0435013306000

Well Details

Well ID: 0435013306000
Loading map...
Location: 00/06-33-043-01W5/0
Location Alias: 00/06-33-43-01 W5M
Location Alias 2: 00/06-33-043-01 W5/00
Country: Canada
Province: Alberta
Township: 043
Meridian: 5
Range: 01
Section: 33
County/Municipality: Ponoka County
Well Name: CVE HOMRIM 6-33-43-1
Operator Name: Cenovus Energy Inc.
License Number: 0189086
License Date: 1996-06-26
License Status: Issued
Spud Date: 1996-07-18
Final Drill Date: 1996-07-29
Well Total Depth: 2299.00 m
Surface Hole Latitude: 52.745535
Surface Hole Longitude: -114.090245

For data sources see[1][2]

Well History

Date Event
1996-06-26 Obtained License
1996-07-18 Well Log Performed
1996-07-19 Surface Casing Operation Performed
1996-07-29 Finished Drilling
1996-07-29 Well Mode changed to Drilled and Cased
1996-07-30 Well Log Performed
1996-08-01 Production Casing Operation Performed
1996-08-01 Rig Released
1996-08-10 Perforation Treatment Performed - Open-Hole Completion
1996-08-10 Well Log Performed
1996-09-19 Well Began Production
1996-09-19 Well Fluid changed to Gas
1996-09-19 Well Mode changed to Flowing
1999-05-01 Well Fluid changed to Crude Oil
1999-05-01 Well Mode changed to Flowing
1999-06-12 Perforation Treatment Performed - Cement Plug
1999-06-12 Perforation Treatment Performed - Open-Hole Completion
1999-06-18 Perforation Treatment Performed - Acid Squeeze - Press Used
2007-05-01 Well Fluid changed to Crude Oil
2007-05-01 Well Mode changed to Gas Lift
2009-03-25 Well Fluid changed to Crude Oil
2009-03-25 Well Mode changed to Pumping

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1996-08-10 Open Hole/Barefoot Completion 2253.00 2299.00 0
1999-06-12 Cement Plug 2295.80 2299.00 0
1999-06-12 Open Hole/Barefoot Completion 2253.00 2295.80 0
1999-06-18 Acid Treatment 2253.00 2295.80 0

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1996 2105 0.0 0.0 0.0
1997 7463 0.0 0.0 0.0
1998 7537 0.0 0.0 0.0
1999 7701 0.0 0.0 0.0
2000 8457 0.0 0.0 0.0
2001 8440 0.0 0.0 0.0
2002 8485 0.0 0.0 0.0
2003 8185 0.0 0.0 0.0
2004 8783 0.0 0.0 0.0
2005 8559 0.0 0.0 0.0
2006 8722 0.0 0.0 0.0
2007 7985 0.0 0.0 0.0
2008 8408 0.0 0.0 0.0
2009 7514 0.0 0.0 0.0
2010 5128 0.0 0.0 0.0
2011 2501 0.0 0.0 0.0
2012 8307 0.0 0.0 0.0
2013 6329 0.0 0.0 0.0
2014 8230 0.0 0.0 0.0
2015 8178 0.0 0.0 0.0
2016 8667 0.0 0.0 0.0
2017 8511 0.0 0.0 0.0
2018 8410 0.0 0.0 0.0
2019 7684 0.0 0.0 0.0
2020 2163 0.0 0.0 0.0

For data sources see[5]