37-015-23388

Well Details

Well ID: 37-015-23388
Loading map...
Country: United States
State: Pennsylvania
County: Bradford
Municipality: Leroy Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 154215
Farm/Lease Name: SGL-12 K NORTH UNIT 1H
License Status:
Spud Date:
Permit Date: 2018-01-18
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.637997
Longitude: -76.711742

For data sources see[1][2][3]

Well History

Date Event
2018-01-18 New Permit Application
2018-03-08 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2019 CHIEF OIL & GAS LLC 1,850,907.01 149 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2018 CHIEF OIL & GAS LLC Drill Cuttings 1,257.31 Tons LANDFILL 301358
2018 CHIEF OIL & GAS LLC Synthetic Liner Materials 14.02 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 280.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 CHIEF OIL & GAS LLC Synthetic Liner Materials 12.56 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Soil Contaminated by Oil 0.34 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Soil Contaminated by Oil & Gas Related Spills 0.34 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 21,042.48 Bbl REUSE (AT WELL PAD)

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2717531 Primary Facility 2018-04-12 Drilling/Alteration No Violations Noted Universal conducting stimulation activities. No leaks detected.
2730022 Primary Facility 2018-05-15 Routine/Complete Inspection No Violations Noted Arrived at 11:30. Weather: windy but nice. There were one shut in well and three conductor only spuds on location. There were six empty oil based mud tanks. Rig mats and liner were still down. No violations were observed at the time of this inspection.
2739673 Primary Facility 2018-06-11 Routine/Complete Inspection No Violations Noted On 6/10/18 a drilling resumption after break of 30 days or more notification was submitted to the Department. The date and time of this action will occur on 6/12/2018 at 10 pm.

The Department arrived on 6/11/2018 for a inspection of containment and E&S controls. All conditions on the well pad were acceptable. The setup of Precision Rig 569 and equipment is underway. No violations noted.

2770330 Primary Facility 2018-09-04 Routine/Complete Inspection No Violations Noted The weather was 71° and partly sunny at time inspection. There were no Chief representatives on location at time of inspection. Well had a 0-10k psi gauge attached above the swab valve on on the wing valves off the well head. The gauge off the swab valve appeared to be closed in and read 0 psi. One of the 2 gauges on the wing valves was broken and one read approximately 600 psi at time of inspection. There were 2 annulus vents plumbed to surface at time of inspection. One the the vents was the 9x5 annulus vent and the other was the 13x9 annulus vent. Both vents were closed in with bull plugs at the well then plumbed together into a poly vent tank at time of inspection. Vents were open to the poly vent at time of inspection. The poly vent tank had 100% LEL and 60% methane detected at time of inspection. No violations were noted at time of inspection.
2850917 Primary Facility 2019-03-08 Routine/Complete Inspection No Violations Noted Inspection conducted in response to a request for a well site restoration extension and to assess overall site conditions. Four wells are staged for production. Two wells are appropriately labeled with their respective well permit numbers and two are not. Two unlabeled white plastic containers are staged near the well heads. The Department recommends labeling the containers. A battery of frac tanks is set-up within secondary containment. The tanks and containment appear to be in good condition. Four roll-off boxes, a tractor trailer, and a vac tank were also present on the pad. One steel produced water tank is present within steel containment with spray-in lining. There is minor corrosion on the produced water tank and the thief hatch on the tank appears to be open. The containment is in good condition. Four GPUs are present within secondary containment. The GPUs and containment are in good condition overall.

Site was snow-covered at the time of inspection. PCSM structures are installed according to the