37-105-21896

Well Details

Well ID: 37-105-21896
Loading map...
Country: United States
State: Pennsylvania
County: Potter
Municipality: Sweden Township
Operator Name: JKLM ENERGY LLC
Well Pad ID: 154232
Farm/Lease Name: SWEDEN VALLEY 107-2HU
License Status:
Spud Date: 2017-10-12
Permit Date: 2017-08-07
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 41.739436
Longitude: -77.899986

For data sources see[1][2][3]

Well History

Date Event
Deviated
2017-08-07 New Permit Application
2017-10-09 Performed Spud Operation
2018-03-19 Drilling Completion

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-05-16 2018-06-15 11,360 11,645,700 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand (Proppant) Keane Proppant Crystalline silica: Quartz (SiO2) 14808-60-7 100 14.7298 16,990,400.0
Hydrochloric Acid (7.5%) Keane Acid Inhibitor Hydrochloric Acid 7647-01-0 7.5 0.0711071 82019.9
Water 7732-18-5 92.5 0.876987 1,011,580.0
KAI-12 Keane Acid Inhibitor Methanol 67-56-1 90 0.00364987 4210.01
isoproyl alcohol 67-63-0 5 0.00020277 233.889
Alcohols, C7-9-iso-, C8-rich 68526-83-0 5 0.00020277 233.889
ethylbenzene 100-41-4 1 0.00004055 46.778
Fatty imidazoline 61790-69-0 5 0.00020277 233.889
prop-2-yn-1-ol 107-19-7 5 0.00020277 233.889
xylene 1330-20-7 5 0.00020277 233.889
Water JKLM Carrier/Base Fluid Water 7732-18-5 100 84.2529 97,183,200.0
KFR-20 Keane Friction Reducer oleic acid diethanolamide 93-83-4 2 0.00119035 1373.03
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00119035 1373.03
Water 7732-18-5 45 0.0267828 30893.2
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.0119035 13730.3
copolymer of 2-propenamide 69418-26-4 30 0.0178552 20595.4
ammonium chloride 12125-02-9 1 0.000595174 686.515
Other Chemical(s) Listed Above See Trade Name(s) List ammonium chloride 12125-02-9 1 0.000595174 686.515
isoproyl alcohol 67-63-0 5 0.00020277 233.889
Water 7732-18-5 92.5 0.876987 1,011,580.0
copolymer of 2-propenamide 69418-26-4 30 0.0178552 20595.4
oleic acid diethanolamide 93-83-4 2 0.00119035 1373.03
oleic acid diethanolamide 93-83-4 2 0.00007353 84.819
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.0119035 13730.3
prop-2-yn-1-ol 107-19-7 5 0.00020277 233.889
Fatty imidazoline 61790-69-0 5 0.00020277 233.889
ethylbenzene 100-41-4 1 0.00004055 46.778
Citric acid 77-92-9 30 0.000585229 675.044
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00007353 84.819
copolymer of 2-propenamide 69418-26-4 20 0.000735334 848.186
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00119035 1373.03
xylene 1330-20-7 5 0.00020277 233.889
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.000735334 848.186
Alcohols, C7-9-iso-, C8-rich 68526-83-0 5 0.00020277 233.889
KFR-23 Keane Friction Reducer Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00007353 84.819
copolymer of 2-propenamide 69418-26-4 20 0.000735334 848.186
oleic acid diethanolamide 93-83-4 2 0.00007353 84.819
Water 7732-18-5 50 0.00183834 2120.47
Distillates (petroleum), hydrotreated light 64742-47-8 20 0.000735334 848.186
KFEAC-30 Keane Iron Control Citric acid 77-92-9 30 0.000585229 675.044
Acetic acid 64-19-7 5 0.00009754 112.507

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 JKLM ENERGY LLC 0.00 0 0.00 0 0.00 0
2018 JKLM ENERGY LLC 856,334.00 85 0.00 0 0.00 0
2019 JKLM ENERGY LLC 2,641,113.00 365 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 JKLM ENERGY LLC Produced Fluid 292.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2017 JKLM ENERGY LLC Produced Fluid 65.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2017 JKLM ENERGY LLC Drill Cuttings 200.69 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 147.18 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 JKLM ENERGY LLC Soil Contaminated by Oil & Gas Related Spills 52.31 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Produced Fluid 2,976.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2018 JKLM ENERGY LLC Produced Fluid 3,346.13 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2018 JKLM ENERGY LLC Produced Fluid 967.50 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Produced Fluid 38,105.25 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2018 JKLM ENERGY LLC Waste Water Treatment Sludge 32.53 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 8.00 Bbl REUSE (AT WELL PAD)
2018 JKLM ENERGY LLC Drill Cuttings 1,554.05 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 88.98 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 JKLM ENERGY LLC Synthetic Liner Materials 26.48 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Soil Contaminated by Oil 52.31 Tons LANDFILL 301358
2018 JKLM ENERGY LLC Other Oil & Gas Wastes 32.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Produced Fluid 1,927.82 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2019 JKLM ENERGY LLC Produced Fluid 5,390.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 926.25 Bbl INJECTION DISPOSAL WELL 34-133-24096
2019 JKLM ENERGY LLC Other Oil & Gas Wastes 32.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 JKLM ENERGY LLC Produced Fluid 815.00 Bbl REUSE (AT WELL PAD)
2019 JKLM ENERGY LLC Produced Fluid 445.83 Bbl STORAGE PENDING DISPOSAL OR REUSE WMGR123NC038
2019 JKLM ENERGY LLC Produced Fluid 1,427.29 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 JKLM ENERGY LLC Produced Fluid 360.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2019 JKLM ENERGY LLC Soil Contaminated by Oil & Gas Related Spills 24.56 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 142.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR119
2019 JKLM ENERGY LLC Soil Contaminated by Oil 24.56 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Other Oil & Gas Wastes 665.00 Bbl REUSE (AT WELL PAD)
2019 JKLM ENERGY LLC Produced Fluid 1,963.75 Bbl INJECTION DISPOSAL WELL 34-133-24189
2019 JKLM ENERGY LLC Waste Water Treatment Sludge 10.55 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Produced Fluid 1.80 Tons LANDFILL 301358
2019 JKLM ENERGY LLC Synthetic Liner Materials 12.81 Tons LANDFILL 301358

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2617049 Primary Facility 2017-07-18 Routine/Partial Inspection No Violations Noted On 7/18/17 at 1323 hrs I attended a preconstruction meeting for the Sweden Valley 107 well site. JKLM representatives, Jeff Long and John Manuel, and J.L. Watts representative, John Watts, were present. CB&I developed the Erosion and Sediment (E&S) control plan and J.L. Watts is the construction contractor.

We reviewed the E&S drawing. Site drainage is to an unnamed tributary to Nelson Run, which is designated as a High Quality stream. A majority of the access road was constructed under the Sweden Valley 106 ESCGP. The access road for the 107 pad will come off the existing access road and is 200 feet in length. The site will consist of a well pad (350 feet x 500 feet) and a sediment basin located off the northwest corner of the pad. The pad will be soil cemented for stability. The E&S drawing shows that a wash rack is to be installed on the access road. JKLM would prefer to install an additional 50 feet of rock constructed entrance in lieu of the wash rack; this is an acceptable alternative when a sediment

2633721 Primary Facility 2017-09-06 Preoperation Inspection No Violations Noted On 9/6/17 at 0938 hrs I conducted a preoperational inspection at the Sweden Valley 107 well site. It was mostly cloudy and 61 degrees F.

I observed the site and the routine Erosion and Sediment (E&S) control inspection log. Earth disturbance is complete. The pad surface and access road will be soil cemented and rocked within the next week or so. E&S controls are installed and disturbed areas have been stabilized with seed and mulch or erosion control blanket; seed has germinated in some areas.

Cellars have not yet been installed. Well permits for the Sweden Valley 107 1HU, 2HU, 3HM and 4HB have been issued.

The last routine E&S inspection was conducted on 8/30/17. No violations are cited during this inspection. I concluded the inspection at 1052 hrs. TLT

2650302 Primary Facility 2017-10-19 Routine/Complete Inspection No Violations Noted Well is conductor only. Well was drilled and cemented on 10-12-17.
2695947 Primary Facility 2018-02-15 Routine/Complete Inspection No Violations Noted The Department of Environmental Protection (DEP) inspected the JKLM Sweden Valley 107 well pad located in Sweden Twp., Potter Co. on 2/15/2018 @1300 hours. The weather was 48 degrees and sunny causing accumulated snow to melt and the pad surface and access road to be very wet/muddy. JKLM representatives Jon Manuel and Ron Hall were present for my inspection. The H&P 500 flex rig is onsite and is currently drilling the 1HU well. The rig was at a depth of 11,474’ feet at the time of my inspection. Mr. Hall stated no issues have been encountered. The rig will be drilling 4 wells while onsite the 1HU, 2HU, 3HM and 4HB. Fluid was observed accumulating along the eastern side of the pad-wide containment. Fluid in containment had a field measured conductivity of between 6.82 mS/cm and 8.28 mS/cm. A puddle on the ground surface approximately 1-2 feet off the edge of containment had an elevated conductivity of 7.23 mS/cm. Additional screening of the surrounding area showed the elevated area to be isolated. A vac truck
2719487 Primary Facility 2018-04-17 Routine/Complete Inspection No Violations Noted At the time of this inspection the drilling of this well was complete and the drilling rig was rigging down and being moved.
2730075 Primary Facility 2018-05-15 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM-Sweden Valley 107 well pad located in Sweden Township, Potter County. The weather was 77° mostly cloudy with severe thunderstorms in the area, winds W 12 mph, 61% humidity. Chris Wiley, JKLM was present onsite.

JKLM was preparing to frack the 1HU, 2HU, 3HU and 4 HB with contractor Keane Frack. Mr. Wiley stated they were hoping to begin fracking later this afternoon. The onsite AST, containment and E&S controls were observed. No puddles or staining was observed around the AST. All duckponds observed appeared dry. All observed puddles, on the pads surface, were measured for field conductivity and found to be within normal range. Rain water was accumulating inside the northern edge of the primary containment. Mr. Wiley was informed of the finding. Due to severe thunderstorms and the potential for heavy precipitation, storage capacity of primary containment should be monitored.

A sheen and bubbles/foam were observed in water standing in the E&S channels in th

2735329 Primary Facility 2018-05-30 Routine/Complete Inspection No Violations Noted At the time of this inspection this well stimulation had not started
2738194 Primary Facility 2018-06-06 Routine/Complete Inspection No Violations Noted At the time of this inspection there was 16 of the39 total stages completed. Additional information on averages of all other pressures and rates was not available at this time.
2738623 Primary Facility 2018-06-06 Incident- Response to Accident or Event Violation(s) Noted The DEP conducted an INCDENT inspection of the JKLM – Sweden Valley 107 well pad located in Sweden Twp., Potter Co. @ 1045 hours on 6/6/2018 in response to spill#334721 reported to the DEP on 6/5/2018 @1534 hours. The weather was 58 degrees and overcast.

A representative from JKLM contractor Whipper Hill Consulting was onsite conducting a grid screening of the impacted area. The following information was provided.

On 6/5/2018, sometime between 1000 – 1330 hours, a contractor punctured the pad-wide containment beneath the sand boxes located along the northern edge of containment. An unknown volume of fluid exhibiting an elevated conductivity flowed to the northern edge of containment, thought to be the “low spot”, where it exited the puncture causing a puddle to form outside of containment. The representative stated the puddle had a field measured conductivity of >20mS/cm. A vacuum truck was dispatched to remove the standing liquid from the pad surface.

The initial soil conductivity of the saturated pad s

2745383 Primary Facility 2018-06-25 Routine/Complete Inspection No Violations Noted At the time of this inspection the hydraulic fracturing of this well was complete.
2775110 Primary Facility 2018-09-14 Administrative/File Review No Violations Noted On September 6, 2018 Environmental Cleanup and Brownsfield program issued the state wide health final report approval for the release that occurred on June 5, 2018 documented in a June 6, 2018 inspection (IR# 2738623). All violations associated With this release are considered closed.
2783176 Primary Facility 2018-10-01 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM - Sweden Valley 107 well pad located in Sweden Twp., Potter Co. on 10/1/2018 @1240 hours. DEP Env Trainee, was present onsite for the inspection. The weather was 73 degrees, partly sunny.

Company personnel onsite appeared to be repairing a dehydration unit that had sprayed glycol onto the pad surface on 9/28/2018. The glycol release was below the reportable limit (but had been reported to the DEP), and appeared remediated by the time of this inspection.

The pad surface appeared very wet and muddy around the well heads, AST and main traffic areas. Puddles on the pad surface, near the production tanks, tested for field conductivity with an Oakton Multi-Parameter PCTestr and a Groline soil conductivity meter measured ~1000 uS/cm.

A number of flowback tanks were arranged, on secondary containment, along the eastern side of the pad. Standing fluid in the secondary containment had a field measured conductivity of "Over Range" or >20.00mS/cm. A large wet/damp

2802111 Primary Facility 2018-11-13 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was drilled,stimulated, flow-backed and was in production status. Flow-back is done before well is put into production as part of production preparation. The pressure reading on a mechanical gauge on this well at this inspection was 3900 pounds per square inch. Flow- back was started on 9/12/18 and completed on 10/23/18. No violations were noted at this inspection.
2820218 Primary Facility 2018-12-20 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM Sweden Valley 107 well pad located in Sweden Twp, Potter Co on 12/20/2018 @1230 hours. The weather was overcast, 34 degrees.

The well pad is currently setup for flowback/production. Personnel were present onsite to monitor transfers from/to the Aboveground Storage Tank (AST). A temporary fluid line was observed connecting the production tanks to the AST, but did not appear to be in use. Fluid with a field measured conductivity of "Over Range" or >19.99 mS/cm was observed in the production tank containment. Puddles screened on the pad surface measured <1000uS/cm.

Violations from an inspection dated 10/29/2018, remain outstanding at this site from a previous release. Site remediation has been performed and a Remediation Action Completion Report has been submitted to DEP’s Environmental Cleanups and Brownfields program for review. The outstanding violations will be closed once attainment with Act 2 standards has be confirmed.

2846825 Primary Facility 2019-02-28 Routine/Complete Inspection No Violations Noted The DEP conducted a routine inspection of the JKLM - Sweden Valley 107 Well Pad located in Sweden Twp, Potter Co. on 2/282019 @1230 hours. The weather was 23 degrees, sunny, winds N 4mph,63% humidity, 2-3" of snow deposited over the previous 24 hrs. The well pad appears to be setup for flowback/production. 4 wells were observed connected to sand traps and a gas buster. 17 orange roll-off tanks were observed on containment on the along the south side of the well pad.
2848059 Primary Facility 2019-03-05 Routine/Complete Inspection No Violations Noted At the time of this inspection this well was in production. There are three (3) annulus vents that are vented to surface. These annulus vents were checked for combustible gas on each annulus vent. Results of this testing were 0 LEL ( lower explosion limit) and 0 Methane on vent 18 x 13 and 0 LEL and 0 Methane on vent 13 x 9 and 0 LEL and 0 Methane on the 9 x 5. A gauge on the well showed a pressure of 2600 psi ( pounds per square inch ) . No violations were noted at this inspection.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2738623 819221 2018-06-06 2018-09-06 CSL 402(b) Environmental Health & Safety A release of a regulated substance to the ground surface and perimeter E&S controls constitutes a potential to pollute Waters of the Commonwealth, a violation of Clean Streams Law 402(b).
2738623 819222 2018-06-06 2018-09-06 78a56(a) Environmental Health & Safety The Operator failed to contain a regulated substance in a tank, series of tanks or other storage structure approved by the Department, whereby it exited the pad-wide containment through a punctured hole causing a release to the ground surface and perimeter E&S BMPs.
2738623 819223 2018-06-06 2018-09-06 SWMA 301 Environmental Health & Safety The Operator failed to properly store, transport, process or dispose of residual waste.

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
819221 364709 NOV - Notice of Violation 2018-09-06
819222 364709 NOV - Notice of Violation 2018-09-06
819223 364709 NOV - Notice of Violation 2018-09-06