X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-105-21906

Well Details

Well ID: 37-105-21906
Loading map...
Country: United States
State: Pennsylvania
County: Potter
Municipality: Pike Township
Operator Name: JKLM ENERGY LLC
Well Pad ID:
Farm/Lease Name: JUDSON HOLLOW 302-6V
License Status:
Spud Date:
Permit Date: 2017-10-31
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: Yes
Latitude: 41.810941
Longitude: -77.697234

For data sources see[1][2][3]

Well History

Date Event
2017-10-31 New Permit Application

For data sources see[4]



Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2684008 Primary Facility 2018-01-16 Routine/Complete Inspection No Violations Noted A preconstruction meeting for the Sweden Valley Tank Farm (ESG29-105-17-0021), The Judson Hollow 302 Well Pad (ESG29-105-17-0011) and the Sweden Valley 104 Well Pad (ESG29105-17-0022) was conducted on 1/16/2018 @ 1100 hours. The preconstruction meeting was held at the JKLM Office located in Coudersport due to inclement weather. Present for the meeting was Jeff Long, JKLM and contractors ESK Inc. and JL Watts.

JKLM is awaiting approval of drilling permits for the Headwaters 104 Well Pad, therefore construction will most likely begin next week at the Sweden Valley Tank Farm. This site will be freshwater until a multi-use permit is obtained from the NCRO.

All three ESCGP E&S control plans show Compost Filter Sock (CFS), but JKLM stated they will be using Wood Chip Filter Berms (WCFB). Please be aware WCFB are not approved for use in EV watersheds. Wood chip filter berms shall not be located in areas of concentrated flow or used to construct sediment traps or other impoundments. A 6" thick layer of compost sha

2781374 Primary Facility 2018-09-28 Preoperation Inspection No Violations Noted The DEP conducted a PRE-SPUD inspection of the JKLM Judson Hollow 302 well pad located in Pike Twp, Potter Co. on 9/28/2018 @ 1330 hours. The weather was 63 degrees, winds NE 9mph,humidity 78%. No personnel were onsite during this inspection.

The site consists of an access road, multi-well pad and associated E&S controls. At the time of this inspection the well pad slopes and topsoil stockpile appeared stabilized by heavy mulch and ~10% vegetative cover of Annual Rye grass. No water was observed in ST-2 off the northern corner of the pad. A small amount of water was observed in ST-1 off the southern side of the pad.

Operator is reminded, a 6" thick layer of compost shall added to the upslope side of any wood chip filter berm located in an HQ watershed. No compost was observed on the chip filter berms during today's inspection.

This inspection meets the requirements of This inspection meets the requirements of 58 Pa. C.S. 3258 (a.1) regarding a "pre-operational inspection".

No violations are noted at

For data sources see[5]

References