37-115-22501

Well Details

Well ID: 37-115-22501
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Harford Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 149723
Farm/Lease Name: PAYNE D 1
License Status:
Spud Date: 2018-08-06
Permit Date: 2018-04-25
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.771922
Longitude: -75.676003

For data sources see[1][2][3]

Well History

Date Event
Deviated
2018-04-25 New Permit Application
2018-08-06 Performed Spud Operation
2019-02-26 Drilling Completion

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 CABOT OIL & GAS CORP 1,339,181.00 168 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 CABOT OIL & GAS CORP Synthetic Liner Materials 5.23 Tons LANDFILL 101247
2018 CABOT OIL & GAS CORP Drill Cuttings 321.82 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Waste Water Treatment Sludge 45.64 Tons REUSE (AT WELL PAD)
2019 CABOT OIL & GAS CORP Drill Cuttings 1,393.14 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Synthetic Liner Materials 18.62 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Produced Fluid 32,086.38 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE004
2019 CABOT OIL & GAS CORP Unused Fracturing Fluid Waste 4.74 Tons LANDFILL 101247
2019 CABOT OIL & GAS CORP Produced Fluid 14,244.93 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2019 CABOT OIL & GAS CORP Other Oil & Gas Wastes 0.18 Tons RESIDUAL WASTE PROCESSING FACILITY 301333
2019 CABOT OIL & GAS CORP Synthetic Liner Materials 0.67 Tons RESIDUAL WASTE TRANSFER FACILITY 101714

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2762395 Primary Facility 2018-08-10 Drilling/Alteration No Violations Noted At time of inspection.

On site for a new spud inspection. Met with company man David Dewberry. United Drilling was on site to drill and set the conductor pipe on the 1H, 4H, 5H, 6H, 7H, 9H, 10H, 12H and 14H wells. All the conductor pipes were set at 92' and Halliburton was on site and cementing them in. The 4H and 5H were cemented and they were on the 6H when I arrived on site. They plan to cement all the wells today. There was a new sign with the permit numbers put at the entrance, the new permit numbers were correct. There are three existing wells on site, the 2H, 3H and 8H. The permit number for the 2H was correct, the 3H was incorrect and there was no permit number for the 8H. The permit numbers were on the entrance sign and correct during prier inspections. David updated the sign before I left the site. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted

2782604 Primary Facility 2018-10-02 Drilling/Alteration No Violations Noted At time of inspection.

Met with company man Shane Brown. PD 181 was on site to drill and set the surface and intermediate casings. There are three existing wells on site that are temporarily plugged and there are nine new wells on site to be drilled. They are on the seventh of the nine wells. They were rigged up on the 6H and drilling the hole for the intermediate casing with WBM at a depth of 1042'. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

2844472 Primary Facility 2019-02-26 Drilling/Alteration No Violations Noted At time of inspection.

Met with company man Marcus Cormier. PD 548 was on site and pulling the drill pipe after completing the lateral section of the well to TD when I arrived on site. The top hole section of the well was drilled and completed to the depth of the intermediate casing by PD 181 on 9/30/18. There are three existing wells on site that are temporarily plugged and 9 new wells to be drilled. The 4H, 5H and 6H were drilled and completed to TD. The 7H, 9H, 10H, 12H and 14H are drilled to the depth of the intermediate casing. The proposed TD for the 1H well is 16967'. I took a walk around the location and there were no obvious concerns noticed. There were no violations noted.

For data sources see[7]

References