37-063-34775

Well Details

Well ID: 37-063-34775
Loading map...
Country: United States
State: Pennsylvania
County: Indiana
Municipality: Center Township
Operator Name: ALLIANCE PETRO CO LLC
Well Pad ID:
Farm/Lease Name: ANDERSON-WALKER-GEORGE 1
License Status: ACTIVE
Spud Date: 2006-06-08
Permit Date: 2006-05-04
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.571301
Longitude: -79.217434

For data sources see[1][2][3]

Well History

Date Event
2006-05-04 New Permit Application
2006-06-08 Performed Spud Operation
2006-06-22 Drilling Completion
2006-07-11 Perforation
2006-08-29 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2006 PHILLIPS EXPLORATION INC 17,430.00 93 0.00 0 0.00 0
2007 PHILLIPS EXPLORATION INC 142440.00 365 0.00 0 0.00 0
2008 PHILLIPS EXPLORATION INC 200315.00 366 0.00 0 0.00 0
2009 PHILLIPS EXPLORATION INC 82271.00 347 0.00 0 0.00 0
2010 PHILLIPS EXPLORATION INC 9,929.00 358 0.00 0 0.00 0
2011 PHILLIPS EXPLORATION INC 2,665.00 319 0.00 0 0.00 0
2012 XTO ENERGY INC 72.00 105 0.00 0 0.00 0
2013 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2014 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2015 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2016 XTO ENERGY INC 0.00 0 0.00 0 0.00 0
2017 ALLIANCE PETRO CO LLC 0.00 0 0.00 0 0.00 0
2018 ALLIANCE PETRO CO LLC 12.00 365 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2008 PHILLIPS EXPLORATION INC Brine 1,049.00 Bbl Brine or Industrial Waste Treatment Plt PA0101508
2010 PHILLIPS EXPLORATION INC Produced Fluid 1,641.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE 301353
2010 PHILLIPS EXPLORATION INC Produced Fluid 222.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026310
2010 PHILLIPS EXPLORATION INC Produced Fluid 196.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443
2010 PHILLIPS EXPLORATION INC Produced Fluid 258.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2010 PHILLIPS EXPLORATION INC Produced Fluid 1.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0020346
2010 PHILLIPS EXPLORATION INC Produced Fluid 3.00 Bbl PUBLIC SEWAGE TREATMENT PLANT PA0026034
2010 PHILLIPS EXPLORATION INC Produced Fluid 70.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472
2011 PHILLIPS EXPLORATION INC Produced Fluid 645.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0254185
2011 PHILLIPS EXPLORATION INC Produced Fluid 705.00 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273
2013 XTO ENERGY INC Produced Fluid 14.00 Bbl REUSE OTHER THAN ROAD SPREADING
2017 ALLIANCE PETRO CO LLC Produced Fluid 36.00 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1546798 Primary Facility 2006-06-09 Drilling/Alteration No Violations Noted CEMENTING MINE STRING/PIT/E&S & NOTIFICATION OK
1555063 Primary Facility 2006-06-27 Routine/Complete Inspection No Violations Noted ONSITE WITH CITIZENS ADVISORY COUNCIL
1939270 Primary Facility 2010-12-28 Routine/Complete Inspection No Violations Noted Producing gas. tag, tank, e&s ok.
2768993 Primary Facility 2018-08-29 Administrative/File Review In Compliance with Policy ADMIN inspection in response to an operator reported release of 35 gal of brine. Department contacted operator rep Kirk Elkin by phone. Mr. Elkin states that the well had been out of service and when it was put back into service one of the relief valves malfunctioned and released approximately 35 gal of brine to the ground. Mr. Elkin states he instructed the field personnel to use straw and hay bales to soak up fluid and to keep it from migrating. Mr. Elkin does not feel any waterways were impacted.

Operator appears to be in compliance at this time. A site visit will be conducted at a later date.

2769618 Primary Facility 2018-08-30 Incident- Response to Accident or Event Violation(s) Noted FUI to inspection record #2768993 where operator reported a release of 35 gal of brine.

At this time, contractors on site working on production equipment. At time of inspection it appears impacted soil has been excavated. Area of excavation begins near brine tank and extends off-site to the south (photo #1-2). Department recommends operator temporarily stabilize disturbed area to avoid any E and S issues. Hay bales are installed in a trench at the southernmost area of earth disturbance (photo #3). Excavated soil located on a tarp on site. This soil is encapsulated in plastic liner and appears to be contained (photo #4). Violations are being issued for operator discharge of brine or other fluids, and for disposal of residual waste inconsistent with DEP rules and regulations. A follow up inspection will be conducted at a later date.

2776266 Primary Facility 2018-09-14 Administrative/File Review Outstanding Violations - Viols Req'd Department received operator response to NOV (photo #1).

Violations issued on 8-30-18 remain outstanding. A follow up inspection will be conducted at a later date.

2786216 Primary Facility 2018-10-09 Compliance Evaluation No Violations Noted Compliance Evaluation Inspection to inspection record #2769618 where violations were issued for operator discharge of brine or other fluids and for disposal of residual waste inconsistent with DEP rules and regulations.

At time of inspection impacted soil has been removed from site. Area of excavation appears backfilled and seeded (photo #1). Vegetation is beginning to grow (photo #2). Hay bales remain on site (photo #3). Department recommends operator continue to monitor and maintain site to avoid any E and S issues. Department recommends operator monitor site to ensure vegetation reaches >70% uniform growth and permanent stabilization is achieved. Violations issued on 8-30-18 have been corrected.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2769618 826879 2018-08-30 2018-10-09 78.57(a) Environmental Health & Safety
2769618 826880 2018-08-30 2018-10-09 SWMA 301 Environmental Health & Safety
2776266 828180 2018-09-14 2018-10-09 78.57(a) Environmental Health & Safety
2776266 828181 2018-09-14 2018-10-09 SWMA 301 Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
826879 367124 NOV - Notice of Violation 2018-10-10
826880 367124 NOV - Notice of Violation 2018-10-10
828180 367124 NOV - Notice of Violation 2018-10-10
828181 367124 NOV - Notice of Violation 2018-10-10