37-019-22453

Well Details

Well ID: 37-019-22453
Loading map...
Country: United States
State: Pennsylvania
County: Butler
Municipality: Franklin Township
Operator Name: XTO ENERGY INC
Well Pad ID: 152218
Farm/Lease Name: CRATTY B UNIT
License Status:
Spud Date:
Permit Date: 2017-04-03
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 40.914436
Longitude: -80.015367

For data sources see[1][2][3]

Well History

Date Event
2017-04-03 New Permit Application
2017-09-18 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-02-19 2018-02-26 5,593 11,990,400 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 CJENERGY-Anionic Polymer-44 Proprietary 5 0.000319 0
Titanium Oxide 13463-67-7 0.1 0.001446 0
Triethyl Phosphate 78-40-0 2.5 0.00004300 0
CJENERGY-Polymer-43 Proprietary 30 0.001913 0
Distillates (Petroleum), Hydrotreated Light 64742-47-8 35 0.023342 0
Water 7732-18-5 96 0.018686 0
Sodium Sulfate 7757-82-6 1 0.00006400 0
Water 7732-18-5 28.5 0.006109 0
Ethylene Glycol 107-21-1 40 0.000691 0
Tar bases, quinoline derivs, benzyl chloride-quaternized 72480-70-7 15 0.000259 0
Iron Oxide 1309-37-1 0.1 0.001446 0
2-Propenoic acid, polymer with 2-propenamide, sodium salt 25987-30-8 30 0.020008 0
1-DECANOL 112-30-1 5 0.00008600 0
Ethylene Glycol 107-21-1 5 0.003335 0
Aluminum Oxide 1344-28-1 1.1 0.041308 0
Aluminum Oxide 1344-28-1 1.1 0.01591 0
Aluminum Oxide 1344-28-1 1.1 0.026835 0
Polyethylene glycol 25322-68-3 50 0.010718 0
Water 7732-18-5 30 0.000518 0
Poly(oxy-1,2-ethanediyl),alpha-(4-nonylphenyl)-omega
hydroxy-, branched
127087-87-0 5 0.00008600 0
Sorbitan Monooleate 1338-43-8 2 0.001334 0
Acrylamide as residual 79-06-1 0 0 0
Isopropanol 67-63-0 2.5 0.00004300 0
2-Propenamide as residual 79-06-1 0.1 0.00006700 0
Cinnamaldehyde 104-55-2 15 0.000259 0
Methanol 67-56-1 1 0.000195 0
Crystalline Silica, quartz 14808-60-7 99.9 1.44492 0
Ammonium Sulfate 7783-20-2 30 0.001913 0
2,2-Dibromo-3-nitrilo-propionamide (DBNPA) 10222-01-2 30 0.006431 0
Monoethanolamine hydrochloride 2002-24-6 2 0.000389 0
Ethoxylated Sorbitan Monooleate 9005-65-6 1 0.000667 0
Titanium Oxide 13463-67-7 0.1 0.00244 0
Water 7732-18-5 92.5 0.896574 0
Poly(oxy-1,2-ethandiyl), alpha-isodecyl-omega-hydroxy-phosphat
e
108818-88-8 2 0.001334 0
Iron Oxide 1309-37-1 0.1 0.003755 0
Sodium Acetate Anhydrous 127-09-3 3 0.002001 0
Urea 57-13-6 5 0.000319 0
2-Butoxyethanol 111-76-2 15 0.000259 0
1-OCTANOL 111-87-5 2.5 0.00004300 0
Alcohols, C12-15-branched and linear,
ethoxylated propoxylated
120313-48-6 2 0.001334 0
Water 7732-18-5 30 0.020008 0
Crystalline Silica, quartz 14808-60-7 99.9 2.43712 0
CJENERGY-Phosphate-00040 Proprietary 6 0.001168 0
Ammonium Chloride 12125-02-9 2 0.000389 0
Titanium Oxide 13463-67-7 0.1 0.003755 0
Crystalline Silica, quartz 14808-60-7 99.9 3.75152 0
Tar Bases, Quinoline Derivs. 68513-87-1 1 0.00001700 0
Water 7732-18-5 100 0.006376 0
Iron Oxide 1309-37-1 0.1 0.00244 0
Dimethylformamide 68-12-2 20 0.000345 0
Hydrochloric Acid 7647-01-0 7.5 0.072695 0
BIO-CLEAR 2000 C&J Energy Services Biocides Listed Below Listed Below 0 0 0
Sand C&J Energy Services Sand - Bulk - Pennsylvania Listed Below Listed Below 0 0 0
HC-7.5 C&J Energy Services Bulk Acid Listed Below Listed Below 0 0 0
FR-27 C&J Energy Services PA-Proprietary Listed Below Listed Below 0 0 0
SI-6 PA-Only C&J Energy Services PA-Proprietary Listed Below Listed Below 0 0 0
CI-3 C&J Energy Services Acid Corrosion Inhibitors Listed Below Listed Below 0 0 0
Water XTO Energy/ExxonMobil Carrier Fluid Water 7732-18-5 100 91.2738 0
FR-16 C&J Energy Services Friction Reducer Listed Below Listed Below 0 0 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2018 XTO ENERGY INC 164,738.85 75 0.00 0 1,506.80 75
2019 XTO ENERGY INC 1,153,723.12 365 0.00 0 5,904.05 365

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 XTO ENERGY INC Drilling Fluid Waste 200.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2017 XTO ENERGY INC Drill Cuttings 426.06 Tons LANDFILL 100585
2018 XTO ENERGY INC Soil Contaminated by Oil 3.28 Tons RESIDUAL WASTE PROCESSING FACILITY 101674
2018 XTO ENERGY INC Produced Fluid 361.69 Bbl INJECTION DISPOSAL WELL 34-133-24096
2018 XTO ENERGY INC Produced Fluid 214.52 Bbl INJECTION DISPOSAL WELL 34-133-24189
2018 XTO ENERGY INC Synthetic Liner Materials 7.04 Tons RESIDUAL WASTE PROCESSING FACILITY 101674
2018 XTO ENERGY INC Synthetic Liner Materials 18.63 Tons LANDFILL 100585
2018 XTO ENERGY INC Drill Cuttings 652.41 Tons LANDFILL 100585
2018 XTO ENERGY INC Soil Contaminated by Oil & Gas Related Spills 3.28 Tons RESIDUAL WASTE PROCESSING FACILITY 101674
2018 XTO ENERGY INC Synthetic Liner Materials 4.99 Tons LANDFILL 100434
2018 XTO ENERGY INC Waste Water Treatment Sludge 35.49 Tons RESIDUAL WASTE PROCESSING FACILITY 101674
2018 XTO ENERGY INC Produced Fluid 7,641.08 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 XTO ENERGY INC Produced Fluid 10,993.70 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2019 XTO ENERGY INC Produced Fluid 2,628.00 Bbl INJECTION DISPOSAL WELL 34-133-24096
2019 XTO ENERGY INC Produced Fluid 2,864.12 Bbl INJECTION DISPOSAL WELL 34-133-21076
2019 XTO ENERGY INC Produced Fluid 5,253.30 Bbl INJECTION DISPOSAL WELL 34-133-24189

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2587867 Primary Facility 2017-04-26 Routine/Partial Inspection No Violations Noted
2639165 Primary Facility 2017-09-18 Routine/Partial Inspection No Violations Noted At the time of inspection, Soilmec is onsite using an auger rig to drill out cellar on the 3H well. Cellar for this well is set, but not cemented yet. This should take place today. Hole for conductor has not been started yet so well has not been technically spud yet. There is a tank onsite where cuttings are being placed. Permit and Emergency Response signs are posted at the entrance to the pad. Along the access road there are sound walls that are 2 panels high. Entering the well pad, there are sound walls 4 panels high in the one corner closest to houses.
2640670 Primary Facility 2017-09-20 Routine/Partial Inspection No Violations Noted At the time of inspection, conductor for well has been set. 24" was set to 40'. This has been cemented into place. Well is now covered with a steel plate. Mouse hole was set beside the well.
2650362 Primary Facility 2017-10-12 Drilling/Alteration No Violations Noted At the time of inspection, Appalachian Drillers rig 1 was onsite tripping out of the well. Cementers were lined up for noon. Rig and equipment were on containment. Chemicals and fuel were within double containment. Plan is to run 13 3/8" casing to 564' with a float shoe and float collar, as well as 5 centralizers.
2652306 Primary Facility 2017-10-19 Routine/Partial Inspection No Violations Noted At the time of inspection, Appalachian Drillers 1 was over the 5H well. This well had surface casing cemented using 510 sxs (111 bbls) Class A,2% CaCl2, 2% Gypsum, 15.6 ppg, 1.22 yield. Displaced with 83 bbls and landed plug. Floats held and 13 bbls cement returned to surface.

Intermediate casing was cemented using 695 sxs (151 bbls) Class A, 2% Gypsum, 2% CaCl2, 15.6 ppg, 1.22 yield. Displaced with 152 bbls freshwater and landed plug. Floats held and 25 bbls cement returned to surface. A float shoe and float collar (top at 1964') were used along with 16centralizers.

2678993 Primary Facility 2018-01-08 Administrative/File Review No Violations Noted
2680923 Primary Facility 2018-01-09 Routine/Partial Inspection No Violations Noted At the time of inspection, Nomac rig 79 is onsite over the #3H well. Production casing for this well was cemented using a lead of 185 sxs 35:65 Poz Class H (36.3 bbls), 15.2 ppg, 1.1 yield and tail of 955 sxs Class H (266 bbls), 15.6 ppg, 1.57 yield. This was displaced with 270 bbls freshwater. Plug was bumped and spacer was returned to surface. Floats held. Top of cement is at 5929'. A float shoe and float collar were used with 182 centralizers.
2689479 Primary Facility 2018-01-30 Routine/Partial Inspection No Violations Noted At the time of inspection, no activity was taking place on the pad. Some drill pipe remained on the pipe racks. There were also a few roll offs and frac tanks on the pad. Containment has been removed and was sitting in the dumpsters. Site was covered with snow, but I did not see any indication of any environmental concerns. Well or pit were not covered and everything looked good.
2691025 Primary Facility 2018-02-05 Administrative/File Review No Violations Noted
2695531 Primary Facility 2018-02-20 Administrative/File Review No Violations Noted
2697447 Primary Facility 2018-02-23 Routine/Partial Inspection No Violations Noted On site for a routine partial inspection.

Stimulation operations underway at time of inspection.

Inspected pad liner, secondary containments, AST, well development pipeline, E/S controls, waste management, and storage tanks.

Operator reported that flow back operations were underway at time of inspection and there were about 100 stages left in the stimulation.

I observed flow back water transfer operations for a period of time while on site.

Heavy rain event while on site.

2700521 Primary Facility 2018-02-22 Drilling/Alteration No Violations Noted At the time of inspection, C & J was onsite stimulating stage 17 of well. Currently, the stimulation is a single well job. There are a total of 35 stages that will be completed. Operations are running 24/7.

Several people in the area have reported either an odor or noise complaint. The odor was reported on Monday. The company man onsite had just come back from days off so he was unsure of operations on Monday. So I contacted his relief. He could not think of any unordinary odors. They had just started stimulation on Monday and he completed 2 stages and the night man did 3. He stated there were no spills and could only suggest diesel fumes from the trucks. In terms of the noise, XTO is working with the township to remedy the issue. They may be extending sound walls soon. There are 3 wells needing to be completed. The other 2 wells have 47 stages for the 3H and 44 for the 5H. Complaint ID is 332468.

2700522 Primary Facility 2018-02-27 Drilling/Alteration No Violations Noted At the time of inspection, C & J was onsite stimulating stage 2 of the well. There are a total of 47 stages that will be completed. Operations are running 24/7.

There have been no changes to operations and there has not been any additions to the sound walls yet. Drove to township building and wind was blowing towards the building from the well pad. This made sound from pad more prevalent. I do not have an accurate, calibrated noise reading device to determine the decibel levels. Complaint ID is 332468

2727919 Primary Facility 2018-05-09 Administrative/File Review No Violations Noted
2742623 Primary Facility 2018-06-14 Routine/Partial Inspection No Violations Noted At the time of inspection, well is still being worked on to be brought into production. Well has a Christmas tree installed on it, but the flow line has yet to be hooked up. There were some workers on the pad doing this, but it didn't appear that it would be completed for a few more days. There has be no earth moving activities yet. Cellar has been filled in to surface with gravel. 4 tanks and 3 line heaters have been placed within lined, steel dikes. The pipeline work is continuing off in the distance from the pad.
2760326 Primary Facility 2018-08-02 Routine/Partial Inspection No Violations Noted At the time of inspection, well remains shut in until pipeline is completed to the pad. Company representative stated that this could take a few more weeks. All of the piping needed to produce on the pad has been completed flow lines, emergency shut off valves). More stone had been added and reworked. 4 tanks are set within a lined, steel dike and 3 line heaters within another dike. A gas buster has also been installed.

No activity was taking place during inspection. There were 2 frac tanks that remained on the pad.

2803551 Primary Facility 2018-11-14 Routine/Partial Inspection No Violations Noted On site for a routine partial inspection.

Well drilled, completed, and in production. Well tag in place. Well protected by fencing and jersey barriers. Production equipment set (production tanks and GPUs) in secondary containment. Combustor installed. Gathering pipeline installed.

Site stabilized, PCSM BMPs installed and 100% vegetated.

For data sources see[8]