Well Details

Well ID: 37-063-36517
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: Black Lick Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: RALPH SHAFFER 7
License Status:
Spud Date: 2009-11-23
Permit Date: 2009-04-17
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.478660
Longitude: -79.273489

For data sources see[1][2][3]

Well History

Date Event
2009-04-17 New Permit Application
2009-11-23 Performed Spud Operation
2009-12-02 Drilling Completion
2009-12-11 Perforation
2010-02-18 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 PHILLIPS EXPLORATION INC 5,990.00 256 0.00 0 0.00 0
2011 PHILLIPS EXPLORATION INC 10,315.00 319 0.00 0 0.00 0
2012 XTO ENERGY INC 10,198.00 366 0.00 0 0.00 0
2013 XTO ENERGY INC 10,064.00 365 0.00 0 0.00 0
2014 XTO ENERGY INC 8,757.00 365 0.00 0 0.00 0
2015 XTO ENERGY INC 8,161.00 365 0.00 0 0.00 0
2016 XTO ENERGY INC 7,454.00 366 0.00 0 0.00 0
2017 ALLIANCE PETRO CO LLC 5,644.00 334 0.00 0 0.00 0
2018 ALLIANCE PETRO CO LLC 8,224.00 365 0.00 0 0.00 0
2019 ALLIANCE PETRO CO LLC 7,086.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2013 XTO ENERGY INC Produced Fluid 24.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273
2013 XTO ENERGY INC Produced Fluid 24 Bbl CENT WASTE TRT FAC NPDES PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1828177 Primary Facility 2009-09-10 Drilling/Alteration No Violations Noted According to records, well permit issued on 4/17/09. Site pad completed. Two pits completed not aligned with plastic. Based on site conditions, no indication of IW issues at the site. Well sign and E&S plan located at entrance way of site pad. No E&S issues at the site. Well marked with survey marker
1849714 Primary Facility 2009-12-03 Routine/Complete Inspection No Violations Noted At the time of inspection, the well was drilled but not set for production. The site was properly signed with E&S plan available for review. Access road to well site was slightly muddy and culvert pipe was damaged, it is recommended that rock be added to the access road and that culvert pipe is replaced in order to prevent erosion and sedimentation concerns promptly. Noted that pit liner did not appear to be tightly secured which could pose a threat for industrial discharge onto grounds of the commonwealth and the pit freeboard was near the 2ft limit. I observed the installation of filter fabric fence below gradient from well pad, but it is recommended the fence be maintained in order to prevent accelerated erosion and sedimentation off well pad, since areas of the fence appeared to be structurally weak. It is highly recommended that operator continue to closely monitor pit freeboard and all Bmp¿s until final restoration activities are completed to maintain compliance. A follow up inspection will be conducted by April Weiland in the near future.
1930546 Primary Facility 2010-11-22 Site Restoration No Violations Noted At the time of inspection, well in production and tag present.
2515015 Primary Facility 2016-08-10 Routine/Complete Inspection No Violations Noted 8/10/2016 - Produced fluids tank, annulus closed.

For data sources see[7]