X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-115-21526

Well Details

Well ID: 37-115-21526
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Lenox Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 151104
Farm/Lease Name: ROGERS UNIT 3H
License Status:
Spud Date:
Permit Date: 2013-12-03
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.696572
Longitude: -75.723178

For data sources see[1][2][3]

Well History

Date Event
2013-12-03 New Permit Application
2014-05-06 Performed Spud Operation
2014-06-18 Drilling Completion
2014-08-07 Perforation
2014-08-07 Performed Stimulation
2015-06-23 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2014-08-07 2014-08-18 7,236 13,126,300

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Hydrochloric Acid 10-30% Halliburton Acid Hydrochloric Acid 7647-01-0 30 0.05 0
MCB-8614 MULTI-CHEM BIOCIDE GLUTARALDEHYDE 111-30-8 30 0.02 0
ALKYL (C12-16) DIMETHYLBENZXYLAMMONIUM CHLORIDE 68424-85-1 5 0.003 0
FR-66 Halliburton Friction Reducer Hydrotreated Light Petroleum Distillate 64742-47-8 30 0.02 0
MCS-2510T MULTI-CHEM Scale Inhibitor ETHYLENE GLYCOL 107-21-1 60 0.01 0
Water Provided by Customer Base Fluid Fresh Water 0000-00-0 100 99.9 0

For data sources see[5]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
2014-08-07 0 0 0

For data sources see[6]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2014 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2015 CHIEF OIL & GAS LLC 1,705,062.28 267 0.00 0 0.00 0
2016 CHIEF OIL & GAS LLC 1,078,194.80 365 0.00 0 0.00 0
2017 CHIEF OIL & GAS LLC 683,937.99 357 0.00 0 0.00 0
2018 CHIEF OIL & GAS LLC 498,109.42 365 0.00 0 0.00 0
2019 CHIEF OIL & GAS LLC 491,792.30 365 0.00 0 0.00 0

For data sources see[7]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2014 CHIEF OIL & GAS LLC Fracturing Fluid Waste 444.00 Tons RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2014 CHIEF OIL & GAS LLC Drilling Fluid Waste 2,310.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2014 CHIEF OIL & GAS LLC Drill Cuttings 1,069.33 Tons LANDFILL 100933
2015 CHIEF OIL & GAS LLC Fracing Fluid Waste 6,712.57 Bbl REUSE OTHER THAN ROAD SPREADING
2015 CHIEF OIL & GAS LLC Produced Fluid 31,748.45 Bbl REUSE OTHER THAN ROAD SPREADING
2015 CHIEF OIL & GAS LLC Fracing Fluid Waste 30.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CHIEF OIL & GAS LLC Fracturing Fluid Waste 60.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CHIEF OIL & GAS LLC Produced Fluid 13,262.06 Bbl REUSE OTHER THAN ROAD SPREADING
2017 CHIEF OIL & GAS LLC Produced Fluid 3,355.99 Bbl REUSE (AT WELL PAD)
2017 CHIEF OIL & GAS LLC Produced Fluid 887.25 Bbl REUSE OTHER THAN ROAD SPREADING
2018 CHIEF OIL & GAS LLC Produced Fluid 3,070.46 Bbl REUSE (AT WELL PAD)
2019 CHIEF OIL & GAS LLC Produced Fluid 4,510.51 Bbl REUSE (AT WELL PAD)

For data sources see[8]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2284378 Primary Facility 2014-05-07 Routine/Complete Inspection No Violations Noted Spudder rig on location
2301056 Primary Facility 2014-09-02 Drilling/Alteration No Violations Noted
2339549 Primary Facility 2015-01-27 Routine/Complete Inspection No Violations Noted On 1/27/15, the Department was on site at the Chief Rogers Well Pad to conduct a routine inspection. Well permits that have been issued for this site are the Rogers 1H (115-21524), 2H (115-21525), 3H (115-21526), and the 4H (115-21523). A crew is on the pad actively installing production equipment on the pad. All four wells appear to have been flowed back, and the crews have emplaced the four production units along with a battery of production tanks. Well heads and production equipment is being plumbed together. Production piping is being buried in approximately 4’ deep excavated ditches. This inspection conducted in conjunction with an inspection of the Regency Taylor to Rogers Pipeline construction. Pipeline scheduled to be ready for production sometime mid to late February. Pad is snow covered. No violations noted.
2659991 Primary Facility 2017-11-08 Routine/Complete Inspection No Violations Noted All fill slopes stone stabilized. Today's inspection was conducted as a routine inspection. Site is stable. Photo 1 shows the well pad layout. Photo 2 shows the southeast corner of the well site. No violations noted.
2803590 Primary Facility 2018-11-13 Routine/Complete Inspection No Violations Noted This inspection was conducted to confirm Chief's assessment that the project meets the minimum requirements for permit termination. The Department’s determination is that the site meets the requirements for permit termination. I recommend the NOT be approved.

For data sources see[9]

References