37-081-21404

Well Details

Well ID: 37-081-21404
Loading map...
Country: United States
State: Pennsylvania
County: Lycoming
Municipality: Lewis Township
Operator Name: SENECA RESOURCES CO LLC
Well Pad ID: 150327
Farm/Lease Name: SRC GAMBLE 23H 51329
License Status:
Spud Date:
Permit Date: 2013-12-27
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 41.388833
Longitude: -77.034508

For data sources see[1][2][3]

Well History

Date Event
2013-12-27 New Permit Application
2014-02-06 Performed Spud Operation
2014-04-13 Drilling Completion
2014-06-13 Perforation
2014-12-23 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2014-06-26 2014-07-04 8,132 7,974,880 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 7.5% HydroChloric Acid Trican Acid Hydrochloric Acid HCl 7647-01-0 7.5 0.0484782 0
FEAC 20 Trican Iron Control Acetic acid 64-19-7 50 0.00049184 0
Citric acid 77-92-9 30 0.0002951 0
AL-7NR Trican Corrosion Inhibitor Prop-2-yn-1-ol 107-19-7 1 0.00001389 0
Sl-7 Trican Scale Inhibitor Ethylene glycol 107-21-1 30 0.00803882 0
FR-15 Trican Friction Reducer Distillates (petroleum), Hydrotreated Light 64742-47-8 25 0.0181029 0
Proprietary Amide Proprietary 2.5 0.00181029 0
Water Seneca Resources Carrier/Base Fluid Water 7732-18-5 100 88.6407 0
MBC 516 Trican Biocide Didecyl dimethyl ammonium chloride 7173-51-5 8.3 0.00079431 0
Ethanol 64-17-5 2.8 0.00026796 0
Glutaraldehyde 111-30-8 27 0.0025839 0
N-alkyl dimethyl benzyl ammonium chloride 68424-85-1 5.5 0.00052635 0
Proppant 80/100 Oklahoma Trican Proppant Silica 14808-60-7 100 0.837516 0
Proppant 30/50 Ottawa Trican Proppant Crystalline silica (quartz) 14808-60-7 100 5.24009 0
Proppant 40/70 Ottawa Trican Proppant Crystalline silica (quartz) 14808-60-7 100 5.20027 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2014 SENECA RESOURCES CO LLC 0.00 0 0.00 0 0.00 0
2015 SENECA RESOURCES CO LLC 436,701.48 26 0.00 0 0.00 0
2016 SENECA RESOURCES CO LLC 3,343,854.70 223 0.00 0 0.00 0
2017 SENECA RESOURCES CO LLC 3,414,159.55 365 0.00 0 0.00 0
2018 SENECA RESOURCES CO LLC 2,010,759.21 359 0.00 0 0.00 0
2019 SENECA RESOURCES CO LLC 1,149,906.78 267 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2014 SENECA RESOURCES CO LLC Drill Cuttings 1,460.83 Tons RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR097R017
2015 SENECA RESOURCES CO LLC Produced Fluid 301.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW011
2016 SENECA RESOURCES CO LLC Produced Fluid 897.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2016 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 27.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW005
2016 SENECA RESOURCES CO LLC Produced Fluid 627.00 Bbl REUSE OTHER THAN ROAD SPREADING
2016 SENECA RESOURCES CO LLC Produced Fluid 5,355.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NW011
2017 SENECA RESOURCES CO LLC Produced Fluid 2,440.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2017 SENECA RESOURCES CO LLC Produced Fluid 2,098.50 Bbl REUSE (AT WELL PAD)
2018 SENECA RESOURCES CO LLC Produced Fluid 1,122.50 Bbl REUSE (AT WELL PAD)
2018 SENECA RESOURCES CO LLC Produced Fluid 465.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 11.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW005
2019 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 38.50 Bbl INJECTION DISPOSAL WELL 34-155-23795
2019 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 119.40 Bbl REUSE (AT WELL PAD)
2019 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 189.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 SENECA RESOURCES CO LLC Produced Fluid 307.50 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW011
2019 SENECA RESOURCES CO LLC Produced Fluid 1,495.00 Bbl REUSE (AT WELL PAD)
2019 SENECA RESOURCES CO LLC Other Oil & Gas Wastes 16.00 Bbl RESIDUAL WASTE TRANSFER FACILITY WMGR123NC039
2019 SENECA RESOURCES CO LLC Produced Fluid 1,532.50 Bbl RESIDUAL WASTE TRANSFER FACILITY WMGR123NC039
2019 SENECA RESOURCES CO LLC Synthetic Liner Materials 4.48 Tons LANDFILL 301358

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2237874 Primary Facility 2014-01-17 Follow-up Inspection No Violations Noted outstanding violations cited to ESG13-081-0054 for stream crossing.
2243750 Primary Facility 2014-01-31 Preoperation Inspection No Violations Noted access road/pad construction complete. stream #1 impacts need to be accounted for in new permit & mitigation. outstanding encroachment violations to ESCGP
2244761 Primary Facility 2014-02-11 Drilling/Alteration No Violations Noted
2249188 Primary Facility 2014-02-28 Drilling/Alteration No Violations Noted
2251624 Primary Facility 2014-03-05 Incident- Response to Accident or Event No Violations Noted 15-20 barrels synthetic oil-based mud spilled to containment; being cleaned-up. No Vio.
2264769 Primary Facility 2014-04-02 Drilling/Alteration No Violations Noted
2266698 Primary Facility 2014-04-09 Drilling/Alteration No Violations Noted
2275292 Primary Facility 2014-05-22 Routine/Partial Inspection No Violations Noted Routine Partial Inspection with Dan Harvey (DEP) and Kristin Brown (DEP); 5/22/2014.
2299542 Primary Facility 2014-08-21 Routine/Complete Inspection No Violations Noted Routine Inspection; 8/21/2014.
2419749 Primary Facility 2015-10-27 Routine/Complete Inspection No Violations Noted Weather calm, cloudy, cool. Arrived @ 14.35. There were 2 wells on the pad .
2440088 Primary Facility 2015-12-23 Routine/Complete Inspection No Violations Noted At the time of the inspection the pipeline had just been connected to the well pad. The pipeline was installed along the access road and seeded and stabilized with straw mulch. No E&S issues were observed onsite. Some leftover rock was stockpiled on the well pad from bedrock encountered digging trench.
2512139 Primary Facility 2016-08-15 Routine/Complete Inspection No Violations Noted Routine Inspection; 8/15/2016.

Dan Harvey (DEP) and I met with Kirk Gregory (Seneca) at 14:00 to review the mitigation project related to the access road. The mitigation project involves installing Filtrexx ® Runoff Diversion’s along the logging road with rock outlet protection. We all agreed that grading would be necessary and acceptable to facilitate the installation of the BMP’s along the logging road. After walking the logging road we also agreed that Filtrexx ® Runoff Diversion #1 at the western edge of the project could be moved east of the existing stream channel. The designed location of Runoff Diversion #1 is currently ineffective and unnecessary as the stream channel is very incised. This change appears to be based on changing conditions (erosion) onsite. At the time we requested that a copy of the red-lined plans be provided depicting the shift of Filtrexx ® Runoff Diversion #1 (attached). No Violations Noted.

2605530 Primary Facility 2017-06-13 Routine/Complete Inspection No Violations Noted Weather: Sunny. Arrived @ 14:00. There are two producing wells on this pad in a linear array: the 23H and the 20H. Each well had three ¼-inch stainless steel candycane vents. Two of the vents were unlabeled, and their candycane outlets were below the cellar grate, no methane was detected on these annuli. On each well the 9”x5” vent was labeled and shut. A 2” green flexible hose appeared to be connecting the 9” x 5” annulus to a 2100-gallon poly tank.

23H, top gauge 1146 psi, digital Cellar filled with water, no bubbling observed. 20H, top gauge 1078 psi, digital Guggling/bubbling appeared to be coming from the green hose, which also appeared to be moving in response to the gurgling. Scheduled a follow-up inspection with Glenn Heckman (Sr Production Engineer) on 6/27/17, to inspect this further. Left @ 14:30

2610652 Primary Facility 2017-06-27 Routine/Complete Inspection No Violations Noted
2682906 Primary Facility 2018-01-11 Routine/Complete Inspection No Violations Noted Routine inspection; 1/11/2018.

I entered the site off Rose Valley Road. The area south of the access road shares disturbed area with the NFG pipeline. This area had been disturbed and is now stabilized with straw mulch. The access road and pad area are stabilized and PCSM has been implemented. Two wells are onsite and the annuli are plumbed to a poly tank. Foamer, defoamer, and methanol are covered and stored in containment for injection. The production tanks are in good condition and are in containment. No violations noted.

2835695 Primary Facility 2019-02-05 Routine/Complete Inspection No Violations Noted Weather was 50° and sunny at time of inspection. There were no Seneca resources representatives on location at time of inspection. Well pad had 7 cellars recently set in place in preparation of 7 new wells. Conductor casing was not yet set on those new wells. Well had digital pressure monitoring equipment attached to the production tubing and production casing at time of inspection. Tubing pressure was 1102 psi and casing pressure was 1256 psi. There were 3 annulus vents plumbed to surface that were labeled 20x13, 13x9 and 9x5. The vents had 0% combustible gas detected at time of inspection. No violations were noted at time of inspection.
2844639 Primary Facility 2019-02-26 Routine/Complete Inspection No Violations Noted Weather was 24 degrees and sunny at time of inspection. Met with Seneca representative Sam Neher on location. Well is in production. There is digital pressure monitoring equipment attached to the production tubing and production casing. Production casing pressure is reading 1244 psi. The production tubing is reading 1138 psi. Well has 3 annular vents plumbed to surface labeled 13x20, 9x13 and 9x5. 100% LEL of combustable gas was detected on the 9x5 annulus. 0% combustable gas is detected anywhere around the well at time of inspection. No violation noted at time of inspection.

For data sources see[8]