37-015-23403

Well Details

Well ID: 37-015-23403
Loading map...
Country: United States
State: Pennsylvania
County: Bradford
Municipality: Leroy Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 154875
Farm/Lease Name: SGL-12 N WEST UNIT 1H
License Status:
Spud Date:
Permit Date: 2018-02-07
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.654406
Longitude: -76.693242

For data sources see[1][2][3]

Well History

Date Event
2018-02-07 New Permit Application
2018-06-19 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 CHIEF OIL & GAS LLC 3,462,856.31 244 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 CHIEF OIL & GAS LLC Drill Cuttings 1,568.86 Tons LANDFILL 301358
2018 CHIEF OIL & GAS LLC Drilling Fluid Waste 708.62 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 CHIEF OIL & GAS LLC Drilling Fluid Waste 101.93 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 CHIEF OIL & GAS LLC Synthetic Liner Materials 13.46 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 570.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 CHIEF OIL & GAS LLC Synthetic Liner Materials 20.18 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 40,386.50 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2737624 Primary Facility 2018-06-05 Preoperation Inspection No Violations Noted Site meets the requirements of § 3258. Inspection and production of materials, witnesses, depositions and rights of entry.

(a.1) Preoperation inspections.--The operator may not commence drilling activities until the department has conducted an inspection of the unconventional well site after the installation of erosion and sediment control measures. The department may conduct follow-up inspections of well sites and related activities to determine compliance with this chapter. All E&Scontrols in place. Site built to plan design. No violations noted. The pre-operational inspection is approved as of 6/5/2018.

2743923 Primary Facility 2018-06-21 Routine/Complete Inspection No Violations Noted Warm/sunny at time of inspection.

At time of inspection crews were drilling and setting conductor.

2770315 Primary Facility 2018-09-04 Routine/Complete Inspection No Violations Noted Weather was 73° and cloudy at time of inspection. Met with Chief representative Jeremy Watson on location. Rig was in the process of drilling the 8 3/4" hole for the production casing. They estimate a TD of 16,550'. They were anticipating cementing the casing on Wednesday 9/5/18. Reviewed the cement job log for the intermediate casing and no discrepancies were noted. Performed a walk around inspection of location and no violations were noted at time of inspection.

For data sources see[7]