34-031-21025

Well Details

Well ID: 34-031-21025
Loading map...
Country: United States
State: Ohio
County: Coshocton
Municipality: Monroe Township
Operator Name: DIVERSIFIED PRODUCTION LLC
Well Pad ID:
Farm/Lease Name: REISS DEWEY
License Status: Producing
License Date: 1957-05-24
Spud Date: 1957-06-01
Spud Drilling Contractor:
Final Drill Date: 1957-07-07
Well Total Depth: 3368.00 ft
Configuration: Vertical
Latitude: 40.430000
Longitude: -82.000000

For data sources see[1]

Well History

Well Status Well Status Date Comment
CO 1801-01-02 79 OXFORD OIL CO
Oil and Gas 1802-01-01
Original Spud 1957-06-01 PG-05/24/1957 DRILLED TO-2ND
Completed 1957-07-07 PG-05/24/1957 DRILLED TO-2ND
Reached Total Depth 1957-07-07 PG-05/24/1957 DRILLED TO-2ND
Change of Owner 2014-02-06 Operator changed from 79, OXFORD OIL to 9216, ECLIPSE RESOURCES-OHIO LLC
Change of Owner 2016-08-02 Operator changed from 9216, ECLIPSE RESOURCES-OHIO LLC to 8685, M & R INVESTMENTS OHIO LLC
Record Last Modified 2016-08-04 PG-05/24/1957 DRILLED TO-2ND

For data sources see[2]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
Not Treated 0 960 Bbl 33500

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1984 OXFORD OIL 0.00 375.00 0
1985 OXFORD OIL 0.00 669.00 365
1986 OXFORD OIL 0.00 628.00 365
1987 OXFORD OIL 0.00 402.00 365
1988 OXFORD OIL 0.00 532.00 365
1989 OXFORD OIL 0.00 340.00 365
1990 OXFORD OIL 0.00 426.00 365
1991 OXFORD OIL 0.00 405.00 365
1992 OXFORD OIL 0.00 353.00 365
1993 OXFORD OIL 0.00 277.00 365
1994 OXFORD OIL 0.00 421.00 365
1995 OXFORD OIL 0.00 290.00 365
1996 OXFORD OIL 0.00 368.00 366
1997 OXFORD OIL 0.00 384.00 365
1998 OXFORD OIL 0.00 310.00 365
1999 OXFORD OIL 0.00 388.00 365
2000 OXFORD OIL 0.00 296.00 0
2001 OXFORD OIL 0.00 218.00 365
2002 OXFORD OIL 0.00 275.00 365
2003 OXFORD OIL 0.00 202.00 365
2004 OXFORD OIL 0.00 219.00 365
2005 OXFORD OIL 0.00 144.00 365
2006 OXFORD OIL 0.00 145.00 365
2007 OXFORD OIL 0.00 216.00 365
2008 OXFORD OIL 0.00 145.00 0
2009 OXFORD OIL 0.00 204.00 0
2010 OXFORD OIL 0.00 147.00 365
2011 OXFORD OIL 0.00 149.00 0
2012 OXFORD OIL 0.00 238.00 0
2013 ECLIPSE RESOURCES-OHIO LLC 0.00 154.00 365
2014 ECLIPSE RESOURCES-OHIO LLC 0.00 153.00 365
2015 ECLIPSE RESOURCES-OHIO LLC 0.00 168.00 365
2016 ECLIPSE RESOURCES-OHIO LLC 0.00 0.00 365
2017 M & R INVESTMENTS OHIO LLC 0.00 218.00 365
2018 M & R INVESTMENTS OHIO LLC 0.00 151.00 365

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1984 OXFORD OIL Brine 0 0
1985 OXFORD OIL Brine 280 365
1986 OXFORD OIL Brine 245 365
1987 OXFORD OIL Brine 700 365
1988 OXFORD OIL Brine 1769 365
1989 OXFORD OIL Brine 634 365
1990 OXFORD OIL Brine 154 365
1991 OXFORD OIL Brine 125 365
1992 OXFORD OIL Brine 99 365
1993 OXFORD OIL Brine 49 365
1994 OXFORD OIL Brine 35 365
1995 OXFORD OIL Brine 75 365
1996 OXFORD OIL Brine 30 366
1997 OXFORD OIL Brine 50 365
1998 OXFORD OIL Brine 35 365
1999 OXFORD OIL Brine 30 365
2000 OXFORD OIL Brine 25
2001 OXFORD OIL Brine 30 365
2002 OXFORD OIL Brine 30 365
2003 OXFORD OIL Brine 0 365
2004 OXFORD OIL Brine 30 365
2005 OXFORD OIL Brine 40 365
2006 OXFORD OIL Brine 5 365
2007 OXFORD OIL Brine 25 365
2008 OXFORD OIL Brine 30
2009 OXFORD OIL Brine 0
2010 OXFORD OIL Brine 25 365
2011 OXFORD OIL Brine 0
2012 OXFORD OIL Brine 30
2013 ECLIPSE RESOURCES-OHIO LLC Brine 0 365
2014 ECLIPSE RESOURCES-OHIO LLC Brine 0 365
2015 ECLIPSE RESOURCES-OHIO LLC Brine 30 365
2016 M & R INVESTMENTS OHIO LLC Brine 0 365
2017 M & R INVESTMENTS OHIO LLC Brine 0 365
2018 M & R INVESTMENTS OHIO LLC Brine 0 365

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1760386176 2018-6-20 0:00: PW No Violations 0.40
-587974893 2018-10-17 0:00 PW No Violations 0.50
0587974893 2018-10-17 Production Wells No Violations I noticed that the dike was holding water in one end when I was driving by this location. I was recently involved with a compliance notice on this well for brine in the dike, so I stopped to investigate. M&R Investments hauled soil out of here and rebuilt the dike to resolve the previous compliance notice. There were new deer tracks in the corner of the dike and scratches in the soil. I tested that standing water with a high range Quantab and found that the chloride level was less than 266 ppm(mg/L) or 0.047% NaCl. The chloride level in the dike water was within the EPA drinking water standards. No compliance notice was issued on this date.
1135875865 2005-12-29 Production Wells No Violations Well in production .
1405703169 2018-06-07 Production Wells Violations Noted On the day of my inspection I noticed standing water and discoloration in the dike when I was driving east on CR 19. I stopped to investigate and found that the inside of the earthen dike was darkly stained, muddy and heavily tracked by deer. The dike was wet in the east end, and I also noticed the odor of brine water. There was one 100-barrel steel tank and one 30-barrel poly tank both set up on gravel. I did not find any signs that the steel tank was leaking. I did notice that the valve on the poly tank was wet and the gravel under the valve was stained. I tested the standing water with a high range Quantab, which maxed out at 6298 ppm(mg/L) chlorides. The chloride content of the water exceeded the Quantab scale. I also found that the water had been leeching through the east end of the earthen dike wall, and there was a brine scald that extended approximately 40 feet into the surrounding hay field. The brine scald in the hay field was approximately 10 feet across at its widest point. I took photographs and sent them to the field supervisor, Dale Smith. I also called Dale to let him know what I had found and to ask that he get a crew out here as soon as possible. All of the brine saturated soil in and outside of the dike will need to be excavated and hauled to an approved landfill. The dike wall where the brine has been leeching through will also need to be removed and rebuilt with clean soil. Dale and I discussed hauling in new topsoil to remediate the area outside of the dike once the affected soil had been removed. The leaking tank valve should be replaced or repaired.
1528896901 2018-06-13 Production Wells No Violations On the day of my inspection I found that Diversified had a crew on site working to remove the brine contaminated soil. They had already scraped the top layer of soil from the hay field and they were working on the dike. There was a water truck, dump truck and track-hoe on site. The poly tank was drained and laying on its side. I spoke with the crew leader who said they were removing the poly tank and decreasing the size of the dike. He said that they had a manifest at Kimbles landfill to dispose of the soil. He also said that they were bringing in new soil to put down in the hay field, and they would treat the whole area with lime and fertilizer.
1531160648 2018-07-09 Production Wells No Violations I visited this site with Trish Cartmell and Jason Blocker from the ERS team to follow up on the spill remediation. There was grass coming up on half of the remediated area and the other half was still bare. Trish and Josh said that they would like to revisit the sit in the fall to follow up on the vegetative growth. There was still a muddy area in the corner of the dike where rainwater was collecting and bringing chlorides to the surface. There were no signs of leaking from the tank and there were no signs of anything leaching out of the new dike. I called Chuck Woods with Diversified and explained what I found. He said that he would get back out there to remove more of the soil from inside of the dike.
1532094684 2018-07-19 Production Wells No Violations On the day of my inspection I met with Jason Blocker at the site to assess the extent of the brine impacted soil with his soil conductivity meter. A crew from Sutton Pump showed up while we were there. We discussed the areas that needed to be excavated, and Jason probed the soil through the excavation process. Sutton removed the affected soil and filled the area in with new stone.
1710769468 2012-01-25 Production Wells No Violations Inspection completed this date. The well is capable of production and equipped with pumping unit, 1-100 barrel storage tank and a separator.
1760386176 2018-06-20 Production Wells No Violations On the day of my inspection I found that the brine contaminated soil had been excavated and removed from inside and outside the dike. The poly tank had been removed and the area of the dike had been reduced. The dike walls had been rebuilt and the soil around the dike had been graded out with fresh topsoil. The whole area was covered with grass seed and straw. The compliance notice is resolved.
2102312760 2011-01-10 Production Wells No Violations Pumping well capable of production.

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1405703169 US-OH-111954 2018-06-25 Well operation causing pollution and contamination
1405703169 US-OH-111955 2018-06-25 Dike or pit not able to prevent escape of brine or other wastes

For data sources see[8]

References