Well ID: 37-115-20026 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.744566,"lon":-75.879518,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Susquehanna | |
Municipality: Dimock Township | |
Operator Name: CABOT OIL & GAS CORP | |
Well Pad ID: 147756 | |
Farm/Lease Name: BAKER 1 | |
License Status: ACTIVE | |
Spud Date: | |
Permit Date: 2008-02-06 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Vertical Well | |
Conservation: Yes | |
Latitude: 41.744566 | |
Longitude: -75.879518 |
Date | Event |
---|---|
2008-02-06 | New Permit Application |
2008-08-11 | Performed Spud Operation |
2008-08-31 | Drilling Completion |
2008-11-09 | Perforation |
2008-11-10 | Performed Stimulation |
2009-02-27 | NEWLY DRILLED |
For data sources see[4]
Stimulation Date | Phase Number | Chemical Agent | Volume (gal) | Treating Pressure (psi) | Breakdown Pressure (psi) |
---|---|---|---|---|---|
2008-11-10 | 0 | 0 | 0 |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2008 | CABOT OIL & GAS CORP | 39833.00 | 29 | 0.00 | 0 | 0.00 | 0 |
2009 | CABOT OIL & GAS CORP | 226484.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2010 | CABOT OIL & GAS CORP | 59,709.50 | 121 | 0.00 | 0 | 0.00 | 0 |
2011 | CABOT OIL & GAS CORP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
For data sources see[6]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2009 | CABOT OIL & GAS CORP | Brine | 6,100.00 Bbl | Municipal Sewage Treatment Plant | PA0026034 |
2009 | CABOT OIL & GAS CORP | Drilling | 357.00 Bbl | Brine or Industrial Waste Treatment Plt | PAR9000009 |
2009 | CABOT OIL & GAS CORP | Drilling | 600.00 Bbl | Brine or Industrial Waste Treatment Plt | PA0027057 |
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 178.50 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PAD085690592 |
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 225.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0008451 |
2011 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 107.29 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0008451 |
2011 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 61.76 Bbl | PUBLIC SEWAGE TREATMENT PLANT | PA0026034 |
2011 | CABOT OIL & GAS CORP | Drill Cuttings | 19.12 Tons | LANDFILL | THR029 |
For data sources see[7]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1716871 | Primary Facility | 2008-06-26 | Routine/Complete Inspection | No Violations Noted | |
1729805 | Primary Facility | 2008-08-20 | Drilling/Alteration | Violation(s) Noted | |
1738413 | Primary Facility | 2008-09-03 | Drilling/Alteration | No Violations Noted | |
1752407 | Primary Facility | 2008-11-20 | Routine/Complete Inspection | No Violations Noted | |
1753532 | Primary Facility | 2008-11-19 | Routine/Complete Inspection | No Violations Noted | |
1761024 | Primary Facility | 2009-01-05 | Routine/Complete Inspection | No Violations Noted | |
1761500 | Primary Facility | 2009-01-08 | Routine/Complete Inspection | No Violations Noted | |
1764219 | Primary Facility | 2009-01-20 | Routine/Complete Inspection | No Violations Noted | |
1764226 | Primary Facility | 2009-01-20 | Drilling/Alteration | No Violations Noted | |
1765442 | Primary Facility | 2009-01-26 | Routine/Complete Inspection | No Violations Noted | |
1768969 | Primary Facility | 2009-02-09 | Routine/Complete Inspection | No Violations Noted | |
1768980 | Primary Facility | 2009-02-10 | Routine/Complete Inspection | No Violations Noted | |
1768986 | Primary Facility | 2009-02-02 | Routine/Complete Inspection | No Violations Noted | |
1768990 | Primary Facility | 2009-02-03 | Routine/Complete Inspection | No Violations Noted | |
1770585 | Primary Facility | 2009-02-18 | Routine/Complete Inspection | No Violations Noted | |
1772824 | Primary Facility | 2009-02-25 | Routine/Complete Inspection | No Violations Noted | |
1774160 | Primary Facility | 2009-03-05 | Routine/Complete Inspection | No Violations Noted | |
1774890 | Primary Facility | 2009-02-18 | Administrative/File Review | Violation(s) Noted | |
1799929 | Primary Facility | 2009-05-01 | Routine/Complete Inspection | No Violations Noted | |
1813856 | Primary Facility | 2009-07-15 | Routine/Complete Inspection | No Violations Noted | |
1833445 | Primary Facility | 2009-09-25 | Follow-up Inspection | No Violations Noted | An existing road was used to access the well site. The road and drill pad are stoned with limestone. The Site ID sign and E/S Plan were present at the entrance of the access road. |
1847933 | Primary Facility | 2009-12-04 | Follow-up Inspection | Violation(s) Noted | At the time of inspection, construction crews were on location fixing the liner in the new reserve pit, and re-working the well pad in preparation for the next proposed well. While on site, I inspected the existing reserve pit. The freeboard in the reserve pit was less than 6". This is a violation of 25 PA Code 78.56(a)(2) which provides: " A pit shall be designed, constructed and maintained so that at least 2 feet of freeboard remain at all times." |
1852357 | Primary Facility | 2009-12-10 | Follow-up Inspection | No Violations Noted | I arrived on site at approximately 8:00 am to perform a follow-up inspection of the reserve pit associated with the Baker 1 Well. A previous DEP inspection of this location dated 12/4/09 resulted in issuing a violation for failure to maintain adequate freeboard in the pit. At the time of this inspection, the reserve pit had been encapsulated and the surface restored to the grade of the existing well pad. A letter received from Cabot Oil and Gas dated 12/22/09 indicates that on 12/03/09 cement was added to the pit and any excess fluid was removed from the pit prior to solidification. The letter further indicates the encapsulation of the pit was completed on 12/05/09. Based on this information, the violation cited on 12/04/09 has been corrected. |
1868960 | Primary Facility | 2010-03-08 | Routine/Complete Inspection | No Violations Noted | |
1876534 | Primary Facility | 2010-04-13 | Follow-up Inspection | No Violations Noted | At the time of inspection the well was shut in and off-line due to drilling activites associated with Baker #3. There was no standing water present around the wellhead. I poured water around the base of the wellhead and observed bubbling around the outside of the 9-5/8" and 7" casings. Gas readings were collected using a Model 60 gas meter. No readings were detected. Crews were on location breaking down Patterson Rig 154 and loading onto transport trucks. The reserve pit was still open and had sufficient freeboard. |
1881281 | Primary Facility | 2010-04-26 | Drilling/Alteration | No Violations Noted | no activity on site |
1881292 | Primary Facility | 2010-04-27 | Drilling/Alteration | No Violations Noted | no activity on site. well still online |
1881347 | Primary Facility | 2010-04-29 | Drilling/Alteration | No Violations Noted | Stone service rig being moved to site and rigged up. plan to shut in well and begin pulling tubing tomorrow. |
1881349 | Primary Facility | 2010-04-30 | Drilling/Alteration | No Violations Noted | Doug Gosnell (Cabot) and Mark Howard (Boots and Coots) on site. Stone service rig set up on hole. In process of pulling tubing and killing well. Have coil tubing unit on standby to start setting plugs per COA. |
1881364 | Primary Facility | 2010-05-03 | Drilling/Alteration | No Violations Noted | Doug Gosnell provided up date of activities completed over weeknd. Set 1st cement plug at 5400 to 7241' on 5/1. After 17 1/2hrs annular pressure was zero. Ran coil back in hle to tag TOC at 5792'. Pulled coil back to 5553' and pumped in 289 sk plug from 5553 up to 1375'. moved rig off site to Ely 4 well site. |
1883180 | Primary Facility | 2010-05-05 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | At time of inspection- Stone rig on well. Crew is trying to pull section of 4 1/2' casing out o f hole. The casing was cut at 1250'. The well so far has been plugged with cement from 7241 back up to 1378'. Steve Barrett is Co. Man on site overseeing work. He indicated after they pull out casing, they they will cement the remaining casing up to surface and then set a monument with API number on it. |
1883224 | Primary Facility | 2010-05-06 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | Pulled 847.1' of 4" casing. Shot with jet cutter. Ran in 1412' tubing to 1418 kb. Cemented up to 500' with 102 sks. Pulled tubing up to 500 and ran 63 sks cement up to 150'. Pulled tubing to 150' and ran another 27 sks of cement up to surface. Stephen Barrett - Co. Man on site. Plan to complete plugging and set monument tomorrow. |
1883300 | Primary Facility | 2010-05-10 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | Plugging of the well has been completed according to Cabot's plugging procedures. A 4' high piece of 4" casing has been installed as a monument with the DEP Permit # welded on a plate attached to the riser. The ground around the well has been leveled off to grade. |
1887839 | Primary Facility | 2010-05-27 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | At the time of inspection there was no activity on site. The well has been plugged. The conductor and surface casings were exposed at the ground surface. There was no standing water present around the well head. A soapy water mixture was introduced around the well head and casings. During the time of inspection, there was evidence of bubbling observed in between the 9 5/8" and 13 3/8" conductor. The bubbling was localized to an area located on the western side of the well head. Along the outside of the conductor, some very small bubbling was also observed. The bubbling in this area was consistent with 1 bubble coming to surface approximately every second. DEP collected a video of the conditions of the well head at the time of inspection. |
1890428 | Primary Facility | 2010-06-03 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | |
1890777 | Primary Facility | 2010-06-08 | Routine/Complete Inspection | No Violations Noted | |
1891112 | Primary Facility | 2010-06-09 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | |
1891344 | Primary Facility | 2010-06-11 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | Stone services rig on site. In process of drilling out cement to 1540' encountered a bunch of metal "junk" in hole at @ 1475'. Crew having a hard time getting through. Continue to mill out junk and retrieve pieces with magnet. Current depth is 1478'. |
1898256 | Primary Facility | 2010-06-22 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | At the time of inspection I met with Johnny Crawford who is overseeing plugging of well. Stone Service Rig is rigged down. Plugging of well is complete. According to Mr. Crawford, top of cement of last plug was taggedat 695' in the 7" casing. The remaining portion of the 7" casing is filled with p-gravel. A plate with a vent has been welded on top of the 9 5/8" casing to cover the space between the 9 5/8" casing and 7" casing. A 4 ' section of 4" casing has been welded on top of the plate which has a metal plate containing the DEP permit number on it 115-20026. Crews on site continue to clean up site and de-mobilize equipment off location. |
1917651 | Primary Facility | 2010-10-04 | Routine/Complete Inspection | No Violations Noted | inspected well for evidence of gas seepage around well head. Well is plugged. Monument present with API#. Standing water present when cleared gravel away from well head. No gas expressions at surface observed. No activity on site. |
2054297 | Primary Facility | 2012-03-22 | Routine/Complete Inspection | No Violations Noted | |
2054298 | Primary Facility | 2012-03-22 | Routine/Complete Inspection | No Violations Noted | |
2641301 | Primary Facility | 2017-09-28 | Site Restoration | No Violations Noted | I inspected the Baker pad on September 28, 2017 for Notice of Termination (NOT). The site's access road was smooth and solid, with a cornfield bordering the one side. The site itself was well vegetated and nicely maintained, mowed neatly and compact in size. The vegetation was all healthy and exceeded the 70% perennial vegetative threshold. The pad surface was smooth and not rutted and there were no erosional issues present at the time of inspection.
I recommend APPROVAL of this NOT. There were no violations noted |
2672704 | Primary Facility | 2017-12-19 | Administrative/File Review | No Violations Noted | I approved a restoration report on December 19, 2017 for this well site. |
Inspection ID | Violation ID | Violation Date | Date Resolved | Violation Code | Violation Type | Violation Comments |
---|---|---|---|---|---|---|
1729805 | 545935 | 08/20/2008 | 2008-08-20 | 78.83GRNDWTR - Improper casing to protect fresh groundwater | Administrative | |
1774890 | 557988 | 02/18/2009 | 2009-02-18 | 212WELLRCD - Failure to submit well record within 30 days of completion of drilling | Administrative | |
1847933 | 577244 | 12/04/2009 | 2009-12-04 | 78.56FRBRD - Failure to maintain 2' freeboard in an impoundment | Administrative |
Violation ID | Penalty ID | Penalty Code | Penalty Status | Penalty Date | Enforcement Date | Penalty Amount | Amount Collected |
---|---|---|---|---|---|---|---|
557988 | 244244 | NOV - Notice of Violation | Superseded | 2010-04-15 | |||
557988 | 252129 | COA - Consent Order and Agreement | Superseded | 2010-04-15 | $120,000.00 | $120,000.00 |