Well ID: 37-105-21858 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.713209,"lon":-77.912673,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Potter | |
Municipality: Summit Township | |
Operator Name: JKLM ENERGY LLC | |
Well Pad ID: 153187 | |
Farm/Lease Name: SWEDEN VALLEY 101 5HU | |
License Status: Plugged OG Well | |
Spud Date: 02/19/2016 | |
Permit Date: 12/21/2015 | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Latitude: 41.713209 | |
Longitude: -77.912673 |
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2016 | JKLM ENERGY LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
For data sources see[4]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2438037 | Primary Facility | 2016-01-05 | Routine/Partial Inspection | No Violations Noted | Preconstruction meeting for the Sweden Valley 101 well pad. Logging operations to begin on 1/6/15. Site construction anticipated to begin after logging operations completed and will take approximately 3 weeks. TLT |
2452377 | Primary Facility | 2016-02-18 | Preoperation Inspection | No Violations Noted | Preoperational inspection. Spud notices for the 2HU - 5HU wells were received on 2/17/16 with an anticipated spud date of 2/19/16. Site has been constructed and stabilized. Perimeter E&S controls have been installed. TLT |
2472685 | Primary Facility | 2016-04-05 | Routine/Complete Inspection | No Violations Noted | |
2472925 | Primary Facility | 2016-04-08 | Routine/Complete Inspection | No Violations Noted | |
2545908 | Primary Facility | 2016-12-19 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | On December 19, 2016 at approximately 10:30 am I arrived on JKLM’s Sweden Valley 102 pad after receiving Notice of Intent from the operator last week to plug and abandon (3) wells; 1HU (105-20848), 2HU (105-21868) both on the 102 pad and the 5HU (105-21858, on the 101 pad). All (3) wells being plugged are conductors only. There was a crew on site. I met with on-site representative to discuss operations on the pad and their plugging procedure. At the time of inspection the crew was digging out the first well; the conductors were cut and buried in the cellar after being buried. All the conductors are reportedly cemented in place outside the pipe and on bottom. After the cellars are dug out they’ll fill conductors with ~50’ cement on bottom (pour ready-mix) and fill with gravel from that point to surface. There are two conductors on this pad (1HU and 2HU) both 96’, and the 5HU on the 102 pad next door, set at 80’. Today they’ll dig out all three cellars in preparation for cementing operations which will likely |
2546841 | Primary Facility | 2016-12-16 | Routine/Complete Inspection | No Violations Noted | Routine inspection. The 2HU - 4HU wells have been drilled and stimulated. Production equipment has been installed at the site. The site was snow covered and frozen, therefore vegetative cover and E&S controls were not observed. TLT |
2551436 | Primary Facility | 2017-01-09 | Routine/Complete Inspection | No Violations Noted | |
2609686 | Primary Facility | 2017-06-22 | Routine/Partial Inspection | No Violations Noted | On 6/22/17 at 1345 hrs I conducted a routine inspection at the Sweden Valley 101 well site. It was overcast and 82 degrees F. Sean Bacha, Oil and Gas Consultant, was present at the site during the inspection.
The 2HU - 4HU wells were drilled in 2016 and are equipped for production. The 5HU well was spud, however, then plugged in December 2016. A new well permit application for the 6V well (105-21900) was received on 6/5/17. I observed the E&S controls, production equipment and other materials staged on site. Grass is becoming well established on the topsoil stockpile and around the sediment traps; however, vegetative cover on the well pad fill slopes remains sparse. The sediment traps were observed (Photo #1). ST-1 (southern trap) held a minimal amount of water and had a field measured specific conductance of 209 micro Siemens/cm. The filter fabric had come off the rock filter and should be restaked (Photo #2). ST-2 (northern trap) was approximately half full and had a specific conductance of 73 micro Sie |
2769269 | Primary Facility | 2018-08-23 | Routine/Complete Inspection | No Violations Noted | The DEP conducted a routine inspection of the JKLM Sweden Valley 101 Well Pad ESG29-105-15-0003 on 8/23/2018 @1130 hours. The weather was 70 degrees sunny, 58% humidity and winds WNW 13 mph.
The 2HU-4HU wells were drilled in 2016 and are currently in production. The 5HU well was spud, then plugged in December 2016. The access road, well pad and associated controls were inspected. A compressor unit appears to have been installed on the SE corner of the well pad. Large puddles were observed on the pad surface from recent heavy rains. All puddles on teh pad surface measured <300mS/cm(Photo#3). The fluid in teh duck pond containment had a field measured conductivity of 300uS/cm. JKLM representatives were contact and a vac truck was dispatched to the site. The elevated conductivity fluid was removed. A violation of 25 Pa Code 78a.56(a) is cited as IMMEDIATELY CORRECTED against the 2HU well API#105-21855 due to the remediation of the elevated conductivity fluid by a vac truck during the inspection. I departe |
2845928 | Primary Facility | 2019-02-27 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was a plugged well. This plugging was completed 12-21-16. The monument is a steel welded plate welded to the conductor 2 1/2' below ground surface. No violations noted at this inspection. |
For data sources see[5]