37-113-20219

Well Details

Well ID: 37-113-20219
Loading map...
Country: United States
State: Pennsylvania
County: Sullivan
Municipality: Elkland Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 149632
Farm/Lease Name: I HARVEY UNIT
License Status: Inactive
Spud Date: 2014-09-06
Permit Date: 2013-08-13
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.514494
Longitude: -76.679819

For data sources see[1][2][3]

Well History

Date Event
2013-08-13 New Permit Application
2014-07-30 Permit Renewal Application
2014-09-06 Performed Spud Operation
2014-12-13 Drilling Completion
2016-10-18 Inactive Well Request Granted
2017-04-27 Newly Drilled

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-01-07 2017-01-16 7,889 7,584,310 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Ethanol, 2,2',2"-nitrilotris-,
tris(dihydrogen phosphate) (ester), sodium salt
68171-29-9 30 0.00159 1180
Alpha olefins (petroleum), (C11-12) 64743-02-8 5 0.00009000 65
Carbonic acid, calcium salt 471-34-1 30 0.16256 120607
Water 7732-18-5 85 0.35822 265765
Ethylene glycol 107-21-1 30 0.00159 1180
Water 7732-18-5 40 0.00159 6947
Propargyl alcohol 107-19-7 10 0.00017 129
Crystallilne silica 14808-60-7 100 13.6975 10,162,200.0
Glutaraldehyde 111-30-8 5 0.00117 868
Methanol 67-56-1 45 0.01053 7815
Water 7732-18-5 40 0.00212 1573
Hydrochloric acid 7647-01-0 15 0.06322 46900
Acetophenone, thiourea, formaldehyde polymer 68527-49-1 30 0.00052 388
Hydrotreated light petroleum distillate 64742-47-8 30 0.16256 120607
Methanol 67-56-1 60 0.00105 776
Alcohols, (C10-16), ethoxylated 68002-97-1 30 0.00052 388
Water 7732-18-5 100 85.3088 63,291,100.0
Quaternary ammonium compound 68424-85-1 10 0.00234 1737
Fatty acid, tall-oil 61790-12-3 30 0.00052 388
Acrylamide sodium acrylate copolymer 25085-02-3 30 0.16256 120607
Methanol Biocide Nalco Champion Listed Below
Triethanolamine Tri Scale Inhibitor Nalco Champion Listed Below
Water Chief Oil & Gas Carrier/Base Fluid Listed Below
Hydrochloric Acid Halliburton Acidizing Listed Below
Ethoxylated Alcohols Haliburton Acid Inhibitor Listed Below
Acrylamide Acrylate Copolymer Haliburton Friction Reducer Listed Below
Sand Halliburton Proppant Listed Below

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2015 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2016 CHIEF OIL & GAS LLC 75,497.75 31 0.00 0 0.00 0
2017 CHIEF OIL & GAS LLC 2,944,293.23 337 0.00 0 0.00 0
2018 CHIEF OIL & GAS LLC 1,408,864.13 363 0.00 0 0.00 0
2019 CHIEF OIL & GAS LLC 1,000,621.24 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2015 CHIEF OIL & GAS LLC Drill Cuttings 117.53 Tons LANDFILL 301358
2015 CHIEF OIL & GAS LLC Fracing Fluid Waste 160.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123
2016 CHIEF OIL & GAS LLC Produced Fluid 3,244.46 Bbl REUSE OTHER THAN ROAD SPREADING
2017 CHIEF OIL & GAS LLC Produced Fluid 7,355.00 Bbl STORAGE PENDING DISPOSAL OR REUSE
2017 CHIEF OIL & GAS LLC Produced Fluid 16,150.55 Bbl REUSE (AT WELL PAD)
2017 CHIEF OIL & GAS LLC Produced Fluid 715.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 CHIEF OIL & GAS LLC Produced Fluid 2,571.24 Bbl REUSE (AT WELL PAD)
2019 CHIEF OIL & GAS LLC Produced Fluid 3,138.57 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2273028 Primary Facility 2014-05-22 Preoperation Inspection No Violations Noted 14:00 preoperational inspection. The pad is being constructed there are no gas well on this location. Frank Ferrana (J.P. Reilly construction contractors) working on site. Location does not have any significant drainage prblems, subsurface is shaley. Perimeter E&S controls are in place, ditches in place as per the plan, sediment retentionl basin in place. Temporary stabilziation good. There were some very minor earth slips along the base of the fill slope, these will be addressed during compaction.
2311410 Primary Facility 2014-10-08 Routine/Complete Inspection No Violations Noted
2434094 Primary Facility 2015-12-16 Routine/Complete Inspection No Violations Noted Arrived at 10:34, weather cold and cloudy. There were 3 wells on this location, 1 in production and the other two TD’ed.
2481009 Primary Facility 2016-05-04 Routine/Complete Inspection No Violations Noted The site currently has >70% coverage of perennial vegetation and temporary erosion and sediment control BMPs have been removed. No evidence of accelerated erosion or sedimentation was observed.

The electrical conductance of puddles was not screened due to the absence of puddles.

The Erosion and Sediment Control General Permit for this site expires on 01/01/2018, and no current well permits exist. Chief has indicated that it plans to partially restore the well pad by the autumn of 2017. In order to remain in compliance with the Department's regulations regarding site restoration (Title 58 Pa. C.S. § 3216), Chief should obtain a new drilling permit or request a 2-year extension of time for site restoration.

No violations were cited during this inspection.

2499048 Primary Facility 2016-06-30 Routine/Complete Inspection No Violations Noted Field monitoring did not detect methane on any annuli.
2509738 Primary Facility 2016-06-30 Routine/Complete Inspection No Violations Noted No combustible gas on either annulus.
2509747 Primary Facility 2016-08-04 Follow-up Inspection No Violations Noted Arrived at 09:00. Weather: cloudy, breezy, cooler. There were no company representatives on site at the time of this inspection. There were 3 wells on this location, 1 in production and the other two TD’ed. This follow-up inspection was prompted by Inactive Well Status applications for the I Harvey 1H and I Harvey 2H. Previously on 6/30/16, (IR 2499045) combustible gas was detected on the I Harvey Unit 2H at the 13-3/8” x 9-5/8” annulus. Typically, the 1” , 13-3/8” x 9-5/8” annular vent T’s into the 2” 13-3/8” x 9-5/8” annular vent, allowing for cross-contamination. To eliminate that possibility in this follow-up inspection, the annuli were open and isolated from each other prior to my arrival on site.

I Harvey Unit I H: 13-3/8” x 9-5/8”: 0%/volume combustible gas 9-5/8” x 5-1/2”: 0% volume combustible gas The result of this inspection is: NOVIO. Left location @ 10:00

2554457 Primary Facility 2017-01-23 Routine/Complete Inspection Pending Routine inspection to assess overall site conditions post-fracking operations. No Chief representatives were present.

The surface of the well pad and access road were extremely muddy due to recent rains, snowmelt, and heavy truck traffic. Recently installed compost filter sock was in place in the field on the downslope side of the access road. No filter medium was present along the upslope sock/ground surface interface as prescribed by the Erosion and Sediment Pollution Control Program Manual (Technical Guidance No. 363-2134-008, Detail 4-1, page 65)(E&S manual). The absence of this filter media allowed sediment to flow underneath the sock in several locations in the vicinity of the guard post. The sediment that flowed under the filter sock continued downslope a short distance and possibly outside of the limit-of-disturbance for the site, but did not affect any aquatic resources or result in a significant accumulation of sediment that would negatively impact land use at that location. Erosion and sediment

2647728 Primary Facility 2017-10-16 Routine/Complete Inspection No Violations Noted Three wells staged for production. Three each dehydration units within containment. No leaks detected. No violations noted.
2650766 Primary Facility 2017-10-23 Routine/Complete Inspection No Violations Noted Arrived at 14:08. Weather: overcast, windy. 3 producing wells onsite. Annuli open and venting to 550-gallon polytank. No combustibe gas detected at polytanks. 3 GPUs, 3 produced water tanks. 1 Harvey 3H adding foam. No violations observed.
2784684 Primary Facility 2018-10-03 Routine/Complete Inspection No Violations Noted Arrived onsite for a routine inspection. The pad size has been reduced and vegetation is established on restored area.

There are 3 properly tagged Marcellus wells staged for production. The well cellars contained water but not bubbling was observed.

There are also 3 GPUs and 3 produced water tanks onsite and in secondary containment. There was very little water in secondary containment. A small amount in the GPU containment had a conductivity of 150.8 µS/cm.

Overall the site is >70% vegetation and no E&S issues were observed. The E&S inspection log and other pertinent paperwork was present onsite. The department recommends inspecting and repairing equipment and storage as needed. At the time of inspection there was some minor rusting on the produced water tanks (Photo #5).

No violations noted.

For data sources see[8]

References