If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-117-24189 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.52,"lon":-82.81,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Morrow | |
Municipality: Gilead Township | |
Operator Name: MFC DRILLING INC | |
Well Pad ID: | |
Farm/Lease Name: LOREN CHARLOTTE | |
License Status: Final Restoration | |
License Date: 2017-03-31 | |
Spud Date: 2005-11-01 | |
Spud Drilling Contractor: MARIC DRILLING CO. | |
Final Drill Date: 2005-11-15 | |
Well Total Depth: 3736.00 ft | |
Configuration: Directional | |
Latitude: 40.520000 | |
Longitude: -82.810000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2005-10-21 | Proposed Formations:BLACK RIVER/LIMESTONE, Issued Date:10/21/2005, Expired Date:10/21/2006 6:00:00 AM, Drilling unit acres:58, Proposed Well Type:OG, Proposed Well Class:POOL |
Correction to Well | 2005-10-21 | TARGET LOCATION: 1547'NL & 350'WL OF SE QTR., SEC. 12; X= 1,912,400; Y= 313,300; ELEV= 1171'. |
Original Spud | 2005-11-01 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
Completed | 2005-11-15 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
Reached Total Depth | 2005-11-15 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
Correction to Well | 2006-03-03 | CHANGES IN TARGET INFORMATION: FOOTAGE= 1637'NL & 398'WL OF SE QTR., SEC. 12; X= 1,912,450; Y= 313,210; ELEV.= 1172'. CHANGES IN SURFACE INFORMATION: FOOTAGE= 967' NL & 368'WL OF SE QTR., SEC.12; X= 1,912,440; Y= 313,880; ELEV.= 1172' (SOURCE OF LOCATION: AS DRILLED SURVEY). |
Completion Report Received | 2006-03-10 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
APP | 2014-04-25 | Proposed Formations:TRENTON/BLACK RIVER, Issued Date:4/25/2014, Expired Date:4/24/2016 12:00:00 PM, Drilling unit acres:58, Proposed Well Type:OG, Proposed Well Class: |
APP | 2017-03-31 | Proposed Formations:TRENTON-BLACK RIVER, Issued Date:3/31/2017, Expired Date:3/31/2019 12:00:00 PM, Drilling unit acres:58, Proposed Well Type:OG, Proposed Well Class: |
Plugged/Abandoned | 2017-04-11 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
Record Last Modified | 2018-01-18 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
Construction Permit Expires | 2019-03-31 | LOCATION UPDATED PER SURVEYOR COORDINATES 06/29/17 ALE. |
For data sources see[2]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
ACID | 0 | 500 Gal | 0 | OPEN HOLE ACID TREATMENT OF BLACK RIVER |
For data sources see[3]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2005 | MFC DRILLING INC | 0.00 | 0.00 | 0 |
2006 | MFC DRILLING INC | 0.00 | 345.00 | 274 |
2007 | MFC DRILLING INC | 0.00 | 232.00 | 365 |
2008 | MFC DRILLING INC | 0.00 | 37.00 | 365 |
2009 | MFC DRILLING INC | 0.00 | 0.00 | 365 |
2010 | MFC DRILLING INC | 0.00 | 15.00 | 365 |
2011 | MFC DRILLING INC | 0.00 | 60.00 | 365 |
2012 | MFC DRILLING INC | 0.00 | 163.00 | 366 |
2013 | MFC DRILLING INC | 0.00 | 0.00 | 365 |
2014 | MFC DRILLING INC | 0.00 | 0.00 | 365 |
2015 | MFC DRILLING INC | 0.00 | 0.00 | 365 |
2016 | MFC DRILLING INC | 0.00 | 0.00 | 365 |
2017 | MFC DRILLING INC | 0.00 | 0.00 | 0 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2005 | MFC DRILLING INC | Brine | 830 | |
2006 | MFC DRILLING INC | Brine | 1260 | 274 |
2007 | MFC DRILLING INC | Brine | 0 | 365 |
2008 | MFC DRILLING INC | Brine | 0 | 365 |
2009 | MFC DRILLING INC | Brine | 0 | 365 |
2010 | MFC DRILLING INC | Brine | 60 | 365 |
2011 | MFC DRILLING INC | Brine | 60 | 365 |
2012 | MFC DRILLING INC | Brine | 40 | 366 |
2013 | MFC DRILLING INC | Brine | 0 | 365 |
2014 | MFC DRILLING INC | Brine | 276 | 365 |
2015 | MFC DRILLING INC | Brine | 0 | 365 |
2016 | MFC DRILLING INC | Brine | 0 | 365 |
2017 | MFC DRILLING INC | Brine | 0 | 0 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1151232277 | 2017-3-13 0:00: | SC | No Violations | |
-1346747338 | 2014-7-30 0:00: | PW | No Violations | |
-1401971402 | 2005-12-23 0:00 | PW | No Violations | |
-2084308277 | 2017-4-10 0:00: | PB | No Violations | |
-2103972780 | 2017-4-11 0:00: | PB | No Violations | |
-469237051 | 2017-4-12 0:00: | FR | No Violations | |
-949827693 | 2012-10-25 0:00 | PW | No Violations | |
-989003539 | 2012-12-10 0:00 | PW | No Violations | |
0073055507 | 2017-06-16 | Final Restoration | No Violations | Received landowner waiver (form 5) from the operator. The landowner waived the complete entrance with limestone and culvert from the roadway edge to the agricultural field. |
0469237051 | 2017-04-12 | Final Restoration | No Violations | The operator added 7 sacks of quick rete to top off the hole. Photo documented identification plate affixed to casing. The operator has remove the flowlines, and drained and closed the workover pit. Discussed final restoration and landowner waivers needed. |
0708467319 | 2014-05-02 | Production Wells | No Violations | Location Information. ENTRANCE: Lat. 40.52813 Long. -82.81530 / WELL HEAD: Lat. 40.52785 Long. -82.81504 / CENTER-OF-STORAGE: Lat. 40.52808 Long. -82.81513. |
0949827693 | 2012-10-25 | Production Wells | No Violations | Inspected the Loren #1 (#4189) as part of a standard productive well status check. The well currently has no pump jack but sits with the rods installed, production has been reported in the past years. The storage has been recently painted and consists of one gray tank (#137892) set in a gravel lined dike. The well identification and emergency contact information is clearly mark on the storage. A horizontal gray separator sits south of the well. Status OK. |
0989003539 | 2012-12-10 | Production Wells | No Violations | Follow-up to previous inspection. According to MFC the well is slated for re-completion/work over. |
1130856886 | 2005-11-01 | Drill / Deepen / Reopen | No Violations | Drilling at 99 foot, preparing to run conductor. |
1137770720 | 2006-01-11 | Production Wells | No Violations | Chk well and storage, Ok. Storage tanks set and has a dike around them Flair is burning inside of the flair tube. The site is wet and muddy. |
1151232277 | 2017-03-13 | Surface Facility Construction | No Violations | The operator has removed the single storage tank from location. |
1184265785 | 2007-07-12 | Preliminary Restoration | No Violations | Preliminary restoation done. |
1185192454 | 2006-05-17 | Production Wells | No Violations | Chk well and storage, Ok. Pits closed site has been graded. |
1270172586 | 2017-06-20 | Final Restoration | No Violations | Inspected the Loren Charlotte #1 (#4189) as part of a standard final restoration status check. Waiver received for the entrance and culvert. Unused electric junction box on post west of the access road is not associated with the location. Status: final restoration complete. |
1346747338 | 2014-07-30 | Production Wells | No Violations | Coshocton Pipe service rig has moved onto location for completion testing. |
1397755384 | 2014-04-17 | Production Wells | No Violations | Had discussion with Mr. Jeff Harmon, Production Manager for MFC Drilling regarding the lack of progress on restoring the Loren Charlotte #1 to production (as reported in previous inspection). He stated he is aware of the concern and will discuss options with owner. Status: will continue to monitor. |
1398689791 | 2014-04-28 | Plug / Plug Back | No Violations | Permit to plug issued: 4/25/2014. Expires: 4/24/2014. |
1398779315 | 2014-04-29 | Plug / Plug Back | No Violations | The operator has abandoned plans to plug the well. Coshocton Pipe service rig has pulled the rods and is currently pulling the tubing. The operator is planning an alternative completion method. |
1401971402 | 2005-12-23 | Production Wells | No Violations | Setting up storage facilities and putting down gravel in lease road. Pumping unit installed on the well. |
1491918386 | 2017-04-07 | Plug / Plug Back | No Violations | On-site with Inspector Tom Benko. Coshocton Pipe finish laying down 2.875 inch tubing. Appalachian Wireline rigged up and ran-in-hole to set bridge plug inside the 5.5 inch casing. Bridge plug set at 2830. Coshocton Pipe started running 1.5 inch tubing into hole to begin plugging and shut down for the weekend. |
1492003967 | 2017-04-11 | Brine Hauler | No Violations | Inspect Mullins Energy Services brine truck providing fresh water for plugging operations. BRINE, UIC number and other identification clearly and properly displayed. Status: ok. |
1493123328 | 2017-04-24 | Final Restoration | No Violations | The operator has rough graded the site and has dug out the stone lease road, while leaving the entrance apron intact. |
1515591416 | 2014-04-25 | Plug / Plug Back | No Violations | Coshocton pipe service rig is on the well in preparation to plugging. Currently rigging up to begin pulling the rods. Permit to plug has been received in Columbus as per Patty Nicklaus. |
1535567051 | 2017-04-06 | Plug / Plug Back | No Violations | On-site with Inspector Tom Benko. Met with the operator and discussed downhole well construction and the plugging procedure. Coshocton Pipe service rig finished pulling the 1.5 inch tubing. 1:20 pm Appalachian Wireline run-in-hole to shoot off 2.78 inch production casing. First attempt failed, pulled out-of-hole and troubleshoot connections. Appalachian Wireline successfully shot off the casing at 2840. |
1705812894 | 2017-05-30 | Final Restoration | No Violations | Inspected the Loren #1 (#4189) as a standard final restoration status check. Status: corn has germinated through the entire area (well spot/storage/road). Stoned entrance and culvert remain for farmer access. Contacted operator with reminder on landowner waiver to complete restoration. |
1831031822 | 2014-05-02 | Casing String Witnessed | No Violations | Coshocton pipe service rig ran 2.875 inch tubing with 7 centralizers into the 4.75 inch slimhole horizontal at the side door cut out in the 5.5 inch casing at approximately 2982, to 3730 measured depth. Petroset hooked up and cemented with 50 sacks 50/50 poz. Well Information: Previously was an openhole horizontal well completion attempt in the Black River formation. A bridge plug was previously set in the 5.5 casing at 3005 feet. Status: Operator plans to perforate and acidize. |
2084308277 | 2017-04-10 | Plug / Plug Back | No Violations | Coshocton Pipe set tubing at 2812 and finished digging and lining the workover pit. Fresh water provided by Mullins Well Service. 11:00 am Petroset hooked up, broke circulation and circulated hole clean. 11:08 am Petroset displaced Plug #1 (Black River) 30 sacks Class A (2% gel) through 1.5 inch tubing: plug down 11:11 am. Hand pulled cement sample weighed 14.7 pounds per gallon. Coshocton Pipe laid down 1.5 inch tubing. Coshocton pipe run-in-hole and ripped 5.5 inch casing at 2308, pulled free and shut down for the day. |
2103972780 | 2017-04-11 | Plug / Plug Back | No Violations | Coshocton Pipe work on power tongs. 1:25 pm Coshocton Pipe begin pulling 5.5 inch casing. 3:30 pm Petroset on location, spot trucks. 4:50 pm Petroset break circulation and displaced 40 sacks Class A plug #2 (Newburg) through 5.5 inch casing. Plug down: 4:10 pm. Coshocton raised casing. Petroset hooked up, broke circulation and displaced 60 sacks Class A plug #3 (bottom of the surface casing) through 5.5 inch casing. Plug down: 4:35 pm. Coshocton raised casing. Petroset hooked up and displaced 50 sacks Class A cement to surface. Plug down: 5:50 pm. Plugging operations co-witnessed by Inspector Mr. Tom Benko and MFC representative Mr. Jim Orr. **The Loren Charlotte #1 (#4189) is officially plugged and abandoned.** |
708467319 | 2014-5-2 0:00:0 | PW | No Violations | |
73055507 | 2017-6-16 0:00: | FR | No Violations |
For data sources see[8]