Well ID: 37-003-22124 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.490333,"lon":-79.750806,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Allegheny | |
Municipality: Plum Borough | |
Operator Name: PENNECO OIL CO INC | |
Well Pad ID: | |
Farm/Lease Name: LANE 2 | |
License Status: | |
Spud Date: | |
Permit Date: 2010-04-14 | |
Well Type: GAS | |
Unconventional Well: N | |
Configuration: Vertical Well | |
Conservation: No | |
Latitude: 40.490333 | |
Longitude: -79.750806 |
Date | Event |
---|---|
2010-04-14 | New Permit Application |
2010-05-06 | Performed Spud Operation |
2010-05-19 | Drilling Completion |
2010-06-02 | Perforation |
2013-04-22 | NEWLY DRILLED |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2010 | PENNECO OIL CO INC | 4,277.00 | 184 | 350.20 | 184 | 0.00 | 0 |
2011 | PENNECO OIL CO INC | 6,839.00 | 365 | 406.12 | 365 | 0.00 | 0 |
2012 | PENNECO OIL CO INC | 2,461.00 | 366 | 5.57 | 366 | 0.00 | 0 |
2013 | PENNECO OIL CO INC | 1,029.00 | 365 | 0.00 | 0 | 0.00 | 0 |
2014 | PENNECO OIL CO INC | 1,628.00 | 335 | 102.51 | 335 | 0.00 | 0 |
2015 | PENNECO OIL CO INC | 1,923.96 | 365 | 306.12 | 92 | 0.00 | 0 |
2016 | PENNECO OIL CO INC | 1,329.71 | 366 | 0.00 | 0 | 0.00 | 0 |
2017 | PENNECO OIL CO INC | 1,510.00 | 365 | 198.58 | 365 | 0.00 | 0 |
2018 | PENNECO OIL CO INC | 1,189.32 | 365 | 173.41 | 91 | 0.00 | 0 |
2019 | PENNECO OIL CO INC | 406.69 | 365 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2010 | PENNECO OIL CO INC | Produced Fluid | 75.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 |
2010 | PENNECO OIL CO INC | Drilling Fluid Waste | 7,946.90 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0091472 |
2010 | PENNECO OIL CO INC | Fracing Fluid Waste | 1,100.00 Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0095443 |
2017 | PENNECO OIL CO INC | Produced Fluid | 19.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2018 | PENNECO OIL CO INC | Produced Fluid | 23.00 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123SW005 |
2019 | PENNECO OIL CO INC | Produced Fluid | 48.67 Bbl | INJECTION DISPOSAL WELL | 34-007-2-3177 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
1875675 | Primary Facility | 2010-04-08 | Routine/Complete Inspection | No Violations Noted | On April 8, 2010 I conducted an inspection for an OG 57 Request for waiver of distance requirement. The well site is proposed to be constructed within 100 ft. from an unnamed tributary to Little Plum Creek. Well was site staked. Construction has not begun at site. Proposed E & S plan should protect stream from adverse impact during site/well development if properly implemented & maintained. Drill cuttings are to be land farmed on site. Operator must ensure that the surface of the land farm area is at least 20 inches above the seasonal high groundwater table. |
1885579 | Primary Facility | 2010-05-19 | Routine/Complete Inspection | No Violations Noted | On May 19th, 2010 I conducted a routine inspection of the above site. Drilling was taking place at the time of the inspection. A site ID sign and E&S plan were posted at the site. The access road was in good condition. A mud broom waas on site to keep the public roadway clean. All E&S controls were in place and constructed according to the plan at site. |
1891220 | Primary Facility | 2010-06-04 | Routine/Complete Inspection | No Violations Noted | On June 4th, 2010 I conducted a routine inspection of the above site. A swabbing rig was on site at the time of the inspection. A site ID sign and E&S plan were posted at the site. The access road was in good condition. The frac pit was constructed. All E&S controls were in place and constructed according to the plan at site. The operator should continue to inspect the E&S controls routinely and after each significant runoff event until the site is restored. |
1894764 | Primary Facility | 2010-05-13 | Drilling/Alteration | No Violations Noted | prepare to run 7" |
1894768 | Primary Facility | 2010-05-18 | Drilling/Alteration | No Violations Noted | bit @3560' |
1894969 | Primary Facility | 2010-05-10 | Drilling/Alteration | No Violations Noted | HILL DRILLING THIS WELL,SUPERIOR ON SITE SETTING UP TO CEMENT 133/8"CASING.SITE,PIT,E&S,AND ACCES,OK. |
1906411 | Primary Facility | 2010-07-21 | Routine/Complete Inspection | No Violations Noted | On July 21st, 2010 I conducted a routine inspection of the above site. Drilling was completed and production equipment was set in place. The access road was in good condition. The site was graded, seeded, and was being mulched at the time of inspection. All E&S controls were still in place and constructed according to the plan at site. The operator should continue to inspect the E&S controls routinely and after each significant runoff event until 70% uniform vegetative cover is achieved. |
1927305 | Primary Facility | 2010-10-06 | Routine/Complete Inspection | No Violations Noted | COMBO OIL AND GAS WELL. SITE RESTORED. TANKS ARE DIKED. |
For data sources see[7]