37-115-20284

Well Details

Well ID: 37-115-20284
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Dimock Township
Operator Name: CABOT OIL & GAS CORP
Well Pad ID: 148440
Farm/Lease Name: GREENWOOD 8
License Status:
Spud Date:
Permit Date: 2010-03-17
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.751081
Longitude: -75.867808

For data sources see[1][2][3]

Well History

Date Event
2010-03-17 New Permit Application
2010-05-05 Performed Spud Operation
2010-06-01 Drilling Completion
2010-06-13 Perforation
2010-08-18 Performed Stimulation
2011-01-25 DEVIATED

For data sources see[4]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
2010-08-18 0 0 0

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 CABOT OIL & GAS CORP 1,473,734.00 122 0.00 0 0.00 0
2011 CABOT OIL & GAS CORP 2,566,467.41 347 0.00 0 0.00 0
2012 CABOT OIL & GAS CORP 1,216,366.88 365 0.00 0 0.00 0
2013 CABOT OIL & GAS CORP 970,890.16 365 0.00 0 0.00 0
2014 CABOT OIL & GAS CORP 785,652.72 355 0.00 0 0.00 0
2015 CABOT OIL & GAS CORP 303,080.48 365 0.00 0 0.00 0
2016 CABOT OIL & GAS CORP 676,524.00 366 0.00 0 0.00 0
2017 CABOT OIL & GAS CORP 505,012.60 365 0.00 0 0.00 0
2018 CABOT OIL & GAS CORP 463,214.00 365 0.00 0 0.00 0
2019 CABOT OIL & GAS CORP 326,711.00 306 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2010 CABOT OIL & GAS CORP Fracing Fluid Waste 9,916.00 Bbl REUSE OTHER THAN ROAD SPREADING
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 262.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR119
2010 CABOT OIL & GAS CORP Produced Fluid 1,855.75 Bbl REUSE OTHER THAN ROAD SPREADING
2010 CABOT OIL & GAS CORP Basic Sediment 2.96 Bbl LANDFILL 101534
2010 CABOT OIL & GAS CORP Drilling Fluid Waste 157.70 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0101508
2010 CABOT OIL & GAS CORP Drill Cuttings 79.30 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 101247
2010 CABOT OIL & GAS CORP Drill Cuttings 22.40 Tons LANDFILL NY # 50S08
2010 CABOT OIL & GAS CORP Drill Cuttings 129.10 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE 8-4630-00010/00
2010 CABOT OIL & GAS CORP Drill Cuttings 129.10 Tons LANDFILL NY # 02S17
2010 CABOT OIL & GAS CORP Drill Cuttings 1.70 Tons LANDFILL 100955
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 524.98 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CABOT OIL & GAS CORP Drill Cuttings 0.64 Tons LANDFILL 101534
2011 CABOT OIL & GAS CORP Fracing Fluid Waste 1.32 Bbl LANDFILL 301626
2011 CABOT OIL & GAS CORP Drill Cuttings 4.03 Tons LANDFILL 101247
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 9.42 Bbl LANDFILL 301626
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 11.67 Bbl LANDFILL 100955
2011 CABOT OIL & GAS CORP Drill Cuttings 54.57 Tons LANDFILL THR029
2011 CABOT OIL & GAS CORP Basic Sediment 10.15 Bbl LANDFILL 101534
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 6.87 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PAD014286009
2011 CABOT OIL & GAS CORP Produced Fluid 1,767.11 Bbl REUSE OTHER THAN ROAD SPREADING
2011 CABOT OIL & GAS CORP Drill Cuttings 4.35 Tons LANDFILL 132310
2011 CABOT OIL & GAS CORP Drill Cuttings 0.82 Tons LANDFILL 100081
2011 CABOT OIL & GAS CORP Drilling Fluid Waste 5.04 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE
2011 CABOT OIL & GAS CORP Drill Cuttings 11.64 Tons CENTRALIZED TREATMENT PLANT FOR RECYCLE PAD014286009
2012 CABOT OIL & GAS CORP Produced Fluid 1,066.82 Bbl REUSE OTHER THAN ROAD SPREADING
2012 CABOT OIL & GAS CORP Basic Sediment 2.21 Bbl LANDFILL THR029
2012 CABOT OIL & GAS CORP Basic Sediment 2.82 Bbl LANDFILL 100081
2012 CABOT OIL & GAS CORP Basic Sediment 6.55 Bbl LANDFILL 101534
2012 CABOT OIL & GAS CORP Produced Fluid 14.84 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NE001
2013 CABOT OIL & GAS CORP Produced Fluid 315.88 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE WMGR123NE002
2013 CABOT OIL & GAS CORP Produced Fluid 154.83 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2014 CABOT OIL & GAS CORP Produced Fluid 190.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2014 CABOT OIL & GAS CORP Produced Fluid 60.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2015 CABOT OIL & GAS CORP Produced Fluid 185.59 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2015 CABOT OIL & GAS CORP Produced Fluid 4.25 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE001
2016 CABOT OIL & GAS CORP Produced Fluid 209.59 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2016 CABOT OIL & GAS CORP Produced Fluid 192.46 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NE002
2017 CABOT OIL & GAS CORP Produced Fluid 209.77 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2017 CABOT OIL & GAS CORP Produced Fluid 150.35 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2018 CABOT OIL & GAS CORP Produced Fluid 270.67 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2018 CABOT OIL & GAS CORP Produced Fluid 165.04 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018
2019 CABOT OIL & GAS CORP Produced Fluid 273.11 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NE002
2019 CABOT OIL & GAS CORP Servicing Fluid 1.79 Tons LANDFILL 100933
2019 CABOT OIL & GAS CORP Servicing Fluid 200.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC018

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1886580 Primary Facility 2010-05-13 Drilling/Alteration Viol(s) Noted & Immediately Corrected Patterson 252. Surface casing set and cemented. Crew getting ready to drill out 9 5/8" shoe. Closed loop system. All cuttings being direct loaded for disposal. BOPs tested and passed. Drillers log was not filled out. Depth of drilling was @ 1500'. I spoke with the mudlogger, toolpusher, driller, and company man on location, and explained what is required in the drillers log. The Operator immediately corrected the violation. No outstanding violations exist.
1947546 Primary Facility 2011-01-05 Routine/Partial Inspection Violation(s) Noted SW-defective cement job, 78.86(a) & 78.81(a)(2)&(3), 0.0 psi at 9 5/8 annulus & 0.4 psi at 5 1/2 annulus, 0.5% gas peaked at 9 5/8 annulus & 90% gas peaked at 5 1/2 annulus, 10 day response requested.
1956783 Primary Facility 2011-03-05 Routine/Complete Inspection No Violations Noted
1980748 Primary Facility 2011-06-13 Follow-up Inspection Violation(s) Noted
2007727 Primary Facility 2011-09-02 Routine/Complete Inspection No Violations Noted
2028185 Primary Facility 2011-12-08 Routine/Complete Inspection No Violations Noted Well is online. Vents are open - vented to Brine Tank. Approx. 2 - 3' water in cellar. No bubbling in cellar. Gauge on well reading @ 3400 psi. Inspection completed as part of an ongoing gas migration investigation.
2035721 Primary Facility 2011-12-05 Incident- Response to Accident or Event Violation(s) Noted
2139940 Primary Facility 2013-02-14 Follow-up Inspection No Violations Noted On site to collect pressure readings from annuli of well. DEP reps on site = Steve Watson, Eric Rooney, and Gene Rickard. DEP met with John Smelko of Cabot. Selman reps on site to assist with collection of pressure data. Cabot shut in annuli at @ 9am this morning. Cabot installed a digital gauge on the 16" x 9 5/8" annulus. Pressure was 0 psi. Gauge was removed and open vent flow was screened using a Model 60 gas meter. Model 60 reading = 0% cobustible gas. Gauge was then installed on 9 5/8" x 5 1/2" annulus. Pressure = 1 psi. Model 60 reading = 100 % combustible gas. No samples were collected. After completion of testing, Cabot re-conected vent lines and locked vents open.
2481924 Primary Facility 2016-04-27 Routine/Partial Inspection No Violations Noted The Department was on site at the Greenwood, R. Pad 1 to conduct a Routine Partial Inspection. The E&S Inspection Log indicated that Mike Brilla (TEC) conducted a Post Rain Event Inspection on 4/27/16. It appears as though the landowner has made a road to the left of the access road gate to circumvent said gate. Also, it seems as if the landowner has been working areas on the well site. There is a large area within the well pad surface that looks like wood chips have been strewn across it and sections of plastic packaging are intermixed.

The perimeter ditch does not appear to meet temporary stabilization requirements. The Department requests that the operator investigate the area and deploy a method of erosion control that is consistent with your plan. The production tanks were stained during the inspection. One of the tanks has more staining than the other. The Department requests that the operator inspect the tanks to find the origin of the staining.

2528907 Primary Facility 2016-10-17 Follow-up Inspection No Violations Noted
2642428 Primary Facility 2017-10-02 Site Restoration No Violations Noted I inspected the site for notice of termination (NOT) on October 2, 2017. The site was surrounded by active agriculture (field corn). The access road leading in was in good shape with no rutting and the site was well vegetated on the cut and fill slopes. The pad surface was solid and stable as well. There were no erosional issues noted.

I recommend APPROVAL of this NOT.

There were no violations observed.

2774791 Primary Facility 2018-09-11 Routine/Complete Inspection No Violations Noted Arrived on location at 09:00. Weather: ~ 65 degs., light rain, slight breeze. Onsite to initiate 72 hr. pressure build up test "PBUT" on the annuli of the Greenwood 1V, 6H, 7H & 8H wells. All wells, back side of production casing annuli have been isolated and were venting to onsite poly vent tanks. The 6H, 7H & 8H wells (16"x 9 5/8") cemented annuli had open top 16" casings in cellar *. The 1V wells (9 5/8"x 7") cemented annulus was beneath water level in cellar, no bubbling was noted at time of inspection.

- Upon arrival I met with Cabot O&G Reps. Jeremy Rapp and Sully Rutledge. Prior to shutting in wells annuli, initial gas screenings and flow checks were performed at the 1V (7"x 4 1/2") and 6H, 7H & 8H (9 5/8"x 5 1/2") annuli using the Depts. Altair 5X gas meter, calibrated this morning, and Cabots' RS-484 Alicat "Whisper" flow meter. Pre-shut in screenings showed: - 1V: (7"x 4 1/2") = 100% CH4, 9.2 cf/d; (9 5/8"x 7") open casing top in cellar, No bubbling noted. - 6H: (9 5/8"x 5 1/2") = 100% CH4, 15.2 cf

2775557 Primary Facility 2018-09-14 Routine/Complete Inspection Pending Arrived on location at: 09:00. Weather: ~ 75 degs., Light rain, Slight breeze. Onsite to conclude the 72-hr. pressure build up test ¿PBUT¿ being performed on the Greenwood 1V, 6H, 7H & 8H wells, back side of production casing annuli and the 1V¿s (9 5/8¿x 7¿) cemented annulus.

- Upon arrival I met with Cabot O&G Rep. Sully Rutledge and Selman and Associates Reps. Kaydee Oliver and Russell Mohlt. There was also a GDS Vac Truck and Operator onsite to add or remove water to cellar areas as needed. The ending PBUT pressures were checked by Cabot Rep. using a digital Crystal pressure gauge. Ending pressures are listed below: - 1V: (7"x 4 ½¿) = 21 psi., Gas sample taken = 100% CH4; (9 5/8"x 7") = 0.0 psi., No sample taken. Cellar was initially full of water w/ no bubbling noted. Cellar was then emptied confirming (9 5/8"x 7") vent line connection to enclosed casing top. - 6H: (9 5/8¿ x 5 ½¿) = 12.0 psi. Gas sample taken = 100% CH4; (16"x 9 5/8") = 0.0 psi. (Open casing top in cellar). Cellar was initially full of w

2804931 Primary Facility 2018-11-15 Follow-up Inspection Pending Arrived on location at 11:00. Weather: Overcast, ~ 32 degs., Snow forecast for this afternoon. Onsite to perform initial gas flow checks at the 8H wells annuli, prior to starting the follow-up 72 hr PBUT on this well. At conclusion of the initial PBUT on 9/14/18, bubbling gas was noted to inside of the open top (16"x 9 5/8") annulus. Since the last PBUT, Cabot has capped off and contained this annulus in preparation for this follow-up PBUT. (* See Pic #1.)

Upon arrival I met with Cabot O&G Rep. Jeremy Rapp. Also present were DEP Reps. Eric Rooney, Geologist and Casey Baldwin, WQS. Initial gas screenings and flow checks were performed using the Depts. Altair 5X gas meter, calibrated this morning, and Cabots' RS-484 Alicat "Whisper" flow meter. Pre-shut in screenings showed: - 8H: (16"x 9 5/8") = 0% CH4, 0.0 cf/d; (9 5/8"x 5 1/2"") = 100% CH4, 12.8 cf/d.

* Possible concern that the existing 2" (16"x 9 5/8") annular vent may be blocked by cement or debris since previous bubbling was noted in this annulus at c
2805195 Primary Facility 2018-11-19 Follow-up Inspection Pending Arrived on location at 09:00. Weather: Overcast, ~ 32 degs., Recent snowfall ~ 10". Onsite for conclusion of the follow-up 72 hr PBUT on the 8H wells annuli. At conclusion of the initial PBUT on 9/14/18, bubbling gas was noted to inside of the open top (16"x 9 5/8") annulus. Since the last PBUT, Cabot has capped off and contained this annulus in preparation for this follow-up PBUT. (* See Pic #1.)

Upon arrival I met with Cabot O&G Rep. Jeremy Rapp. Also present was DEP Rep. Eric Rooney, Geologist and Selman & Assoc. Rep. Tyler Thomas. The ending PBUT pressures were checked by Cabot Rep. using a digital Crystal pressure gauge. Ending gas checks were performed using the Dept's Altair 5X gas meter, calibrated on 11/15/18. Ending pressures and gas screening results are listed below:

- 8H: (16"x 9 5/8")* = -3.0 psi. (vac.), 15% LEL, 0% CH4. Gas sample collected, bag gas check showed <5% LEL, 0% CH4. Results too low to send for analysis. (9 5/8"x 5 1/2")** = 17.5 psi., 100% CH4. Sample collected at 09:10.

  • Co

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
1886580 587792 05/13/2010 2010-05-13 78.122 - Drillers Log not on site Administrative drillers log not filled out and kept up to date
1947546 604118 01/05/2011 2011-01-05 78.86* - Failure to report defective, insufficient, or improperly cemented casing w/in 24 hrs or submit plan to correct w/in 30 days Administrative 0.0 psi at 9 5/8 annulus & 0.4 psi at 5 1/2 annulus, 0.5% gas peaked at 9 5/8 annulus & 90% gas peaked at 5 1/2 annulus
1947546 604119 01/05/2011 2011-01-05 207B - Failure to case and cement to prevent migrations into fresh groundwater Environmental Health & Safety 78.81(a)(2)&(3) - 0.0 psi at 9 5/8 annulus & 0.4 psi at 5 1/2 annulus, 0.5% gas peaked at 9 5/8 annulus & 90% gas peaked at 5 1/2 annulus
1980748 613571 06/13/2011 2011-06-13 78.65(1)* - Rat hole not filled Environmental Health & Safety rathole cleaned and filled in
1980748 613572 06/13/2011 2011-06-13 78.56(1) - Pit and tanks not constructed with sufficient capacity to contain pollutional substances. Administrative rathole cleaned and filled in
1980748 613573 06/13/2011 2011-06-13 402CSL B - Failure to meet requirements of permit, rules and regulations, or order of DEP. Environmental Health & Safety rathole cleaned and filled in
1980748 613574 06/13/2011 2011-06-13 SWMA301 - Failure to properly store, transport, process or dispose of a residual waste. Environmental Health & Safety rathole cleaned and filled in
2035721 629834 12/05/2011 2011-12-05 78.54* - Failure to properly control or dispose of industrial or residual waste to prevent pollution of the waters of the Commonwealth. Environmental Health & Safety
2035721 629835 12/05/2011 2011-12-05 691.1 - Clean Streams Law-General. Used only when a specific CLS code cannot be used Administrative 402- potential for pollutional substances to enter the waters of the commonwealth
2035721 629836 12/05/2011 2011-12-05 SWMA301 - Failure to properly store, transport, process or dispose of a residual waste. Environmental Health & Safety 401- management of hazardous waste

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
604118 267424 NOV - Notice of Violation
604119 267424 NOV - Notice of Violation
613571 272562 NOV - Notice of Violation
613572 272562 NOV - Notice of Violation
613573 272562 NOV - Notice of Violation
613574 272562 NOV - Notice of Violation
629834 279932 NOV - Notice of Violation
629835 279932 NOV - Notice of Violation
629836 279932 NOV - Notice of Violation

For data sources see[8]

References