Well Details

Well ID: 37-113-20255
Loading map...
Country: United States
State: Pennsylvania
County: Sullivan
Municipality: Fox Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 150974
Farm/Lease Name: WALDEISEN LADD UNIT 1H
License Status:
Spud Date: 2014-06-03
Permit Date: 2014-03-06
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.553833
Longitude: -76.760142

For data sources see[1][2][3]

Well History

Date Event
2014-03-06 New Permit Application
2014-06-03 Performed Spud Operation
2014-08-16 Drilling Completion
2014-11-24 Perforation
2015-03-31 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2014-11-24 2014-12-03 8,118 13,307,500

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Gyptron T-390 Champion Technologies Scale Inhibitor Methanol 67-56-1 10 0.001 0
Unislik ST 50 Universal Friction Reducer Petroleum distillates, hydrotreated light 64742-47-8 30 0.02 0
Hydrochloric Acid Universal Acid Hydrochloric Acid 7647-01-0 37 0.05 0
Bactron K-139 Champion Technologies Biocide Ethanol 64-17-5 5 0.002 0
Glutaraldehyde 111-30-8 5 0.002 0
Quaternary ammonium compounds,
benzyl-C-12-16 alkyldimethyl, chlorides
68424-85-1 10 0.004 0
Water Provided by Customer Base Fluid Fresh Water 0000-00-0 100 99.92 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2014 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2015 CHIEF OIL & GAS LLC 2,372,609.94 237 0.00 0 0.00 0
2016 CHIEF OIL & GAS LLC 1,552,530.96 365 0.00 0 0.00 0
2017 CHIEF OIL & GAS LLC 973,537.29 365 0.00 0 0.00 0
2018 CHIEF OIL & GAS LLC 783,106.30 365 0.00 0 0.00 0
2019 CHIEF OIL & GAS LLC 551,672.34 363 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2014 CHIEF OIL & GAS LLC Drilling Fluid Waste 668.71 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW018
2014 CHIEF OIL & GAS LLC Fracing Fluid Waste 720.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2014 CHIEF OIL & GAS LLC Drill Cuttings 91.29 Tons LANDFILL 100933
2014 CHIEF OIL & GAS LLC Fracing Fluid Waste 5,989.00 Bbl REUSE OTHER THAN ROAD SPREADING
2014 CHIEF OIL & GAS LLC Drilling Fluid Waste 2,243.33 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2014 CHIEF OIL & GAS LLC Drill Cuttings 1,823.53 Tons LANDFILL 301358
2015 CHIEF OIL & GAS LLC Fracing Fluid Waste 5,039.33 Bbl REUSE OTHER THAN ROAD SPREADING
2015 CHIEF OIL & GAS LLC Produced Fluid 27,402.77 Bbl REUSE OTHER THAN ROAD SPREADING
2015 CHIEF OIL & GAS LLC Fracing Fluid Waste 440.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CHIEF OIL & GAS LLC Fracturing Fluid Waste 120.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CHIEF OIL & GAS LLC Produced Fluid 7,837.72 Bbl REUSE OTHER THAN ROAD SPREADING
2017 CHIEF OIL & GAS LLC Produced Fluid 2,053.90 Bbl REUSE (AT WELL PAD)
2017 CHIEF OIL & GAS LLC Produced Fluid 262.30 Bbl REUSE OTHER THAN ROAD SPREADING
2018 CHIEF OIL & GAS LLC Produced Fluid 2,452.20 Bbl REUSE (AT WELL PAD)
2019 CHIEF OIL & GAS LLC Produced Fluid 2,777.79 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2275043 Primary Facility 2014-05-29 Preoperation Inspection Viol(s) Noted & Immediately Corrected The access road and associated BMPs were completed. The perimeter of the site was inspected and the silt sock had been installed as per the E&S plan and appeared to be functioning. There was a gap in the silt sock along the southeast perimeter of the Limit of Disturbance, near Sediment Trap 2 that present a potential to discharge sediment to an identified wetland area. The super-silt fence baffles in the Sediment Traps were improperly installed. As per the E&S plan and the E&S BMP manual (see Standard Construction Detail # 4-10), the fabric toe should be placed in the bottom of the trench, backfilled and compacted. The toe of the fabric of the super silt fences in both sediment traps was laid on the ground surface and cover with soil. This constitutes a violation of § 102.11(a). This violation was cited against the 113-20255 permit and was immediately corrected. No violations were cited against the 113-20260 or ESG29-113-14-0001.
2278469 Primary Facility 2014-06-11 Drilling/Alteration No Violations Noted
2280666 Primary Facility 2014-06-21 Drilling/Alteration No Violations Noted
2280781 Primary Facility 2014-06-23 Routine/Complete Inspection No Violations Noted
2292402 Primary Facility 2014-07-27 Drilling/Alteration No Violations Noted
2329064 Primary Facility 2014-12-15 Routine/Complete Inspection No Violations Noted
2344662 Primary Facility 2015-02-17 Routine/Complete Inspection No Violations Noted 3 Marcellus Shale natural gas wells drilled/fractured. Pipeline being hooked up today.
2376133 Primary Facility 2015-06-02 Routine/Complete Inspection No Violations Noted
2421261 Primary Facility 2015-11-02 Routine/Complete Inspection No Violations Noted Arrived on site at 13:00 and departed at 13:30. Weather conditions were partly cloudy ~60°F, with recent significant rainfall. No Chief representatives were present during the inspection.
2427792 Primary Facility 2015-11-23 Routine/Complete Inspection No Violations Noted Arrived @ 12:50. Weather sunny, cold and windy. There are three producing wells on location. Met with Jon Hafer (Chief) to check on a report of combustible gas on the 13-3/8” x 9-5/8” annulus of the WL SE Unit 1H.
2496279 Primary Facility 2016-06-27 Routine/Complete Inspection No Violations Noted Routine inspection conducted to assess overall site conditions. No Chief representatives were present.

Vegetative cover on site is greater than 70% in some areas, but less in others. Temporary erosion and sediment control BMPs are in place and in good repair. No evidence of accelerated erosion or sedimentation was observed.

According to the Department's records, a request for a 2-year extension of time for site restoration was received on 03/16/2016. As of the date of my inspection, this request has not yet been approved.

No violations were cited during this inspection.

2556810 Primary Facility 2017-01-30 Routine/Complete Inspection No Violations Noted Routine inspection to assess overall site conditions. No Chief representatives were present during the inspection.

Vegetative cover on site is greater than 70% in most places though some areas were obscured by snow cover, and temporary erosion and sediment control BMPs are in place. No evidence of accelerated erosion or sedimentation was observed.

This site was due for restoration in November 2015. According to the restoration schedule submitted by Chief, this site is anticipated to be restored during Spring 2018. While this proposed schedule has been acknowledged by the Department, Chief should still submit a request for a 2-year extension of time to restore the site in accordance with Title 58 Pa. C.S. § 3216 (relating to site restoration) (2012 Oil and Gas Act).

No violations were cited during this inspection.

2682048 Primary Facility 2018-01-12 Routine/Complete Inspection No Violations Noted Three wells in production phase. Three each sand and water separators within containment. Natural gas powered suction engine on location. No leaks detected from production equipment. No violations noted.
2811580 Primary Facility 2018-12-04 Routine/Complete Inspection No Violations Noted Arrived onsite for a routine inspection at 12:21; the weather was ~30°F, and calm.

There were 3 properly tagged Marcellus wells staged for production. All the well cellars were filled in with gravel. There were 3 GPUs, 3 produced water tanks, 1 compressor, and 1 freshwater tank onsite.

Two infiltration basins were onsite as PCSM. Both basins contained a fair amount of ice and snow. The rest of the area was free from snow and was greater than 70% vegetative cover. No E&S issues were observed at the time of inspection.

According to Department records the ESCGP for this pad expires on 3/23/19. It also appears that a 2-year site restoration extension was acknowledged on 10/5/18.

No violations were noted at the time of inspection.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2275043 697252 05/29/2014 2014-05-29 102.11 - Failure to design, implement or maintain BMPs to minimize the potential for accelerated erosion and sedimentation. Administrative