidly when attempting to circulate. The pressure was not allowed to increase over 1200 psi. Cemenco shut down without pumping any cement. The casing will need to be perforated again.
1800384799 2016-08-08 Production Wells No Violations On the day of my inspection I found that the bare, sludgy area had been graded out. It was dry and was growing with grass. Identification was posted at the wellhead. The bare area below the wellhead was not growing. I called Mark Fluharty, pumper for Northwood and left a message to contact me.
1857571445 2014-09-15 Plug / Plug Back No Violations On the day of my inspection I found that Appalachian Well Surveys set an electric bridge plug at 4100 and then perforated the 4.5 casing at 4090 with four shots. Formation Cementing established circulation and squeezed 170 sacks of class A cement behind the casing to cement off the Clinton sand.
1993741583 2013-11-12 Preliminary Restoration No Violations On the day of my inspection I found that the well site was graded out to the approximate contour of the surrounding landscape and covered in well established short grasses. This plug back site passes preliminary restoration.
784909817 2013-5-14 0:00: PB No Violations
851136184 2016-2-22 0:00: PW No Violations
933583251 2013-5-13 0:00: PB No Violations
9689 PL No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
0851136184 US-OH-129681 2016-11-28 Well operation causing pollution and contamination
0851136184 US-OH-129682 2016-11-28 Failure to legibly identify well
1236959815 US-OH-106330 2009-03-13 Failure to legibly identify well
1236959815 US-OH-106331 2009-03-13 Violation of tank spacing requirements