34-055-22118

Well Details

Well ID: 34-055-22118
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2010-05-26
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 41.5175128218
Longitude: -81.333153494

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1626702490 2010-06-09 Operator has completed mixing 3rd load of cement fines into pits. Pits have firmed up and are sufficiently solidified. Operator was putting up safety fence around pits. Drainage controls are in good repair. Operator pushed dirt up to the silt fence north end of blow pit. Dirt was up to the silt fence, fence was in place and a berm is behind fence. Locks, pop off and gauge are on annulus.
-1899302184 2010-06-02 On site for long string job. Operator ran new R-3 11.6 lb pipe. Hole was TD at 3880' pipe set at 3867'. Top of the Lockport was 3186'. Cementing 100' above Lockport 3086' TD 3880= 794' of cement coverage needed. 794' X .2278 / 1.18= 153 sacks of class A cement needed for the job. Operator ran 210 sacks of class A cement, no circulation issues noted during cementing. Pits were in good repair. Lease road was stable. Operator will replace silt fence and straw bails north end of site. Drainage controls were washed out during flood event. Area had a 250 to 500 year rain event, 2.45 inches of rain in 45 minutes.
-2040835223 2010-07-07 Pits have been filled. Lease road is stable. Drainage controls are in place. Took readings of Clinton gas and annulus gas with operator and gas meter the DMRM is field testing. Clinton gas readings: CH4 9.10, CO 277, H2S 2ppm. Annulus readings Ch4 8.5 H2S 2. No H2S readings around well head, H2S was detected only when probe was inserted directly into the annulus.
-304431111 2010-06-01 Drill depth 3500'. Operator is drilling on fluid. Permit is posted in the dog house. Fire extinguishers in good working order were in the dog house, on the boom, the light plant and mud pump. Hand rails were up. Safety fence was up. BOP was in place. Pits were in good repair. Operator had to drain fresh water tank Sunday and pump pits into tank. Operator also had additional frac tank brought onto site and pumped pits into frac tank. Area received 2.45 inches of rain in 45 minutes. Sunday.
-350530493 2013-05-29 My inspection found the well to be equipped with a plunger lift unit. The annulus valve is open to a pop off valve that is plumbed into the production tank. The tank battery and well are in good repair and surrounded by a chain link fence. The tank battery consists of two 100 BBL production tanks, a 50 BBL poly brine tank, and a mechanical separator. The vent stack on the production tank is plumbed into a 55 gallon charcoal filter. The vent stack is then plumbed up and topped with a spark arrestor. The proper identification is located on the tank battery. The lease road is in stable condition.
-781953690 2010-05-27 On site for BOP test. Operator pressured up BOP to 375 psi pressured hole to 200psi. Start time 15:05 end time 15:20, 20psi loss of pressure chock valve was leaking, not closed all the way. Pressured stabilized after 5 minutes. No lose of pressure at the annulus. Dog house has working fire extinguishers in it as well as the mud pump.
1273764046 2010-05-12 Operator has cleared and removed trees and stumps from site. Permit Identification sign is posted. Called company requested that silt fence be installed along the stream. Operator has not disturbed topsoil at this time.
1274959053 2010-05-27 On site for surface cement. Hole #2 was an 11 inch hole 335 feet in depth. Operator ran 309' of 8.625 pipe set at 319'LJ. Pipe was new R-3 20lb pipe, set open ended. Petroset cementing company broke circulation ran 1 bag of cotton seed hauls ahead. Mixed cement and ran cement until it returned to surface. Petroset changed over and displaced cement. 18 BBL return of good cement to surface. Cement held at surface. Berea top was 200' bottom 245'. Operator had collected cutting samples every ten feet. Permit was posted in the dog house. Safety fence was up. Pits were in good repair. Lease road was stable. Permit sign posted at the entrance of the lease road.
1276178201 2010-06-09 Operator was mixing in 2nd load of cement fines into pits to solidify them. Blow pit is soft and will need a 3rd load to complete solidification, 3rd load has been ordered. Operator was sufficiently mixing pits to solidify them top to bottom. Lease road is stable and in good repair. Annulus pressure was zero. Opened annulus with operator, annulus was on vacuum.
1276192537 2010-06-07 Call from Warren Schoernfelt annulus readings are zero. Pits will be closed Wednesday.
2069072719 2011-03-10 Site is snow covered, preliminary restoration can not be passed at this time. Well and tank battery are in good repair.
354838518 2012-01-04 The annulus on the well is open. The tank battery is equipped with two 100 barrel production tanks and the man doors are locked. An identification sign needs posted. Site is in good repair.
533725410 2011-01-04 Wellhead is in good repair. Well is a rabbit well. Tank battery is in good repair, 2 100Bbl tanks, mechanical separator, charcoal filter, spark arrestor and low pressure relief valve are all in the battery. Fencing is 8 foot tall with three strands of barbed wire. Bull plugs are in place. Hatches are closed and secure. Site has been graded, seeded, vegetation is established and landscaping is installed. Drainage is controlled. Lease road is stable.
990587753 2010-05-25 On site for site construction. Drainage controls are in place. North end of the site, area adjacent to the stream, operator has installed silt fence backed with straw bails. There is silt fence installed east and west side of the site as well. Lease road is stable. Permit is posted in the dog house. Pits were under construction. Soil was damp when digging, there was approximately a foot of black topsoil, 4 feet of brown subsoil then into a gray clay. No flow of ground water noted. Operator lined pits with a re-enforced liner. Fresh water was pulled from the stream north of the site.