37-039-25016

Well Details

Well ID: 37-039-25016
Loading map...
Operator Name: D & L ENERGY INC
First Permit Date: 2007-02-09
Last Permit Date: 2007-02-09
Spud Date: 2007-03-13
Unconventional: No
Horizontal: No
Violations: 2
Latitude: 41.507305
Longitude: -80.40298

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2010-0 1609.4 365.0 0.0 0.0 0.0 0.0
2008-0 3884.0 366.0 0.0 0.0 166.0 365.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2010-0 PRODUCED FLUID 69.0 Bbl INJECTION DISPOSAL WELL 34-155-23584 KOONTZ #1 DISPOSAL WELL WARREN OH
2010-0 PRODUCED FLUID 1129.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 34-007-22038 PAROBEK #2 (SWIW #12) OH

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1605894 2007-03-09 In Compliance with Schedule
1606838 2007-03-14 No Violations Noted
1615281 2007-04-12 In Compliance with Schedule
1619896 2007-05-01 No Violations Noted
1638846 2007-07-11 In Compliance with Schedule
1980913 2011-06-15 Violation(s) Noted Upon inspection today i found the production equipment apparently had either a leak or overtoped the capacity and dumped a large volume of oil and bring into the dike area. The oil appeared as htough it had been in the dike for several days if not weeks. Some mimimal effort had been made tro clean it up. The well pump jack is on a timer. the production equipmetn comnsisted of a two steel stock tanks and one poly tank with a separator. The well had an active prodcution chart in place. I called the operator and required them to remove all the comtaminated stone and dirt, then call me for an inspection before replacing the stone. I will send a NOV.dirt. 613694
1981635 2011-06-16 Violation(s) & Outstanding Violations Today's inspection was in follow-up to my 6/15 inspection to determine if the operator had taken steps to clean-up the oil spill. Upon inspection I found that the operator had placed spill abosorbent material in the oil/water laying inside the dike. On 6/16 I contacted the production Manager Dave Rice and explained we required the stone and contaminated soil be removal and that I must inspect the soil before reinstalling the stone.

A NOV as mailed out for the violation on 6/20/11.

613850
1985102 2011-06-27 Repairs or Upgrade Required On site revealed the stone and soil under the stock tanks needed to be removed to complete clean-up- I conact Dave Rice the production manager for D&L and explained this to him- he said they would get it done and call me.
1985192 2011-06-29 No Violations Noted Follow-up to verify the spill had been cleaned up and equipment reinstalled as required in NOV.All work is completed.
2110816 2012-10-24 No Violations Noted