X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-117-21987

Well Details

Well ID: 37-117-21987
Loading map...
Country: United States
State: Pennsylvania
County: Tioga
Municipality: Union Township
Operator Name: ROCKDALE MARCELLUS LLC
Well Pad ID: 149555
Farm/Lease Name: WESNESKI 724 4H
License Status:
Spud Date: 2018-06-19
Permit Date: 2018-05-08
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.621808
Longitude: -76.897389

For data sources see[1][2][3]

Well History

Date Event
Deviated
2018-05-08 New Permit Application
2018-06-18 Performed Spud Operation
2018-09-12 Drilling Completion

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2018 ROCKDALE MARCELLUS LLC 441,645.00 74 0.00 0 0.00 0
2019 ROCKDALE MARCELLUS LLC 1,286,932.69 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 ROCKDALE MARCELLUS LLC Produced Fluid 47.57 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 ROCKDALE MARCELLUS LLC Soil Contaminated by Oil & Gas Related Spills 24.53 Tons LANDFILL 301358
2018 ROCKDALE MARCELLUS LLC Drilling Fluid Waste 1,323.00 Bbl REUSE (AT WELL PAD)
2018 ROCKDALE MARCELLUS LLC Produced Fluid 307.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2018 ROCKDALE MARCELLUS LLC Produced Fluid 18,522.53 Bbl REUSE (AT WELL PAD)
2018 ROCKDALE MARCELLUS LLC Produced Fluid 48.16 Tons LANDFILL 301358
2018 ROCKDALE MARCELLUS LLC Other Oil & Gas Wastes 1,051.90 Bbl REUSE (AT WELL PAD)
2018 ROCKDALE MARCELLUS LLC Drill Cuttings 1,235.65 Tons LANDFILL 301358
2018 ROCKDALE MARCELLUS LLC Other Oil & Gas Wastes 104.84 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 ROCKDALE MARCELLUS LLC Synthetic Liner Materials 23.47 Tons LANDFILL 301358
2018 ROCKDALE MARCELLUS LLC Soil Contaminated by Oil 24.53 Tons LANDFILL 301358
2019 ROCKDALE MARCELLUS LLC Produced Fluid 1,505.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC022
2019 ROCKDALE MARCELLUS LLC Other Oil & Gas Wastes 117.68 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC036
2019 ROCKDALE MARCELLUS LLC Soil Contaminated by Oil & Gas Related Spills 25.72 Tons LANDFILL 301358
2019 ROCKDALE MARCELLUS LLC Produced Fluid 5,947.00 Bbl REUSE (AT WELL PAD)
2019 ROCKDALE MARCELLUS LLC Produced Fluid 3,567.50 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC036
2019 ROCKDALE MARCELLUS LLC Soil Contaminated by Oil 25.72 Tons LANDFILL 301358
2019 ROCKDALE MARCELLUS LLC Produced Fluid 71.93 Tons LANDFILL 301358
2019 ROCKDALE MARCELLUS LLC Synthetic Liner Materials 20.99 Tons LANDFILL 301358
2019 ROCKDALE MARCELLUS LLC Waste Water Treatment Sludge 12.99 Tons RESIDUAL WASTE PROCESSING FACILITY 2014-541
2019 ROCKDALE MARCELLUS LLC Other Oil & Gas Wastes 604.33 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2743913 Primary Facility 2018-06-21 Routine/Complete Inspection No Violations Noted Waiting on cement truck to cement cellars.
2755229 Primary Facility 2018-07-24 Routine/Complete Inspection No Violations Noted Weather was 72 degrees and raining. It had been raining for a few days prior to this inspection. Well is a spud conductor. Conductor had a steel plate welded over the top of it. Well was mostly covered with a rig mat. Cellar was visible. No violations were noted at time of inspection.
2760874 Primary Facility 2018-08-06 Routine/Complete Inspection No Violations Noted Weather was 72° and sunny at time of inspection. Met with Rockdale Marcellus representative Jimmy Larsen on location. Well had surface and intermediate casing drilled and cemented at time of inspection. Rig had drilled down into the curve and loaded the hole with oil based mud for the production rig. Reviewed the cement job logs from the surface and intermediate casing and no discrepancies were noted. Conducted a walk around inspection of location. No violations were noted at time of inspection.
2771622 Primary Facility 2018-09-06 Routine/Complete Inspection No Violations Noted Weather was 78° and partly cloudy at time of inspection. Met with Rockdale Marcellus representative Danny Brooks on location. Well was shut in with a night cap, awaiting completion by the rig that was on location. Rig is expecting to move onto this well to finish drilling on 9/7/2018. No violations were noted at time of inspection.
2776839 Primary Facility 2018-09-19 Routine/Complete Inspection No Violations Noted Weather was 70° and cloudy at time of inspection. There were no Rockdale Marsellus representatives on location at time of inspection. Well had recently been drilled and cemented to TD. Well has a nightcap installed. There was a 0-5k psi analog gauge attached to the top of the nightcap that read 0 psi at time of inspection. Cement was visible at surface outside the surface casing. The mouse hole had a steel plate sitting on it. No violations noted at time of inspection.
2790932 Primary Facility 2018-10-17 Routine/Complete Inspection Pending I met Luke Chesner and Marc McCartor of Rockdale when I arrived. The frac was temporarily on hold because there was not yet enough water in the MASS to begin the next stages. The area around the MASS looked good overall, with all puddles on the ground surface showing low conductance (.11-.56 mS/ cm). One of the large pump containments had several inches of water in it that showed slightly elevated conductance (2.56 mS/cm). Walking around the sitewide containment, the liner and berms appeared to be in good condition, and most puddles were low in conductance (.4-.83 mS/cm). Large (approximately 12" diameter) collapsible hoses were run from the MASS onto the sitewide containment, and one of these hoses was compressing a foam berm. When I informed Luke, he told me he would have the containment vacced and prop up the 12" water line over the berm. A vac truck was working on the sitewide containment caddy corner from the entrance; immediately outside of this containment I discovered an approximately 15-20 ga
2802351 Primary Facility 2018-11-14 Administrative/File Review Violation(s) Noted Results were received for sample ID #0939077 taken on 10/17/2018 (see pictures). Sample was taken from a 15-20gallon puddle located outside of containment. Elevated barium, strontium, and chlorides indicate that the fluid on the pad was wastewater; the result of the administrative inspection is Violations Noted.
2825038 Primary Facility 2019-01-09 Routine/Complete Inspection Outstanding Violations - Viols Req'd Light activity on the site when I arrived. 2 temporary sand separators currently hooked up to the recently fraced wells. The onsite modular storage structure was still present, but a worker was pumping water from the tank to a bank of Baker tanks in containment. The area around the MASS was dry, and a downgradient sediment trap nearby showed low conductance (.13 mS/cm). A truck loading area at the Baker tanks had a 10' x 5' (1-2" deep) in front of it that showed slightly elevated conductance; I recommend that the puddle be vacced. The area where I noted fluid with elevated conductance on my 10/17/18 inspection had recently had fresh gravel placed on it.
2853454 Primary Facility 2019-03-13 Routine/Complete Inspection No Violations Noted Routine inspection conducted to assess overall site conditions. Two wells are still in flowback. Batteries of frac tanks are present on the pad within secondary containment. The containment appears to be in good condition overall. An aboveground storage tank is present on site. Several puddles on the pad to the south of the AST had a conductivity of between 1.1 and 1.6 mS/cm. Three GPUs are present n site, are labeled, and appear to be in good condition. Two steel double-walled produced water tanks are present, labeled, and appear to be in good condition.

No violations noted.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2802351 833572 2018-11-14 CSL 402(b) Environmental Health & Safety Wastewater released to pad surface
2802351 833573 2018-11-14 78a66(b)1 Environmental Health & Safety Wastewater released to pad surface
2802351 833574 2018-11-14 78a56(a) Environmental Health & Safety Wastewater released to pad surface
2802351 833575 2018-11-14 SWMA 301 Environmental Health & Safety Wastewater released to pad surface
2825038 838556 2019-01-09 CSL 402(b) Environmental Health & Safety
2825038 838557 2019-01-09 78a66(b)1 Environmental Health & Safety Outstanding violations from 11/14/18 admin inspection
2825038 838558 2019-01-09 78a56(a) Environmental Health & Safety Outstanding violations from 11/14/18 admin inspection
2825038 838559 2019-01-09 SWMA 301 Environmental Health & Safety Outstanding violations from 11/14/18 admin inspection

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
833572 369522 NOV - Notice of Violation
833573 369522 NOV - Notice of Violation
833574 369522 NOV - Notice of Violation
833575 369522 NOV - Notice of Violation

For data sources see[7]