37-115-20092

Well Details

Well ID: 37-115-20092
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Dimock Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 148385
Farm/Lease Name: G SHIELDS 1
License Status:
Spud Date:
Permit Date: 2009-03-12
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: No
Latitude: 41.712817
Longitude: -75.946638

For data sources see[1][2][3]

Well History

Date Event
2009-03-12 New Permit Application
2009-08-14 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2009 CABOT OIL & GAS CORP 0.00 0 0.00 0 0.00 0
2010 CABOT OIL & GAS CORP 195,695.50 204 0.00 0 0.00 0
2011 CABOT OIL & GAS CORP 132,852.26 357 0.00 0 0.00 0
2012 CABOT OIL & GAS CORP 97,967.78 353 0.00 0 0.00 0
2013 CABOT OIL & GAS CORP 49,061.93 363 0.00 0 0.00 0
2014 CABOT OIL & GAS CORP 56,281.35 321 0.00 0 0.00 0
2015 CABOT OIL & GAS CORP 25,086.06 322 0.00 0 0.00 0
2016 CABOT OIL & GAS CORP 50,364.24 365 0.00 0 0.00 0
2017 CABOT OIL & GAS CORP 47,874.21 358 0.00 0 0.00 0
2018 CABOT OIL & GAS CORP 31,090.00 302 0.00 0 0.00 0
2019 CABOT OIL & GAS CORP 26,541.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2009 CABOT OIL & GAS CORP Drilling 600.00 Bbl Brine or Industrial Waste Treatment Plt PA0027057
2009 CABOT OIL & GAS CORP Drilling 1,190.00 Bbl Brine or Industrial Waste Treatment Plt PA0008451
2009 CABOT OIL & GAS CORP Drilling 777.00 Bbl Brine or Industrial Waste Treatment Plt PAR9000009
2009 CABOT OIL & GAS CORP Drilling 2,200.00 Bbl Municipal Sewage Treatment Plant PA0026034
2010 CABOT OIL & GAS CORP Basic Sediment 2.22 Bbl LANDFILL 101534
2010 CABOT OIL & GAS CORP Drill Cuttings 51.90 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 101247
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 171.50 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2010 CABOT OIL & GAS CORP Produced Fluid 314.11 Bbl REUSE OTHER THAN ROAD SPREADING
2010 CABOT OIL & GAS CORP Drill Cuttings 14.70 Tons LANDFILL NY # 50S08
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 1,100.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026034
2010 CABOT OIL & GAS CORP Drill Cuttings 84.50 Tons LANDFILL NY # 02S17
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 103.20 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CABOT OIL & GAS CORP Drill Cuttings 1.10 Tons LANDFILL 100955
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 357.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAD085690592
2010 CABOT OIL & GAS CORP Drill Cuttings 84.50 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 8-4630-00010/00
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 1,073.55 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0008451
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 1,140.76 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CABOT OIL & GAS CORP Basic Sediment 1.15 Bbl LANDFILL 101534
2011 CABOT OIL & GAS CORP Produced Fluid 276.97 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CABOT OIL & GAS CORP Drill Cuttings 1.47 Tons LANDFILL 101534
2011 CABOT OIL & GAS CORP Drill Cuttings 1.66 Tons LANDFILL THR029
2011 CABOT OIL & GAS CORP Drill Cuttings 1.69 Tons LANDFILL 100081
2012 CABOT OIL & GAS CORP Servicing Fluid 67.82 Bbl LANDFILL THR029
2012 CABOT OIL & GAS CORP Basic Sediment 0.40 Bbl LANDFILL 100081
2012 CABOT OIL & GAS CORP Basic Sediment 0.81 Bbl LANDFILL 101534
2012 CABOT OIL & GAS CORP Produced Fluid 102.17 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CABOT OIL & GAS CORP Servicing Fluid 86.52 Bbl LANDFILL 100945
2013 CABOT OIL & GAS CORP Produced Fluid 52.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2013 CABOT OIL & GAS CORP Produced Fluid 199.45 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NE002
2013 CABOT OIL & GAS CORP Produced Fluid 7.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2014 CABOT OIL & GAS CORP Produced Fluid 250.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2014 CABOT OIL & GAS CORP Produced Fluid 5.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2015 CABOT OIL & GAS CORP Produced Fluid 58.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Produced Fluid 4.50 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2016 CABOT OIL & GAS CORP Produced Fluid 34.74 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2016 CABOT OIL & GAS CORP Produced Fluid 30.07 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2017 CABOT OIL & GAS CORP Produced Fluid 44.20 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2017 CABOT OIL & GAS CORP Produced Fluid 36.34 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 19.59 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Servicing Fluid 42.09 Tons LANDFILL 100933
2018 CABOT OIL & GAS CORP Produced Fluid 37.47 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2018 CABOT OIL & GAS CORP Synthetic Liner Materials 7.73 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Produced Fluid 90.29 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1851911 Primary Facility 2009-11-12 Routine/Complete Inspection No Violations Noted
1890399 Primary Facility 2010-05-24 Routine/Complete Inspection No Violations Noted
2028197 Primary Facility 2011-12-13 Drilling/Alteration No Violations Noted DOH Energy 282. Co. man Ronnie Wright. Ran Temp logs. Perf'd and squeezed on 4 1/2' string. shot holes 1420 - 1422 (4 shots/ft). Were able to squeeze @ bbls of microfine cement into perforations. monitored for 48 hrs. Pressured up to 1500 lbs - no leak off detected. When let off , start to again see buildup of pressure on backside up to 520psi. Currently waiting for instructions on next procedure. Will be running CBL tomorrow.
2029561 Primary Facility 2011-12-22 Drilling/Alteration No Violations Noted Currently doing remedial work on well. On 12/28 perf'd and squeezed .5 bbl microfine cement at 1442-1444 (6 SPF). Pressured up to 1500 lbs and held for 48 hrs. Reportedly no shows of pressure on annulus after squeeze. Currently drilling out cement and tagging top of sand. Will be installing chart recorders on annulus and let sit over holiday break. Work to resume on 12/28.
2405548 Primary Facility 2015-09-09 Routine/Complete Inspection No Violations Noted
2496273 Primary Facility 2016-06-27 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 10:35a.m., the cellar was empty with no gas detected at the perimeter of the cellar, the (9x5) vent pipe was open and venting to a tank, there was 584psi on the production casing. I took a walk around the location and everything looked OK.

I left the site at 11:10a.m.

2691058 Primary Facility 2018-02-05 Administrative/File Review No Violations Noted The Well Site Restoration Report required by 78.65 was accepted. No violations were noted. If you have any questions, please contact me.
2704585 Primary Facility 2018-03-08 Routine/Complete Inspection No Violations Noted Arrived at location at 08 30. Weather: Overcast, cold, ~ 25 degs. (2) wells were present on location, the Shields, G. 1V and 5H. Both wells were producing at time of inspection. Both wells production pressures were being monitored by remote monitors sending data to Total Flow Control Units "TFCU"s with LED readouts located by production units. Each well had (1) annular vent plumbed to a shared poly vent tank. The 1V wells annular vent was labeled (9 5/8" x 4 1/2") and the 5H wells annular vent was labeled (9 5/8" x 5 1/2"). Both wells annular vents were open and venting to vent tank. A gas check performed at the shared vent tank opening showed: 100% LEL, 100% CH4. Gas check performed 3' away from vent tank showed 0% LEL, 0% CH4.

- Review of well history showed that previous 72 hr. pressure build up tests "PBUT" had been performed on these wells on (10/29 - 11/1/11) and (12/28 - 12/31/11). The initial PBUT showed the 1V, (9x4) press. build to 550 psi. and the 5H, (9x5) built to 8 psi. Subsequently, Cabot perf

2706931 Primary Facility 2018-03-19 Routine/Complete Inspection No Violations Noted Arrived at location at 08:45. Weather: Clear, cold, ~ 30 degs. (2) wells were present on location, the Shields, G. 1V and 5H. Both wells were producing at time of inspection. Onsite to witness start of the 72hr. press. build up test "PBUT" being performed on both wells surface x production casing annuli. Upon arrival met with Cabot O&G Reps., Adam Vogt, Aaron Onks, Brody Webster and Steve Catalfamo onsite. Both wells surface x production casing annuli were equipped with pressure logging units tied into Cabot's cygnet monitoring system. Adam confirmed communication with loggers through cynet system. These annuli were shut in at 09:00. We will return to site on Thursday, March 22 at 09:00 for conclusion of the 72 hr. PBUT.

Wells pressures were taken off LED readouts mounted at production units. (Prod. Casing Press. = CP, Static Press. = SP, Differential Press. = DP.) Shields, G. 1V: CP = 466.8 psi., SP = 491.4 psi., DP = 9.0 psi. Shields, G. 5H: CP = 490.7 psi., SP = 493.8 psi., DP = 61.8 psi.

No obvious c

2709411 Primary Facility 2018-03-22 Routine/Complete Inspection No Violations Noted Arrived at location at 09:00. Weather: Clear, cold, ~ 30 degs. Onsite for the conclusion of the 72hr. press. build up test "PBUT" being performed on both wells surface x production casing annuli. The PBUT was started on 3/19/18 at 09:00. Upon arrival met with Cabot O&G Reps., Adam Vogt & Aaron Onks and (3) Selman & Assoc. Reps. Both wells surface x production casing annuli were equipped with pressure logging units tied into Cabot's cygnet monitoring system. The PBUT ending pressures were:

- 1V: (9 5/8"x 4 1/2") = 212 psi. - 5H: (9 5/8"x 5 1/2") = 42 psi. Gas checks performed by the Dept. and Selman showed: 100% CH4. The Dept. and Selman collected gas samples off both these annuli at approx. 09:30. Both wells annuli were bleed down and opened back up to poly vent tank. Post PBUT, water samples were collected at area resident by Eric Rooney, D.E.P. Geologist and Moody & Associates prior to bleeding pressures off of gas wells. - The press. build in the 1V (9x4) annulus is a significant increase from the last

2739575 Primary Facility 2018-06-05 Routine/Complete Inspection No Violations Noted Arrived on location at 08:30. Weather: Clear, mild ~ 60 degs. Cabot O & G has mobilized "Hybrad" W/O Rig onto location to start remedial work of the 1V wells (9x4) annulus. I met with Cabot's Well Site Supervisor "WSS", James Restley, on location. Mr. Restley mentioned that Rig crew will be arriving on location at 10:00 today to start rigging up "RU", W/O rig and ancillary rig equipment. GDS site contractors were onsite readying to set liner and containment as needed.

- A protective cage has been placed around the existing 5H well. This well will remain in production throughout the 1V wells remedial work. - Mr. Restley anticipates having site prep and W/O RU completed to start remedial operations tomorrow morning. We discussed basics of W/O plan and anticipated timeline. Cabot will be sending daily progress reports throughout these W/O operations. All was found in good order at time of inspection. Left site at 09:30.

For data sources see[7]