| Well ID: 34-163-20885
 
| Well ID: 34-163-20885
| style="height=100%; align=center" rowspan="15" | {{#display_map: 39.2073486578, -82.2731332885 | width=100% | height=100% }}
+
| style="height=100%; align=center" rowspan="15" | {{#display_map: 39.20753683, -82.27363806 | width=100% | height=100% }}  
 
|-
 
|-
| County:
+
| County: [[Vinton County, Ohio|Vinton]]
 
|-
 
|-
| Municipality:
+
| Municipality:  
 
|-
 
|-
| Operator Name:
+
| Operator Name: [[BANCEQUITY PETROLEUM CORP]]
 
|-
 
|-
| Well Pad ID:
+
| Well Pad ID:  
 
|-
 
|-
| Farm/Lease Name:
+
| Farm/Lease Name:  
 
|-
 
|-
| First Permit Date:
+
| First Permit Date:  
 
|-
 
|-
| Last Permit Date:
+
| Last Permit Date:  
 
|-
 
|-
 
| Spud Date: 1986-01-30
 
| Spud Date: 1986-01-30
 
|-
 
|-
| Unconventional:
+
| Unconventional: No
 
|-
 
|-
| Horizontal:
+
| Configuration: Vertical
 
|-
 
|-
| Producing: No
+
| Well Status: Active Injection
 
|-
 
|-
| Violations: 8
+
| Violations: 0
 
|-
 
|-
| Latitude: 39.2073486578
+
| Latitude: 39.20753683
 
|-
 
|-
| Longitude: -82.2731332885
+
| Longitude: -82.27363806
 
|-
 
|-
 
|}
 
|}
Line 43: Line 43:
 
!scope="col" | OIL QUANTITY
 
!scope="col" | OIL QUANTITY
 
!scope="col" | OIL PRODUCTION DAYS
 
!scope="col" | OIL PRODUCTION DAYS
|}
 
== Waste Data ==
 
{| class="wikitable sortable" width="95%"
 
!scope="col" | PERIOD
 
!scope="col" | TYPE
 
!scope="col" | QUANTITY
 
!scope="col" | UNITS
 
!scope="col" | DISPOSAL METHOD
 
!scope="col" | WASTE FACILITY PERMIT ID
 
!scope="col" | WASTE FACILITY NAME
 
!scope="col" | FACILITY CITY
 
!scope="col" | FACILITY STATE
 
|}
 
== Inspection Data ==
 
{| class="wikitable sortable" width="95%"
 
!scope="col" | INSPECTION ID
 
!scope="col" | DATE
 
!scope="col" | DESCRIPTION
 
!scope="col" | COMMENT
 
!scope="col" | VIOLATION ID
 
!scope="col" | VIOLATION CODE
 
!scope="col" | VIOLATION_COMMENT
 
 
|-
 
|-
| -1139264332
+
| 1988-0
| 2013-02-12
+
| style="text-align:right;" | 0.0
|
+
|  
| There is some fluid in the tank battery.  Injection pumps were running at the time of inspection.  Spoke with Mike McPeak about the fluid in the tank battery.  He stated that the next time the water truck is out there, he will have it sucked out.  No other violations were noted.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 533.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1156527164
+
| 1989-0
| 2010-03-22
+
| style="text-align:right;" | 0.0
|
+
|  
| An inspection revealed no violations at this time.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 406.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1287940721
+
| 1990-0
| 2010-09-23
+
| style="text-align:right;" | 0.0
|
+
|  
| An inspection revealed no violations.  Note: The gauge utilized for this inspection will require calibration.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 0.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1561344386
+
| 1991-0
| 2012-04-26
+
| style="text-align:right;" | 0.0
|
+
|  
| Unloading pad has been constructed. Sump pump is installed and line is connected to steel tank.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 490.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1648071760
+
| 1992-0
| 2011-08-22
+
| style="text-align:right;" | 0.0
|
+
|  
| Wellhead has been excavated around and is full of water (18" deep). Storm event with in last 24 hours of inspection. Annulus at 270 psi, injection at 270 psi. Called Jess Hess. Jess came to well site and tested the Annulus at 775 psi for 15 minutes. After 15 minutes 770 psi. Test passed.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 211.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1659343750
+
| 1993-0
| 2009-06-15
+
| style="text-align:right;" | 0.0
|
+
|  
| An inspection revealed no violations at this time.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 272.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -16714452
+
| 1994-0
| 2012-08-31
+
| style="text-align:right;" | 0.0
|
+
|  
| No violations were noted at the time of inspection.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 0.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1720426544
+
| 1995-0
| 2008-09-16
+
| style="text-align:right;" | 0.0
|
+
|  
| No violations were noted.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 0.0
|
+
|  
 
|-
 
|-
 
|-
 
|-
| -1734127772
+
| 1996-0
| 2008-02-11
+
| style="text-align:right;" | 0.0
|
+
|  
| No violations were noted.
+
|  
|
+
|  
|
+
| style="text-align:right;" | 0.0
|
+
|  
 
|-
 
|-
 +
|}
 +
For data sources see<ref>{{cite web
 +
| title = Ohio Department of Natural Resources RBDMS
 +
| publisher = [http://oilandgas.ohiodnr.gov/]
 +
| date = 2015-06-19
 +
| url = http://wellwiki.org/wiki/Ohio_Oil_and_Gas_Data_Sources#Production
 +
| accessdate = 2015-06-20 }}</ref>
 +
== Inspection Data ==
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | INSPECTION ID
 +
!scope="col" | DATE
 +
!scope="col" | DESCRIPTION
 +
!scope="col" | COMMENT
 +
!scope="col" | VIOLATION ID
 +
!scope="col" | VIOLATION CODE
 +
!scope="col" | VIOLATION COMMENT
 
|-
 
|-
| -1888553662
+
| 1048949607
| 2007-11-05
+
| 2007-01-11
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|  
|
+
|  
|
+
| Compliance Notice
 
|-
 
|-
 
|-
 
|-
| -1907233193
+
| 1048949607
| 2005-01-12
+
| 2007-01-11
|
+
|  
| No violations.
+
| No violations were noted.
|
+
|  
|
+
|  
|
+
| Compliance Notice
 
|-
 
|-
 
|-
 
|-
| -197596680
+
| 1048949607
| 2011-03-29
+
| 2007-01-11
|
+
|  
| Good identification at tank battery. 1/4" ball valve on annulus has a crack in the valve body and needs replaced. I talked to Jess Hess and Tom Fischietto about the valve.
+
| No violations were noted.
|
+
|  
|
+
|  
|
+
| Compliance Notice
 
|-
 
|-
 
|-
 
|-
| -1981311621
+
| 1048949607
| 2004-01-15
+
| 2007-01-11
|
+
|  
| An insection of the well and tank battery revealed  oil and oily gravel in dike around storage tanks.
+
| No violations were noted.
|
+
|  
| 9-3-05(A)6
+
|  
|
+
| Field Visit or Inspection
 
|-
 
|-
 
|-
 
|-
| -2082491979
+
| 1048949607
| 2006-09-25
+
| 2007-01-11
|
+
|  
| A follow-up inspection was conducted at the facility owned by Bancequity Petroleum Corp., on 9/25/2006.  During the inspection, it was noted that the leaking fitting has not been replaced and the oily soil has not been removed.
+
| No violations were noted.
|
+
|  
|
+
|  
|
+
| Phone Call
|-
 
|-
 
| -548055831
 
| 2012-04-20
 
|
 
| Witnessed the concrete being poured for the unloading pad.
 
|
 
|
 
|
 
|-
 
|-
 
| -585156901
 
| 2009-09-01
 
|
 
| An inspection was conducted with Mr. Jeff Fry, West Region Oil & Gas Supervisor and UIC Field Supervisor.  During the inspection, it was noted that corrosion exists around the outside of casing.  Low Range Quantabs revealed no chlorides in fluid found dripping from the tubing.  When the gauge was removed from the annulus, the fluid released resembled corrosion inhibitor.  The pressure(s) for injection and annulus were close in value and noted as 250/240.
 
|
 
|
 
|
 
|-
 
|-
 
| -905643794
 
| 2003-01-30
 
|
 
| No violations at this time.
 
|
 
|
 
|
 
 
|-
 
|-
 
|-
 
|-
 
| 1048949607
 
| 1048949607
 
| 2007-01-11
 
| 2007-01-11
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1091468270
 
| 1091468270
 
| 2004-07-29
 
| 2004-07-29
|
+
|  
 
| No violations
 
| No violations
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1139264332
 +
| 2013-02-12
 +
|
 +
| There is some fluid in the tank battery.  Injection pumps were running at the time of inspection.  Spoke with Mike McPeak about the fluid in the tank battery.  He stated that the next time the water truck is out there, he will have it sucked out.  No other violations were noted.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1152991768
 
| 1152991768
 
| 2012-06-18
 
| 2012-06-18
|
+
|  
 
| Upon arrival, I observed a couple of inches of water inside the tank battery.  Recent rain events were the reason for this.  I mentioned this to Mike Mcpeak.  He agreed to remedy the situation.
 
| Upon arrival, I observed a couple of inches of water inside the tank battery.  Recent rain events were the reason for this.  I mentioned this to Mike Mcpeak.  He agreed to remedy the situation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1156527164
 +
| 2010-03-22
 +
|
 +
| An inspection revealed no violations at this time.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i12
 
| 1269i12
 
| 2001-01-18
 
| 2001-01-18
|
+
|  
 
| An inspection revealed Injection and Annulus pressures were the equal when first checked after bleeding off Annulus pressure checked pressure again and it had built up to 60 lbs and stayed for approx. 10 minutes. Request that the next monthly MIT test performed by company that an inspector be present to witness test .
 
| An inspection revealed Injection and Annulus pressures were the equal when first checked after bleeding off Annulus pressure checked pressure again and it had built up to 60 lbs and stayed for approx. 10 minutes. Request that the next monthly MIT test performed by company that an inspector be present to witness test .
|
+
|  
| 9-3-07(G)
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i1228
 
| 1269i1228
 
| 2002-07-23
 
| 2002-07-23
|
+
|  
 
| Pressures on well meet requirements at this time, filters at well will need to be removed from site.
 
| Pressures on well meet requirements at this time, filters at well will need to be removed from site.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i1322
 
| 1269i1322
 
| 2002-08-20
 
| 2002-08-20
|
+
|  
 
| In-Complinace.
 
| In-Complinace.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i1551
 
| 1269i1551
 
| 2002-11-21
 
| 2002-11-21
|
+
|  
 
| No violations at this time, lease rd will need graded and water breaks in spring.
 
| No violations at this time, lease rd will need graded and water breaks in spring.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i3550949
 
| 1269i3550949
 
| 2001-02-15
 
| 2001-02-15
|
+
|  
 
| Follow - up on NOV , tested Annulus of well to max. injection pressure . Test pressure at 765 lbs for 15 minutes , no lose.  Dennis Crist also witnessed the test.      IN - COMPLAINCE
 
| Follow - up on NOV , tested Annulus of well to max. injection pressure . Test pressure at 765 lbs for 15 minutes , no lose.  Dennis Crist also witnessed the test.      IN - COMPLAINCE
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i407
 
| 1269i407
 
| 2001-10-02
 
| 2001-10-02
|
+
|  
|
+
|  
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1269i852
 
| 1269i852
 
| 2002-03-06
 
| 2002-03-06
|
+
|  
 
| An inspection of the well revealed that the dike around the storage tanks is standing 1/2 full of water, also the liner in the dike may have failed due to brush growing in the dike, water pump leaking brine, oily gravel in dike area. NEED TO EMPTY DIKE, REPAIR OR REPLACE LINER IN DIKE, REPAIR WATER PUMP, CLEAN-UP ALL OILY GRAVEL AND CONTAMINATED GRAVEL FROM DIKE.
 
| An inspection of the well revealed that the dike around the storage tanks is standing 1/2 full of water, also the liner in the dike may have failed due to brush growing in the dike, water pump leaking brine, oily gravel in dike area. NEED TO EMPTY DIKE, REPAIR OR REPLACE LINER IN DIKE, REPAIR WATER PUMP, CLEAN-UP ALL OILY GRAVEL AND CONTAMINATED GRAVEL FROM DIKE.
|
+
|  
| 9-9-05(A)8
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
| 1269i852
+
| -1287940721
| 2002-03-06
+
| 2010-09-23
|
+
|  
| An inspection of the well revealed that the dike around the storage tanks is standing 1/2 full of water, also the liner in the dike may have failed due to brush growing in the dike, water pump leaking brine, oily gravel in dike area. NEED TO EMPTY DIKE, REPAIR OR REPLACE LINER IN DIKE, REPAIR WATER PUMP, CLEAN-UP ALL OILY GRAVEL AND CONTAMINATED GRAVEL FROM DIKE.
+
| An inspection revealed no violations. Note: The gauge utilized for this inspection will require calibration.
|
+
|  
| 9-9-05(A)9
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1349378763
 
| 1349378763
 
| 2012-10-01
 
| 2012-10-01
|
+
|  
 
| Inspected injection pressure and annulus pressure. Collected brine sample from brine tank. Sample taken to Ohio Department of Natural Resources, Division of Oil and Gas Lab. Mike McPeak was on site during sampling.
 
| Inspected injection pressure and annulus pressure. Collected brine sample from brine tank. Sample taken to Ohio Department of Natural Resources, Division of Oil and Gas Lab. Mike McPeak was on site during sampling.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1379007452
 
| 1379007452
 
| 2013-09-10
 
| 2013-09-10
|
+
|  
| Inspected the unloading pad, containment dike, tanks, injection line, annulus pressure, and injection pressure. Containment dike is free of water. Met with Mike McPeak on site to talk about the 1" steel line that is installed from the injection pump to the unloading pad. The 1" line drains leaking brine from the injection pump to the unloading pad sump, which is connected to a tank with in the containment dike. Mike told me that the connection was temporary and it will be changed as soon as a new pump for the injection pump sump is installed.
+
| Inspected the unloading pad, containment dike, tanks, injection line, annulus pressure, and injection pressure. Containment dike is free of water. Met with Mike McPeak on site to talk about the 1 steel line that is installed from the injection pump to the unloading pad. The 1 line drains leaking brine from the injection pump to the unloading pad sump, which is connected to a tank with in the containment dike. Mike told me that the connection was temporary and it will be changed as soon as a new pump for the injection pump sump is installed.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1393431198
 
| 1393431198
 
| 2014-02-26
 
| 2014-02-26
|
+
|  
 
| Inspected containment dike, tanks, unloading pad, injection pump, annulus pressure and injection pressure. Identification posted at the containment dike and well site.
 
| Inspected containment dike, tanks, unloading pad, injection pump, annulus pressure and injection pressure. Identification posted at the containment dike and well site.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1403716866
 
| 1403716866
 
| 2014-06-25
 
| 2014-06-25
|
+
|  
 
| Inspected the containment dike, tanks, injection pump, unloading pad, annulus pressure, and injection pressure. Checked brine hauling log and witnessed the unloading of a Bancequity brine truck. Unloading pad  has two cracks that need to be repaired. I called and talked to Mike McPeak and we discussed the unloading pad cracks and that they need to repair them.
 
| Inspected the containment dike, tanks, injection pump, unloading pad, annulus pressure, and injection pressure. Checked brine hauling log and witnessed the unloading of a Bancequity brine truck. Unloading pad  has two cracks that need to be repaired. I called and talked to Mike McPeak and we discussed the unloading pad cracks and that they need to repair them.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 1410877951
 +
| 2014-09-16
 +
|
 +
| Inspected the unloading pad, containment dike, tanks, injection pump, annulus pressure and injection pressure. Good identification at the containment dike and well. Containment dike is free of water. Met with Mike McPeak on site to discuss the well operations.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1418069198
 +
| 2014-12-08
 +
|
 +
| Inspected the unloading pad, containment dike, tanks, injection pump, annulus pressure and injection pressure. Witnessed Bancequity truck unloading on the pad.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1426785320
 +
| 2015-03-19
 +
|
 +
| Inspected the unloading pad, containment dike, tanks, injection pump, injection line, injection pressure and annulus pressure. Containment dike was free of fluids. Identification was posted at the well and containment dike. Injection pump was in operation during the inspection.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1433860791
 +
| 2015-06-09
 +
|
 +
| Inspected the containment dike, tanks, injection pump, unloading pad, injection pressure and annulus pressure. Identification posted at well and facility. Containment dike is free of fluids.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1460822929
 
| 1460822929
 
| 2012-04-26
 
| 2012-04-26
|
+
|  
 
| Dike is full of water. Talked to Mike McPeak about removing the water from dike.
 
| Dike is full of water. Talked to Mike McPeak about removing the water from dike.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1461582844
 
| 1461582844
 
| 2003-10-30
 
| 2003-10-30
|
+
|  
 
| No violations
 
| No violations
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 148919856
 
| 148919856
 
| 2012-04-26
 
| 2012-04-26
|
+
|  
 
| Observed new unloading pad with Inspector Jon Scott.  Then performed regular status check.
 
| Observed new unloading pad with Inspector Jon Scott.  Then performed regular status check.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1561344386
 +
| 2012-04-26
 +
|
 +
| Unloading pad has been constructed. Sump pump is installed and line is connected to steel tank.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1645609207
 
| 1645609207
 
| 2013-04-04
 
| 2013-04-04
|
+
|  
| 3" line has been repaired. The line was cut and a new section of line was installed. Violation is resolved.
+
| 3 line has been repaired. The line was cut and a new section of line was installed. Violation is resolved.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1648071760
 +
| 2011-08-22
 +
|
 +
| Wellhead has been excavated around and is full of water (18 deep). Storm event with in last 24 hours of inspection. Annulus at 270 psi, injection at 270 psi. Called Jess Hess. Jess came to well site and tested the Annulus at 775 psi for 15 minutes. After 15 minutes 770 psi. Test passed.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1659343750
 +
| 2009-06-15
 +
|
 +
| An inspection revealed no violations at this time.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -16714452
 +
| 2012-08-31
 +
|
 +
| No violations were noted at the time of inspection.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1720426544
 +
| 2008-09-16
 +
|
 +
| No violations were noted.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1734127772
 +
| 2008-02-11
 +
|
 +
| No violations were noted.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 178139816
 
| 178139816
 
| 2006-07-12
 
| 2006-07-12
|
+
|  
 
| An inspection was conducted at the facility owned by Bancequity Petroleum Corp. on 7/12/2006.  During the inspection, it was noted that a fitting located at the storage tank needs replaced.  An oil discharge was observed around this area.
 
| An inspection was conducted at the facility owned by Bancequity Petroleum Corp. on 7/12/2006.  During the inspection, it was noted that a fitting located at the storage tank needs replaced.  An oil discharge was observed around this area.
|
+
|  
| 9-3-05(A)3
+
|  
|
+
|
 +
|-
 +
|-
 +
| -1888553662
 +
| 2007-11-05
 +
|
 +
| No violations were noted.
 +
|
 +
|
 +
|  
 
|-
 
|-
 
|-
 
|-
| 178139816
+
| -1907233193
| 2006-07-12
+
| 2005-01-12
|
+
|  
| An inspection was conducted at the facility owned by Bancequity Petroleum Corp. on 7/12/2006.  During the inspection, it was noted that a fitting located at the storage tank needs replaced. An oil discharge was observed around this area.
+
| No violations.
|
+
|
| 9-3-05(A)6
+
|
|
+
|
 +
|-
 +
|-
 +
| -197596680
 +
| 2011-03-29
 +
|
 +
| Good identification at tank battery. 1/4 ball valve on annulus has a crack in the valve body and needs replaced. I talked to Jess Hess and Tom Fischietto about the valve.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1980417309
 
| 1980417309
 
| 2011-11-02
 
| 2011-11-02
|
+
|  
 
| Good vegetative cover established.
 
| Good vegetative cover established.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1981311621
 +
| 2004-01-15
 +
|
 +
| An insection of the well and tank battery revealed  oil and oily gravel in dike around storage tanks.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 2000246827
 
| 2000246827
 
| 2004-03-04
 
| 2004-03-04
|
+
|  
 
| Follow-up on NOV, In-Complaince.
 
| Follow-up on NOV, In-Complaince.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 2042730676
 
| 2042730676
 
| 2013-11-04
 
| 2013-11-04
|
+
|  
 
| Inspected unloading pad, containment dike, tanks,  injection pump, injection line, annulus pressure, and injection pressure. Identification is posted at the wellhead and containment dike. Dike is free of water.
 
| Inspected unloading pad, containment dike, tanks,  injection pump, injection line, annulus pressure, and injection pressure. Identification is posted at the wellhead and containment dike. Dike is free of water.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -2082491979
 +
| 2006-09-25
 +
|
 +
| A follow-up inspection was conducted at the facility owned by Bancequity Petroleum Corp., on 9/25/2006.  During the inspection, it was noted that the leaking fitting has not been replaced and the oily soil has not been removed.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 2130214539
 
| 2130214539
 
| 2010-06-22
 
| 2010-06-22
|
+
|  
 
| An inspection revealed no violations.
 
| An inspection revealed no violations.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 261933827
 
| 261933827
 
| 2012-04-19
 
| 2012-04-19
|
+
|  
 
| Witnessed construction of unloading pad at tank battery.  Crews were forming up and preparing to pour concrete.
 
| Witnessed construction of unloading pad at tank battery.  Crews were forming up and preparing to pour concrete.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 273491706
 
| 273491706
 
| 2007-04-19
 
| 2007-04-19
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 342075127
 
| 342075127
 
| 2009-03-02
 
| 2009-03-02
|
+
|  
 
| An inspection revealed no violations at this time.
 
| An inspection revealed no violations at this time.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 387007605
 
| 387007605
 
| 2013-05-15
 
| 2013-05-15
|
+
|  
 
| Inspected injection pressure, annulus pressure, containment dike, injection pump, tanks and unloading pad. Tanks have been painted. Dike has new sump pit with a sump pump connected to a steel horizontal tank in the containment dike. A brine sample was collected from a Bancequity brine truck (UIC # 25-476) Sample to be shipped to ODNR Lab.
 
| Inspected injection pressure, annulus pressure, containment dike, injection pump, tanks and unloading pad. Tanks have been painted. Dike has new sump pit with a sump pump connected to a steel horizontal tank in the containment dike. A brine sample was collected from a Bancequity brine truck (UIC # 25-476) Sample to be shipped to ODNR Lab.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 434413212
 
| 434413212
 
| 2006-11-13
 
| 2006-11-13
|
+
|  
 
| A follow-up inspection on 11/13/2006 revealed that the previously noted  violations have been resolved.
 
| A follow-up inspection on 11/13/2006 revealed that the previously noted  violations have been resolved.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 438417582
 
| 438417582
 
| 2013-03-28
 
| 2013-03-28
|
+
|  
| Inspected injection pressure and annulus pressure. 3" yellow plastic line 6 feet  from pump has a pin hole and is leaking brine into dike. I called Mike McPeak and told him about the leak. Mike said that he will come to the dike today. I placed a red marking ribbon on the 3" line next to the leak.
+
| Inspected injection pressure and annulus pressure. 3 yellow plastic line 6 feet  from pump has a pin hole and is leaking brine into dike. I called Mike McPeak and told him about the leak. Mike said that he will come to the dike today. I placed a red marking ribbon on the 3 line next to the leak.
|
+
|  
| 9-3-05(A)6
+
|  
|
+
|
 +
|-
 +
|-
 +
| -548055831
 +
| 2012-04-20
 +
|
 +
| Witnessed the concrete being poured for the unloading pad.
 +
|
 +
|
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 5609i209
 
| 5609i209
 
| 2001-06-01
 
| 2001-06-01
|
+
|  
 
| No violations at this time.
 
| No violations at this time.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -585156901
 +
| 2009-09-01
 +
|
 +
| An inspection was conducted with Mr. Jeff Fry, West Region Oil & Gas Supervisor and UIC Field Supervisor.  During the inspection, it was noted that corrosion exists around the outside of casing.  Low Range Quantabs revealed no chlorides in fluid found dripping from the tubing.  When the gauge was removed from the annulus, the fluid released resembled corrosion inhibitor.  The pressure(s) for injection and annulus were close in value and noted as 250/240.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 594801966
 
| 594801966
 
| 2009-12-09
 
| 2009-12-09
|
+
|  
 
| An inspection revealed no violations.
 
| An inspection revealed no violations.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 706858123
 
| 706858123
 
| 2011-11-02
 
| 2011-11-02
|
+
|  
 
| Accompanied Jon Scott on inspection.
 
| Accompanied Jon Scott on inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 725217064
 
| 725217064
 
| 2008-12-16
 
| 2008-12-16
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 769040020
 
| 769040020
 
| 2007-07-03
 
| 2007-07-03
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 832084189
 +
| 2014-10-02
 +
|
 +
| Inspected the unloading pad, containment dike, tanks, injection pump, injection pressure and annulus pressure. Witnessed the testing of a 2 black plastic SDR 11 line from the Surface facility to the Beckley SWIW facility # 883.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -905643794
 +
| 2003-01-30
 +
|
 +
| No violations at this time.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 952107953
 
| 952107953
 
| 2008-05-27
 
| 2008-05-27
|
+
|  
 
| No violations were noted.
 
| No violations were noted.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 959117696
 
| 959117696
 
| 2006-11-03
 
| 2006-11-03
|
+
|  
 
| The company was contacted by telephone on 11/3/2006 and informed to resolve this violation within a week.
 
| The company was contacted by telephone on 11/3/2006 and informed to resolve this violation within a week.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| iTOMK000101
 
| iTOMK000101
 
| 2001-01-18
 
| 2001-01-18
|
+
|  
|
+
|  
|
+
|  
| 9-3-07(G)
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| PL2239
 
| PL2239
|
+
|  
|
+
|  
 
| Preliminary Restoration  done information from Data Point
 
| Preliminary Restoration  done information from Data Point
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|}
 
|}
 +
For data sources see<ref>{{cite web
 +
| title = Ohio Department of Natural Resources RBDMS
 +
| publisher = [http://oilandgas.ohiodnr.gov/]
 +
| date = 2015-06-19
 +
| url = http://wellwiki.org/wiki/Ohio_Oil_and_Gas_Data_Sources#Inspection
 +
| accessdate = 2015-06-20 }}</ref>
 +
== References ==
 +
{{reflist}}
 
__NOEDITSECTION__
 
__NOEDITSECTION__
 
[[Category:Wells]]
 
[[Category:Wells]]

Revision as of 01:39, 16 July 2015

Well Details

Well ID: 34-163-20885
Loading map...
County: Vinton
Municipality:
Operator Name: BANCEQUITY PETROLEUM CORP
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 1986-01-30
Unconventional: No
Configuration: Vertical
Well Status: Active Injection
Violations: 0
Latitude: 39.20753683
Longitude: -82.27363806

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
1988-0 0.0 533.0
1989-0 0.0 406.0
1990-0 0.0 0.0
1991-0 0.0 490.0
1992-0 0.0 211.0
1993-0 0.0 272.0
1994-0 0.0 0.0
1995-0 0.0 0.0
1996-0 0.0 0.0

For data sources see[1]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
1048949607 2007-01-11 No violations were noted. Compliance Notice
1048949607 2007-01-11 No violations were noted. Compliance Notice
1048949607 2007-01-11 No violations were noted. Compliance Notice
1048949607 2007-01-11 No violations were noted. Field Visit or Inspection
1048949607 2007-01-11 No violations were noted. Phone Call
1048949607 2007-01-11 No violations were noted.
1091468270 2004-07-29 No violations
-1139264332 2013-02-12 There is some fluid in the tank battery. Injection pumps were running at the time of inspection. Spoke with Mike McPeak about the fluid in the tank battery. He stated that the next time the water truck is out there, he will have it sucked out. No other violations were noted.
1152991768 2012-06-18 Upon arrival, I observed a couple of inches of water inside the tank battery. Recent rain events were the reason for this. I mentioned this to Mike Mcpeak. He agreed to remedy the situation.
-1156527164 2010-03-22 An inspection revealed no violations at this time.
1269i12 2001-01-18 An inspection revealed Injection and Annulus pressures were the equal when first checked after bleeding off Annulus pressure checked pressure again and it had built up to 60 lbs and stayed for approx. 10 minutes. Request that the next monthly MIT test performed by company that an inspector be present to witness test .
1269i1228 2002-07-23 Pressures on well meet requirements at this time, filters at well will need to be removed from site.
1269i1322 2002-08-20 In-Complinace.
1269i1551 2002-11-21 No violations at this time, lease rd will need graded and water breaks in spring.
1269i3550949 2001-02-15 Follow - up on NOV , tested Annulus of well to max. injection pressure . Test pressure at 765 lbs for 15 minutes , no lose. Dennis Crist also witnessed the test. IN - COMPLAINCE
1269i407 2001-10-02
1269i852 2002-03-06 An inspection of the well revealed that the dike around the storage tanks is standing 1/2 full of water, also the liner in the dike may have failed due to brush growing in the dike, water pump leaking brine, oily gravel in dike area. NEED TO EMPTY DIKE, REPAIR OR REPLACE LINER IN DIKE, REPAIR WATER PUMP, CLEAN-UP ALL OILY GRAVEL AND CONTAMINATED GRAVEL FROM DIKE.
-1287940721 2010-09-23 An inspection revealed no violations. Note: The gauge utilized for this inspection will require calibration.
1349378763 2012-10-01 Inspected injection pressure and annulus pressure. Collected brine sample from brine tank. Sample taken to Ohio Department of Natural Resources, Division of Oil and Gas Lab. Mike McPeak was on site during sampling.
1379007452 2013-09-10 Inspected the unloading pad, containment dike, tanks, injection line, annulus pressure, and injection pressure. Containment dike is free of water. Met with Mike McPeak on site to talk about the 1 steel line that is installed from the injection pump to the unloading pad. The 1 line drains leaking brine from the injection pump to the unloading pad sump, which is connected to a tank with in the containment dike. Mike told me that the connection was temporary and it will be changed as soon as a new pump for the injection pump sump is installed.
1393431198 2014-02-26 Inspected containment dike, tanks, unloading pad, injection pump, annulus pressure and injection pressure. Identification posted at the containment dike and well site.
1403716866 2014-06-25 Inspected the containment dike, tanks, injection pump, unloading pad, annulus pressure, and injection pressure. Checked brine hauling log and witnessed the unloading of a Bancequity brine truck. Unloading pad has two cracks that need to be repaired. I called and talked to Mike McPeak and we discussed the unloading pad cracks and that they need to repair them.
1410877951 2014-09-16 Inspected the unloading pad, containment dike, tanks, injection pump, annulus pressure and injection pressure. Good identification at the containment dike and well. Containment dike is free of water. Met with Mike McPeak on site to discuss the well operations.
1418069198 2014-12-08 Inspected the unloading pad, containment dike, tanks, injection pump, annulus pressure and injection pressure. Witnessed Bancequity truck unloading on the pad.
1426785320 2015-03-19 Inspected the unloading pad, containment dike, tanks, injection pump, injection line, injection pressure and annulus pressure. Containment dike was free of fluids. Identification was posted at the well and containment dike. Injection pump was in operation during the inspection.
1433860791 2015-06-09 Inspected the containment dike, tanks, injection pump, unloading pad, injection pressure and annulus pressure. Identification posted at well and facility. Containment dike is free of fluids.
1460822929 2012-04-26 Dike is full of water. Talked to Mike McPeak about removing the water from dike.
1461582844 2003-10-30 No violations
148919856 2012-04-26 Observed new unloading pad with Inspector Jon Scott. Then performed regular status check.
-1561344386 2012-04-26 Unloading pad has been constructed. Sump pump is installed and line is connected to steel tank.
1645609207 2013-04-04 3 line has been repaired. The line was cut and a new section of line was installed. Violation is resolved.
-1648071760 2011-08-22 Wellhead has been excavated around and is full of water (18 deep). Storm event with in last 24 hours of inspection. Annulus at 270 psi, injection at 270 psi. Called Jess Hess. Jess came to well site and tested the Annulus at 775 psi for 15 minutes. After 15 minutes 770 psi. Test passed.
-1659343750 2009-06-15 An inspection revealed no violations at this time.
-16714452 2012-08-31 No violations were noted at the time of inspection.
-1720426544 2008-09-16 No violations were noted.
-1734127772 2008-02-11 No violations were noted.
178139816 2006-07-12 An inspection was conducted at the facility owned by Bancequity Petroleum Corp. on 7/12/2006. During the inspection, it was noted that a fitting located at the storage tank needs replaced. An oil discharge was observed around this area.
-1888553662 2007-11-05 No violations were noted.
-1907233193 2005-01-12 No violations.
-197596680 2011-03-29 Good identification at tank battery. 1/4 ball valve on annulus has a crack in the valve body and needs replaced. I talked to Jess Hess and Tom Fischietto about the valve.
1980417309 2011-11-02 Good vegetative cover established.
-1981311621 2004-01-15 An insection of the well and tank battery revealed oil and oily gravel in dike around storage tanks.
2000246827 2004-03-04 Follow-up on NOV, In-Complaince.
2042730676 2013-11-04 Inspected unloading pad, containment dike, tanks, injection pump, injection line, annulus pressure, and injection pressure. Identification is posted at the wellhead and containment dike. Dike is free of water.
-2082491979 2006-09-25 A follow-up inspection was conducted at the facility owned by Bancequity Petroleum Corp., on 9/25/2006. During the inspection, it was noted that the leaking fitting has not been replaced and the oily soil has not been removed.
2130214539 2010-06-22 An inspection revealed no violations.
261933827 2012-04-19 Witnessed construction of unloading pad at tank battery. Crews were forming up and preparing to pour concrete.
273491706 2007-04-19 No violations were noted.
342075127 2009-03-02 An inspection revealed no violations at this time.
387007605 2013-05-15 Inspected injection pressure, annulus pressure, containment dike, injection pump, tanks and unloading pad. Tanks have been painted. Dike has new sump pit with a sump pump connected to a steel horizontal tank in the containment dike. A brine sample was collected from a Bancequity brine truck (UIC # 25-476) Sample to be shipped to ODNR Lab.
434413212 2006-11-13 A follow-up inspection on 11/13/2006 revealed that the previously noted violations have been resolved.
438417582 2013-03-28 Inspected injection pressure and annulus pressure. 3 yellow plastic line 6 feet from pump has a pin hole and is leaking brine into dike. I called Mike McPeak and told him about the leak. Mike said that he will come to the dike today. I placed a red marking ribbon on the 3 line next to the leak.
-548055831 2012-04-20 Witnessed the concrete being poured for the unloading pad.
5609i209 2001-06-01 No violations at this time.
-585156901 2009-09-01 An inspection was conducted with Mr. Jeff Fry, West Region Oil & Gas Supervisor and UIC Field Supervisor. During the inspection, it was noted that corrosion exists around the outside of casing. Low Range Quantabs revealed no chlorides in fluid found dripping from the tubing. When the gauge was removed from the annulus, the fluid released resembled corrosion inhibitor. The pressure(s) for injection and annulus were close in value and noted as 250/240.
594801966 2009-12-09 An inspection revealed no violations.
706858123 2011-11-02 Accompanied Jon Scott on inspection.
725217064 2008-12-16 No violations were noted.
769040020 2007-07-03 No violations were noted.
832084189 2014-10-02 Inspected the unloading pad, containment dike, tanks, injection pump, injection pressure and annulus pressure. Witnessed the testing of a 2 black plastic SDR 11 line from the Surface facility to the Beckley SWIW facility # 883.
-905643794 2003-01-30 No violations at this time.
952107953 2008-05-27 No violations were noted.
959117696 2006-11-03 The company was contacted by telephone on 11/3/2006 and informed to resolve this violation within a week.
iTOMK000101 2001-01-18
PL2239 Preliminary Restoration done information from Data Point

For data sources see[2]

References

  1. "Ohio Department of Natural Resources RBDMS". [1]. 2015-06-19. Retrieved 2015-06-20. 
  2. "Ohio Department of Natural Resources RBDMS". [2]. 2015-06-19. Retrieved 2015-06-20.