37-115-21593

Well Details

Well ID: 37-115-21593
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Brooklyn Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 149403
Farm/Lease Name: MAKOSKY T 8
License Status:
Spud Date:
Permit Date: 2014-01-13
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.752678
Longitude: -75.834850

For data sources see[1][2][3]

Well History

Date Event
2014-01-13 New Permit Application
2014-03-20 Performed Spud Operation
2014-04-29 Drilling Completion
2014-09-14 Perforation
2014-10-23 Performed Stimulation
2015-01-30 DEVIATED

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2014-10-23 2014-11-03 7,132 7,119,760 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Ferrotrol 300L Baker Hughes Iron Control MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0037388 2521.35
Scaletrol 720, 330 gl tote Baker Hughes Scale Inhibitor MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.013477 9088.53
Ingredients in Additive(s) (MSDS and non-MSDS) Baker Hughes See Trade Name(s) List Hydrochloric Acid 7647-01-0 15 0.081582 55025.8
Formaldehyde 50-00-0 1 0.00000860 5.8
2-Propenoic, Polymer with Sodium Phosphinate, Sodium Salt 71050-62-9 20 0.0029921 2018.13
Water 7732-18-5 85 0.516653 348474
Polyoxythylene Sorbitan Monooleate 9005-65-6 0.5 0.0003928 264.935
Olefin 64743-02-8 5 0.00004300 29
Quaternary Ammonium Compound 68424-85-1 5 0.0011351 765.625
Modified Thiourea Polymer 68527-49-1 7 0.00006020 40.6
Citric Acid 77-92-9 60 0.0022429 1512.81
Fatty Acids 61790-12-3 10 0.00008600 58
Oleamide DEA 93-83-4 2 0.0015712 1059.74
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.0015712 1059.74
Hydrotreated Light Distillate 64742-47-8 30 0.0235678 15896.1
Calcium Chloride 10043-52-4 5 0.000748 504.533
Potassium Chloride 7447-40-7 1 0.0001496 100.907
Sodium Chloride 7647-14-5 5 0.0040776 2750.25
Ethanol 64-17-5 5 0.0011351 765.625
Methanol 67-56-1 100 0.0008599 580
Sorbitan Monooleate 1338-43-8 0.5 0.0003928 264.935
Glutaraldehyde 111-30-8 30 0.0068108 4593.75
Poly (acrylamide-co-acrylic acid) partial sodium salt 62649-23-4 30 0.0235678 15896.1
Didecyl Dimethyl Ammonium Chloride 7173-51-5 10 0.0022703 1531.25
Propargyl Alcohol 107-19-7 5 0.00004300 29
Crystalline Silica (Quartz) 14808-60-7 100 11.3061 7,625,800.0
Polyoxyalkylenes 68951-67-7 30 0.000258 174
Ammonium Chloride 12125-02-9 3 0.0023568 1589.61
Ethylene Glycol 107-21-1 45 0.0067322 4540.79
Water Operator Carrier Water 7732-18-5 100 88.0126 59,363,100.0
Sand, White, 40/70 Baker Hughes Proppant MSDS and Non-MSDS Ingredients Listed Below N/A 0 10.7128 7,224,400.0
Scaletrol 720 Baker Hughes Scale Inhibitor MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.001486 1002.12
Sand, White, 100 mesh Baker Hughes Proppant MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.59522 401400
HCl, 10.1 - 15% Baker Hughes Acidizing MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.543913 366800
FRW-18 Baker Hughes Friction Reducer MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0785723 52987
CI-14 Baker Hughes Corrosion Inhibitor MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0008601 580
Alpha 1427 Baker Hughes Biocide MSDS and Non-MSDS Ingredients Listed Below N/A 0 0.0227063 15312.5

For data sources see[5]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
2014-10-23 0 0 0

For data sources see[6]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2014 CABOT OIL & GAS CORP 406,128.43 23 0.00 0 0.00 0
2015 CABOT OIL & GAS CORP 4,848,539.71 365 0.00 0 0.00 0
2016 CABOT OIL & GAS CORP 2,235,158.01 366 0.00 0 0.00 0
2017 CABOT OIL & GAS CORP 1,344,463.85 365 0.00 0 0.00 0
2018 CABOT OIL & GAS CORP 1,040,825.00 365 0.00 0 0.00 0
2019 CABOT OIL & GAS CORP 826,231.00 363 0.00 0 0.00 0

For data sources see[7]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2014 CABOT OIL & GAS CORP Fracing Fluid Waste 501.62 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2014 CABOT OIL & GAS CORP Drill Cuttings 1,165.01 Tons LANDFILL 101247
2014 CABOT OIL & GAS CORP Fracing Fluid Waste 8,505.34 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Fracing Fluid Waste 1,112.64 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Produced Fluid 2,551.45 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Produced Fluid 5.26 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2016 CABOT OIL & GAS CORP Produced Fluid 234.19 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2016 CABOT OIL & GAS CORP Produced Fluid 247.19 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2017 CABOT OIL & GAS CORP Synthetic Liner Materials 0.06 Tons LANDFILL 101247
2017 CABOT OIL & GAS CORP Produced Fluid 125.61 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2017 CABOT OIL & GAS CORP Produced Fluid 10.66 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE004
2017 CABOT OIL & GAS CORP Produced Fluid 212.99 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 201.37 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 60.19 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2019 CABOT OIL & GAS CORP Produced Fluid 243.08 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002

For data sources see[8]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2257364 Primary Facility 2014-03-18 Routine/Partial Inspection No Violations Noted
2266470 Primary Facility 2014-03-24 Drilling/Alteration No Violations Noted Spudder rig on location
2301332 Primary Facility 2014-09-03 Incident- Response to Accident or Event No Violations Noted Arrived at the site at 9:45 in response to a spill of (10-15) gallons of drilling mud. I was accompanied by Briana Cunningham DEP O&G WQS during the inspection. Cabot Oil and Gas contacted DEP Northeast Regional Office Emergency Response Team on 8/31/14 at 5:22 PM to report the incident. Calvin Cooley, site Company man and Brody Webster EH&S Specialist were on-site. Cabot was in the process of rigging down equipment and cleaning up the site. Mr. Cooley explained that the spill occurred as the shale shaker was in the process of being moved from one section of the drilling rig secondary containment to another in order to clean it. The actual material spilled is synthetic oil based drilling mud. As the shale shaker was in the process of being transferred, residuals in the shaker spilled onto the surface of the ground on the well pad. The impacted area was excavated on 8/31/14. The surface was scraped one-half to (2) inches in depth where the impact occurred.
2372917 Primary Facility 2015-05-26 Routine/Complete Inspection No Violations Noted
2400590 Primary Facility 2015-08-20 Administrative/File Review No Violations Noted This administrative inspection has been created to document Cabot’s remediation of an approximately (10-15) gallon release of oil based drilling fluids to the pad surface that occurred on 8/31/14 as documented in the Department's 9/3/14 inspection report. Cabot submitted a Remediation Summary Report prepared by Resource Environmental Management Incorporated of Montrose, PA to the Department on 8/4/2015. The report indicates and on-site track-hoe was utilized to remove impacted soils immediately after the release occurred. A review of the Remediation Summary Report and e-mails submitted by Andy Mehalko, Environmental Supervisor of Cabot Oil and Gas, to the Department on 8/6/15 and 8/17/15 indicates that the remediation was adequate. No further action is required of Cabot at this time.
2471220 Primary Facility 2016-03-29 Follow-up Inspection No Violations Noted GDS responded to the release and used rakes and shovels to scrape the access road to the well site. He explained that this was done on the same day that the release occurred. He mentioned that they originally believed that 15 gallons were lost and that 5 impacted the ground however they now re-estimated it to 1 gallon off of containment. Mr. Watson said that it was reported to him that the majority was lost on SR 2024. He also explained that once GDS cleaned the impacted material up, that they stored it in a drum. The excavation was not screened because it was considered a small spill and no samples were collected. Mr. Watson explained that the release occurred around the area where the asphalt/dirt roads interface.
2471256 Primary Facility 2016-03-30 Follow-up Inspection No Violations Noted Steve Watson (Cabot Oil & Gas) contacted me on 3/25/16 at 1019 hours to report a release of (15) gallons of antifreeze from a truck in route to the Makosky Pad. Mr. Watson stated the following. “The release occurred at 0930 hours on 3/25/16. A hose clamp failed on the truck. The release occurred near the lease (access) road entrance. Approximately (10) gallons impacted the ground surface while the remaining (5) gallons impacted the paved road, PA State Route 2024. The well site has since dried from the rain event. The areas that were photographed by Mr. Schoonover (those that appeared to have fluid running over them) now have a white residue on the surface of the ground. The Department collected three separate samples: One within the excavation, one within the white residue, and one on the access road away from the excavation and closer to the access road gate. The soil samples will be analyzed for glycol in response to the antifreeze release.
2475343 Primary Facility 2016-04-15 Administrative/File Review No Violations Noted The Pennsylvania Department of Environmental Protection Bureau of Laboratories in Harrisburg, PA submitted sample results to the Department on 4/7/16 and 4/12/16. The Department collected the samples in the impacted area on the access road on 3/30/16. The reported results (the PaBol is not accredited for ethylene glycol analysis) indicate a concentration of (6,840) mg/kg of ethylene glycol in sample identification number 4559-213, point 001, and a concentration of (2,960) mg/kg of ethylene glycol in sample identification number 4559-214, point 002. These qualitative sample results indicate a potential exceedance of the Act 2, Residential Soil to Groundwater, Statewide Health MSC for Ethylene Glycol of (1,400) mg/kg. The concentration of ethylene glycol detected in the samples indicated the antifreeze spill was not properly remediated at that time.
2476707 Primary Facility 2016-04-20 Routine/Complete Inspection No Violations Noted At time of inspection, arrived on site at 11:05 a.m., the cellar was about a quarter full of water with no bubbling noticed, the (13x9) vent pipe was open and venting to a tank, the (9x5) vent pipe was open and venting to a tank, there was 660psi on the production casing. I took a walk around the location and everything looked OK.

I left the site at 12:00 p.m.

2483823 Primary Facility 2016-05-13 Administrative/File Review No Violations Noted On 5/12/16, Andy Mehalko, Environmental Supervisor, of Cabot Oil and Gas provided the Department a Remediation Summary Report prepared by Resource Environmental Management Incorporated of Montrose, PA. The Remediation Summary Report states the following information; Resource on behalf of Cabot mobilized to the site later in the day on 3/30/16 to evaluate soils. They had identified an excavation measuring approximately 7’X3’ x 1-2” on the east side of the access road approximately (83) feet form SR 2024. They collected (3) samples in the same locations as the Department had collected samples on the lease road. Concentrations of ethylene glycol exceeded the Statewide Health Standard (SHS) residential, used-aquifer (R-U) Medium Specific Concentration (MSC) in two (2) of the three (3) samples. Based on these results, additional soil remediation was scheduled by Cabot.

Ethylene Glycol was reported at (6,840) mg/kg in sample number 4559-213 and (2,940) mg/kg in sample number 4559-214, both samples collected

2551811 Primary Facility 2017-01-09 Routine/Complete Inspection No Violations Noted The Department was on site to conduct a routine complete inspection of the Makosky T well site, ESX10-115-0050.

There are 8 wells associated with this site. They are as follows: 115-21586 115-21587 115-21588 115-21589 115-21590 115-21591 115-21592 115-21593 The pad has been considerably shrunk down and it appears PCSMs have been installed. Growth is good, even in recently worked areas. The access road is in good shape with no issues at this time.

There were no erosion or sedimentation issues on site at this time.

There were no violations

If there are any questions please feel free to contact me at (570)346-5539.

2665546 Primary Facility 2017-11-13 Site Restoration No Violations Noted Photo 1 is a picture of infiltration berm # 1. Photo 2 is a picture of the pad layout. This inspection was conducted to confirm Cabot's assessment that the project meets the minimum requirements for permanent stabilization. The Department's determination is that the site meets the requirements for permit termination. I recommend the NOT be approved.

For data sources see[9]