If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 37-115-20008 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.751108,"lon":-75.868132,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Susquehanna | |
Municipality: Dimock Township | |
Operator Name: CABOT OIL & GAS CORP | |
Well Pad ID: 148440 | |
Farm/Lease Name: GREENWOOD 1 | |
License Status: ACTIVE | |
Spud Date: | |
Permit Date: 2007-07-31 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Vertical Well | |
Conservation: Yes | |
Latitude: 41.751108 | |
Longitude: -75.868132 |
Date | Event |
---|---|
2007-07-31 | New Permit Application |
2007-09-25 | Performed Spud Operation |
2007-10-12 | Drilling Completion |
2007-11-09 | Perforation |
2007-11-09 | Performed Stimulation |
2008-02-01 | NEWLY DRILLED |
2010-10-01 | REWORKED |
For data sources see[4]
Stimulation Date | Phase Number | Chemical Agent | Volume (gal) | Treating Pressure (psi) | Breakdown Pressure (psi) |
---|---|---|---|---|---|
2007-11-09 | 0 | 0 | 0 |
For data sources see[5]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2007 | CABOT OIL & GAS CORP | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
2008 | CABOT OIL & GAS CORP | 22203.00 | 15 | 0.00 | 0 | 0.00 | 0 |
2009 | CABOT OIL & GAS CORP | 157714.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2010 | CABOT OIL & GAS CORP | 60,734.08 | 181 | 0.00 | 0 | 0.00 | 0 |
2011 | CABOT OIL & GAS CORP | 50,791.90 | 365 | 0.00 | 0 | 0.00 | 0 |
2012 | CABOT OIL & GAS CORP | 27,777.89 | 353 | 0.00 | 0 | 0.00 | 0 |
2013 | CABOT OIL & GAS CORP | 39,348.46 | 365 | 0.00 | 0 | 0.00 | 0 |
2014 | CABOT OIL & GAS CORP | 38,460.19 | 276 | 0.00 | 0 | 0.00 | 0 |
2015 | CABOT OIL & GAS CORP | 17,222.87 | 356 | 0.00 | 0 | 0.00 | 0 |
2016 | CABOT OIL & GAS CORP | 29,962.86 | 365 | 0.00 | 0 | 0.00 | 0 |
2017 | CABOT OIL & GAS CORP | 23,562.66 | 365 | 0.00 | 0 | 0.00 | 0 |
2018 | CABOT OIL & GAS CORP | 23,109.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2019 | CABOT OIL & GAS CORP | 18,274.00 | 365 | 0.00 | 0 | 0.00 | 0 |
For data sources see[6]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 158.90 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR119 |
2010 | CABOT OIL & GAS CORP | Produced Fluid | 106.09 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2010 | CABOT OIL & GAS CORP | Basic Sediment | 1.85 Bbl | LANDFILL | 101534 |
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 95.60 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 |
2010 | CABOT OIL & GAS CORP | Drill Cuttings | 48.10 Tons | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 101247 |
2010 | CABOT OIL & GAS CORP | Drill Cuttings | 13.60 Tons | LANDFILL | NY # 50S08 |
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 119.05 Bbl | PUBLIC SEWAGE TREATMENT PLANT | PA0026034 |
2010 | CABOT OIL & GAS CORP | Drill Cuttings | 78.30 Tons | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 8-4630-00010/00 |
2010 | CABOT OIL & GAS CORP | Drill Cuttings | 78.30 Tons | LANDFILL | NY # 02S17 |
2010 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 3,404.76 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0008451 |
2010 | CABOT OIL & GAS CORP | Drill Cuttings | 1.00 Tons | LANDFILL | 100955 |
2011 | CABOT OIL & GAS CORP | Drilling Fluid Waste | 80.00 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2011 | CABOT OIL & GAS CORP | Drill Cuttings | 0.23 Tons | LANDFILL | 101534 |
2011 | CABOT OIL & GAS CORP | Basic Sediment | 0.82 Bbl | LANDFILL | 101534 |
2011 | CABOT OIL & GAS CORP | Produced Fluid | 67.94 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2011 | CABOT OIL & GAS CORP | Drill Cuttings | 11.64 Tons | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PAD014286009 |
2012 | CABOT OIL & GAS CORP | Servicing Fluid | 75.00 Bbl | LANDFILL | 100945 |
2012 | CABOT OIL & GAS CORP | Produced Fluid | 97.15 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2012 | CABOT OIL & GAS CORP | Basic Sediment | 0.41 Bbl | LANDFILL | THR029 |
2012 | CABOT OIL & GAS CORP | Basic Sediment | 0.40 Bbl | LANDFILL | 101534 |
2012 | CABOT OIL & GAS CORP | Produced Fluid | 14.84 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123NE001 |
2012 | CABOT OIL & GAS CORP | Servicing Fluid | 0.52 Bbl | LANDFILL | 100081 |
2012 | CABOT OIL & GAS CORP | Servicing Fluid | 309.89 Bbl | REUSE OTHER THAN ROAD SPREADING | |
2012 | CABOT OIL & GAS CORP | Servicing Fluid | 3.30 Bbl | LANDFILL | 101534 |
2013 | CABOT OIL & GAS CORP | Produced Fluid | 146.17 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | WMGR123NE002 |
2013 | CABOT OIL & GAS CORP | Produced Fluid | 20.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2014 | CABOT OIL & GAS CORP | Produced Fluid | 68.00 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2014 | CABOT OIL & GAS CORP | Produced Fluid | 7.50 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE001 |
2015 | CABOT OIL & GAS CORP | Produced Fluid | 60.42 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2015 | CABOT OIL & GAS CORP | Produced Fluid | 4.25 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE001 |
2016 | CABOT OIL & GAS CORP | Produced Fluid | 10.71 Bbl | RESIDUAL WASTE PROC FAC (GENERAL PERMIT) | WMGR123NE002 |
2016 | CABOT OIL & GAS CORP | Produced Fluid | 28.38 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2017 | CABOT OIL & GAS CORP | Produced Fluid | 6.97 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC018 |
2017 | CABOT OIL & GAS CORP | Produced Fluid | 15.14 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2018 | CABOT OIL & GAS CORP | Produced Fluid | 16.53 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
2018 | CABOT OIL & GAS CORP | Produced Fluid | 23.71 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NC018 |
2019 | CABOT OIL & GAS CORP | Produced Fluid | 17.56 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NE002 |
For data sources see[7]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1656333 | Primary Facility | 2007-09-27 | Drilling/Alteration | No Violations Noted | |
1656338 | Primary Facility | 2007-09-26 | Drilling/Alteration | No Violations Noted | |
1656342 | Primary Facility | 2007-09-25 | Drilling/Alteration | No Violations Noted | |
1662428 | Primary Facility | 2007-10-31 | Routine/Complete Inspection | No Violations Noted | |
1665467 | Primary Facility | 2007-11-01 | Drilling/Alteration | Violation(s) Noted | |
1671567 | Primary Facility | 2007-12-12 | Site Restoration | No Violations Noted | |
1689289 | Primary Facility | 2008-02-28 | Routine/Complete Inspection | No Violations Noted | |
1723948 | Primary Facility | 2008-06-18 | Routine/Complete Inspection | No Violations Noted | |
1729817 | Primary Facility | 2008-08-20 | Routine/Complete Inspection | No Violations Noted | |
1733048 | Primary Facility | 2008-09-03 | Site Restoration | No Violations Noted | |
1764280 | Primary Facility | 2009-01-20 | Routine/Complete Inspection | No Violations Noted | |
1764287 | Primary Facility | 2009-01-21 | Routine/Complete Inspection | No Violations Noted | |
1765550 | Primary Facility | 2009-01-21 | Routine/Complete Inspection | No Violations Noted | |
1774908 | Primary Facility | 2009-02-18 | Administrative/File Review | Violation(s) Noted | |
1799972 | Primary Facility | 2009-05-01 | Routine/Complete Inspection | No Violations Noted | |
1833448 | Primary Facility | 2009-09-25 | Follow-up Inspection | No Violations Noted | An existing road was used to access the well site. The road and drill pad are stoned with limestone. The Site ID sign and E/S Plan were present at the entrance of the access road. |
1845085 | Primary Facility | 2009-11-10 | Follow-up Inspection | No Violations Noted | I inspected the well head for evidence of leakage. There was standing water present around the well. No bubbling was observed. |
1956786 | Primary Facility | 2011-03-05 | Routine/Complete Inspection | No Violations Noted | |
1980738 | Primary Facility | 2011-06-13 | Follow-up Inspection | Violation(s) Noted | On site to collect gas readings and isotopic samples. Observed oil sheen in cellar water. Oil has been dumped into ratholes of other three wells on site. See inspection report for full details. |
2005228 | Primary Facility | 2011-09-19 | Follow-up Inspection | Pending | Operator has digital gauges on both 9x5 and 9 x 7 annuli. Readings at time of inspection: 9x5 had no pressure. 9x7 currently reading 44psi. In the process of 30 day shut in. |
2007186 | Primary Facility | 2011-09-27 | Follow-up Inspection | Pending | Follow up on status of 30 day Pressure Recording. 9 x 7" annulus = 65 lbs. 7 x 4 1/2" = 0 lbs. |
2007604 | Primary Facility | 2011-09-02 | Routine/Complete Inspection | Violation(s) Noted | |
2009282 | Primary Facility | 2011-10-03 | Follow-up Inspection | Pending | Digital pressure gauges on well annuli. Operator currently in process of 30-day shut in pressure monitoring program. Pressure readings at time of inspection : 9" x 7"=78.86 psi, 7 "x 4 1/2" = -23.00 psi (0 psi - negative reading likely due to cold ambient air temps). Monitoring being completed as part of ongoing gas migration investigation. |
2028178 | Primary Facility | 2011-12-08 | Routine/Complete Inspection | Outstanding Violations - No Viols Req'd | Well online. Cellar full of water. no bubbling observed. Pipeline crews working on site. Vents are open - venting to Brine Tanks. inspection performed as part of ongoing gas migration investigation. |
2033531 | Primary Facility | 2011-12-05 | Incident- Response to Accident or Event | No Violations Noted | |
2053594 | Primary Facility | 2012-03-20 | Drilling/Alteration | No Violations Noted | Stone service Rig on site. Jim Reistly is Co. Man. Objective is to squeeze cement into 7 x 8 3/4" annular space # 354 ' KB. |
2139932 | Primary Facility | 2013-02-14 | Follow-up Inspection | No Violations Noted | On site to collect pressure reading and isotopic gas sample from annulus of well. DEP reps on site = Steve Watson, Eric Rooney, and Gene Rickard. DEP met with John Smelko of Cabot. Selman reps on site to assist with collection of gas readings and gas sampling. Cabot shut in annuli on well at @9am. A digital pressure gauge was installed on the 7 5/8" x 4 1/2" annulus. Pressure indicated was 13.3 psi. Gauge was removed, and open flow was screened using Model 60 gas meter. Model 60 reading = >5% combustible gas. DEP and Cabot collected samples for isotopic analysis. The pressure gauge was installed on the 9 5/8" x 7" annulus. Pressure reading was 0 psi. Model 60 reading = >5% combustible gas. DEP and Cabot collected samples for isotopic analysis. After completion of sampling, Cabot re-connected vent lines and locked vents open. |
2481911 | Primary Facility | 2016-04-27 | Routine/Partial Inspection | No Violations Noted | The Department was on site at the Greenwood, R. Pad 1 to conduct a Routine Partial Inspection. The E&S Inspection Log indicated that Mike Brilla (TEC) conducted a Post Rain Event Inspection on 4/27/16. It appears as though the landowner has made a road to the left of the access road gate to circumvent said gate. Also, it seems as if the landowner has been working areas on the well site. There is a large area within the well pad surface that looks like wood chips have been strewn across it and sections of plastic packaging are intermixed.
The perimeter ditch does not appear to meet temporary stabilization requirements. The Department requests that the operator investigate the area and deploy a method of erosion control that is consistent with your plan. The production tanks were stained during the inspection. One of the tanks has more staining than the other. The Department requests that the operator inspect the tanks to find the origin of the staining. |
2528903 | Primary Facility | 2016-10-17 | Follow-up Inspection | No Violations Noted | |
2642431 | Primary Facility | 2017-10-02 | Site Restoration | No Violations Noted | I inspected the site for notice of termination (NOT) on October 2, 2017. The site was surrounded by active agriculture (field corn). The access road leading in was in good shape with no rutting and the site was well vegetated on the cut and fill slopes. The pad surface was solid and stable as well. There were no erosional issues noted.
I recommend APPROVAL of this NOT. There were no violations observed. |
2774797 | Primary Facility | 2018-09-11 | Routine/Complete Inspection | No Violations Noted | Arrived on location at 09:00. Weather: ~ 65 degs., light rain, slight breeze. Onsite to initiate 72 hr. pressure build up test "PBUT" on the annuli of the Greenwood 1V, 6H, 7H & 8H wells. All wells, back side of production casing annuli have been isolated and were venting to onsite poly vent tanks. The 6H, 7H & 8H wells (16"x 9 5/8") cemented annuli had open top 16" casings in cellar *. The 1V wells (9 5/8"x 7") cemented annulus was beneath water level in cellar, no bubbling was noted at time of inspection.
- Upon arrival I met with Cabot O&G Reps. Jeremy Rapp and Sully Rutledge. Prior to shutting in wells annuli, initial gas screenings and flow checks were performed at the 1V (7"x 4 1/2") and 6H, 7H & 8H (9 5/8"x 5 1/2") annuli using the Depts. Altair 5X gas meter, calibrated this morning, and Cabots' RS-484 Alicat "Whisper" flow meter. Pre-shut in screenings showed: - 1V: (7"x 4 1/2") = 100% CH4, 9.2 cf/d; (9 5/8"x 7") open casing top in cellar, No bubbling noted. - 6H: (9 5/8"x 5 1/2") = 100% CH4, 15.2 cf |
2775651 | Primary Facility | 2018-09-14 | Routine/Complete Inspection | No Violations Noted | Arrived on location at 09:00. Weather: ~ 65 degs., light rain, slight breeze. Onsite to initiate 72 hr. pressure build up test "PBUT" on the annuli of the Greenwood 1V, 6H, 7H & 8H wells. All wells, back side of production casing annuli have been isolated and were venting to onsite poly vent tanks. The 6H, 7H & 8H wells (16"x 9 5/8") cemented annuli had open top 16" casings in cellar *. The 1V wells (9 5/8"x 7") cemented annulus was beneath water level in cellar, no bubbling was noted at time of inspection.
- Upon arrival I met with Cabot O&G Reps. Jeremy Rapp and Sully Rutledge. Prior to shutting in wells annuli, initial gas screenings and flow checks were performed at the 1V (7"x 4 1/2") and 6H, 7H & 8H (9 5/8"x 5 1/2") annuli using the Depts. Altair 5X gas meter, calibrated this morning, and Cabots' RS-484 Alicat "Whisper" flow meter. Pre-shut in screenings showed: - 1V: (7"x 4 1/2") = 100% CH4, 9.2 cf/d; (9 5/8"x 7") open casing top in cellar, No bubbling noted. - 6H: (9 5/8"x 5 1/2") = 100% CH4, 15.2 cf |
Inspection ID | Violation ID | Violation Date | Date Resolved | Violation Code | Violation Type | Violation Comments |
---|---|---|---|---|---|---|
1665467 | 527463 | 11/01/2007 | 2007-11-01 | 102.4NOPLAN - No E&S plan developed, plan not on site | Administrative | |
1774908 | 558001 | 02/18/2009 | 2009-02-18 | 212WELLRCD - Failure to submit well record within 30 days of completion of drilling | Administrative | |
1980738 | 613560 | 06/13/2011 | 2011-06-13 | 78.56(1) - Pit and tanks not constructed with sufficient capacity to contain pollutional substances. | Administrative | violation of 78.56 (a). failure to contain a pollutional substance in a pit or tank. |
1980738 | 613561 | 06/13/2011 | 2011-06-13 | 402CSL B - Failure to meet requirements of permit, rules and regulations, or order of DEP. | Environmental Health & Safety | vilation of CSL 402. Potential pollution. |
1980738 | 613562 | 06/13/2011 | 2011-06-13 | SWMA301 - Failure to properly store, transport, process or dispose of a residual waste. | Environmental Health & Safety | Unpermitted discharge of residual waste |
2007604 | 621392 | 09/02/2011 | 2011-09-02 | 691.1 - Clean Streams Law-General. Used only when a specific CLS code cannot be used | Administrative | 402 |
2007604 | 621393 | 09/02/2011 | 2011-09-02 | SWMA301 - Failure to properly store, transport, process or dispose of a residual waste. | Environmental Health & Safety |
Violation ID | Penalty ID | Penalty Code | Penalty Status | Penalty Date | Enforcement Date | Penalty Amount | Amount Collected |
---|---|---|---|---|---|---|---|
527463 | 227675 | NOV - Notice of Violation | Comply/Closed | 2007-12-12 | |||
558001 | 244244 | NOV - Notice of Violation | Superseded | 2010-04-15 | |||
558001 | 252129 | COA - Consent Order and Agreement | Superseded | 2010-04-15 | $120,000.00 | $120,000.00 | |
613560 | 272559 | NOV - Notice of Violation | |||||
613561 | 272559 | NOV - Notice of Violation | |||||
613562 | 272559 | NOV - Notice of Violation |
For data sources see[8]