X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-115-20118

Well Details

Well ID: 37-115-20118
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Dimock Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 148386
Farm/Lease Name: G SHIELDS 2H
License Status:
Spud Date:
Permit Date: 2009-03-06
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.717111
Longitude: -75.943854

For data sources see[1][2][3]

Well History

Date Event
2009-03-06 New Permit Application
2009-08-28 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 CABOT OIL & GAS CORP 0.00 0 0.00 0 0.00 0
2010 CABOT OIL & GAS CORP 705,700.50 206 0.00 0 0.00 0
2011 CABOT OIL & GAS CORP 618,015.10 352 0.00 0 0.00 0
2012 CABOT OIL & GAS CORP 418,631.03 365 0.00 0 0.00 0
2013 CABOT OIL & GAS CORP 284,168.29 364 0.00 0 0.00 0
2014 CABOT OIL & GAS CORP 298,084.63 348 0.00 0 0.00 0
2015 CABOT OIL & GAS CORP 174,953.26 327 0.00 0 0.00 0
2016 CABOT OIL & GAS CORP 216,314.48 355 0.00 0 0.00 0
2017 CABOT OIL & GAS CORP 215,259.14 360 0.00 0 0.00 0
2018 CABOT OIL & GAS CORP 182,244.00 365 0.00 0 0.00 0
2019 CABOT OIL & GAS CORP 160,446.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 221.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2010 CABOT OIL & GAS CORP Produced Fluid 711.45 Bbl REUSE OTHER THAN ROAD SPREADING
2010 CABOT OIL & GAS CORP Drill Cuttings 18.90 Tons LANDFILL NY # 50S08
2010 CABOT OIL & GAS CORP Basic Sediment 2.59 Bbl LANDFILL 101534
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 133.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 247.50 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAD085690592
2010 CABOT OIL & GAS CORP Drill Cuttings 66.90 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 101247
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 660.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026034
2010 CABOT OIL & GAS CORP Drill Cuttings 108.90 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 8-4630-00010/00
2010 CABOT OIL & GAS CORP Drill Cuttings 108.90 Tons LANDFILL NY # 02S17
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 357.05 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0008451
2010 CABOT OIL & GAS CORP Drill Cuttings 1.40 Tons LANDFILL 100955
2011 CABOT OIL & GAS CORP Basic Sediment 1.15 Bbl LANDFILL 100081
2011 CABOT OIL & GAS CORP Basic Sediment 1.19 Bbl LANDFILL 101534
2011 CABOT OIL & GAS CORP Produced Fluid 270.20 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CABOT OIL & GAS CORP Produced Fluid 178.32 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CABOT OIL & GAS CORP Basic Sediment 0.66 Bbl LANDFILL THR029
2012 CABOT OIL & GAS CORP Basic Sediment 0.42 Bbl LANDFILL 100081
2012 CABOT OIL & GAS CORP Basic Sediment 0.86 Bbl LANDFILL 101534
2013 CABOT OIL & GAS CORP Produced Fluid 90.71 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NE002
2013 CABOT OIL & GAS CORP Produced Fluid 66.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2013 CABOT OIL & GAS CORP Produced Fluid 7.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2014 CABOT OIL & GAS CORP Produced Fluid 345.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2014 CABOT OIL & GAS CORP Produced Fluid 3.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2015 CABOT OIL & GAS CORP Produced Fluid 73.23 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Produced Fluid 4.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2016 CABOT OIL & GAS CORP Produced Fluid 66.42 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2016 CABOT OIL & GAS CORP Produced Fluid 117.46 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2017 CABOT OIL & GAS CORP Synthetic Liner Materials 0.79 Tons LANDFILL 101247
2017 CABOT OIL & GAS CORP Produced Fluid 67.10 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2017 CABOT OIL & GAS CORP Produced Fluid 77.23 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 158.10 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 84.35 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2019 CABOT OIL & GAS CORP Produced Fluid 127.16 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2142594 Primary Facility 2009-11-12 Routine/Complete Inspection No Violations Noted
2405551 Primary Facility 2015-09-09 Routine/Complete Inspection No Violations Noted
2496276 Primary Facility 2016-06-27 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 10:00a.m., the cellar was full of gravel with no gas detected at the perimeter of the cellar, the (9x4) vent pipe was open and venting to a tank, there was 559psi on the production casing. I took a walk around the location and everything looked OK.

I left the site at 10:35a.m.

2516835 Primary Facility 2016-09-01 Site Restoration No Violations Noted The Department was on site to conduct a Notice of Termination (NOT) for the Shields G P2 well site, permit number 58-09-802. The wells associated with this site are as follows:

115-20118


The site was constructed according to plan, the vegetation was perennial, at or above the 70% vegetative standard and there were no erosional actions occuring at this time. All BMPs have been removed. I recommend APPROVAL of this Notice of Termination.

If there are any questions please feel free to contact me at (570) 346-5539

2704875 Primary Facility 2018-03-08 Routine/Complete Inspection No Violations Noted Arrived at location at 09:45. Weather: Overcast, cold, ~ 25 degs. (2) wells were present on location, the Shields, G. 2H and 4H. Both wells were producing at time of inspection. Both wells production pressures were being monitored by remote monitors sending data to Total Flow Control Units "TFCU"s with LED readouts located by production units. Each well had (1) annular vent plumbed to a shared poly vent tank. Both vents were labeled (9 5/8" x 5 1/2") and were open and venting to vent tank. A gas check performed at the shared vent tank opening showed: 100% LEL, 100% CH4. Gas check performed 3' away from vent tank showed 0% LEL, 0% CH4.

- Review of well history showed that a previous 72 hr. pressure build up tests "PBUT" had been performed on these wells on (10/29 - 11/1/11). The PBUT showed the 4H, (9x5) press. built to 166 psi. and the 2H, (9x5) showed no press. build up. - Further review of well history revealed that these wells are part of an ongoing gas migration investigation initiated by the Dept. on 1

2706937 Primary Facility 2018-03-19 Routine/Complete Inspection No Violations Noted Arrived at location at 09:10. Weather: Clear, cold, ~ 30 degs. (2) wells were present on location, the Shields, G. 2H and 4H. Both wells were producing at time of inspection. Onsite to witness start of the 72hr. press. build up test "PBUT" being performed on both wells surface x production casing annuli. Upon arrival met with Cabot O&G Reps., Adam Vogt, Aaron Onks, Brody Webster and Steve Catalfamo onsite. Both wells surface x production casing annuli were equipped with pressure logging units tied into Cabot's cygnet monitoring system. Adam confirmed communication with loggers through cynet system. These annuli were shut in at 09:15. We will return to site on Thursday, March 22 at 09:15 for conclusion of the 72 hr. PBUT.

Wells pressures were taken off LED readouts mounted at production units. (Prod. Casing Press. = CP, Static Press. = SP, Differential Press. = DP.) Shields, G. 2H: CP = 461.6 psi., SP = 474.4 psi., DP = 25.2 psi. Shields, G. 4H: CP = 473.6 psi., SP = 476.2 psi., DP = 92.4 psi.

No obvious

2710021 Primary Facility 2018-03-22 Routine/Complete Inspection No Violations Noted Arrived at location at 09:45. Weather: Clear, cold, ~ 30 degs. Onsite for the conclusion of the 72hr. press. build up test "PBUT" being performed on both wells surface x production casing annuli. The PBUT was started on 3/19/18 at 09:15. Upon arrival met with Cabot O&G Reps., Adam Vogt & Aaron Onks and (3) Selman & Assoc. Reps. Both wells surface x production casing annuli were equipped with pressure logging units tied into Cabot's cygnet monitoring system. The PBUT ending pressures were:

- 2H: (9 5/8"x 5 1/2") = 49 psi. - 4H: (9 5/8"x 5 1/2") = 84 psi. Gas checks performed by the Dept. and Selman showed: 100% CH4. The Dept. and Selman collected gas samples off both these annuli at approx. 09:50. Both wells annuli were bleed down and opened back up to poly vent tank. Post PBUT, water samples were collected at area resident by Eric Rooney, D.E.P. Geologist and Moody & Associates prior to bleeding pressures off of gas wells. - Review of well record for the 2H well showed the 5 1/2" prod. casing cement top was

For data sources see[7]

References