37-015-23316

Well Details

Well ID: 37-015-23316
Loading map...
Country: United States
State: Pennsylvania
County: Bradford
Municipality: Leroy Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 154215
Farm/Lease Name: SGL-12 K SOUTH UNIT 1H
License Status:
Spud Date:
Permit Date: 2017-04-28
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 41.637956
Longitude: -76.711951

For data sources see[1][2][3]

Well History

Date Event
2017-04-28 New Permit Application
2017-08-28 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2018-04-08 2018-04-19 8,584 16,085,900 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand Sargent/Unimin Proppant Listed Below
Unihib G GeoSafe Acid Inhibitor Listed Below
Methanol 67-56-1 5 0.00001000 9
Hydrochloric acid 7647-01-0 15 0.02152 33546
Water 7732-18-5 50 0.03524 54918
Thiourea 62-56-6 1 0.00001000 2
Ethoxylated (C10-16) alcohols 68002-97-1 35 0.00004000 66
Water 7732-18-5 85 0.12197 190093
Glutaraldehyde 111-30-8 5 0.00118 1831
Ethanol, 2,2',2"-nitrilotris-,
tris(dihydrogen phosphate) (ester), sodium salt
68171-29-9 30 0.0016 2494
Copolymer of 2-Propenamide 79-06-1 20 0.01409 21967
Alcohols, C12-16, ethoxylated 68551-12-2 2 0.00141 2197
Formaldehyde 50-00-0 1 0.00001000 2
Oleic acid diethanolamide 93-83-4 2 0.00141 2197
2-Propenoic acid, polymer with 2-propenamide, sodium salt 25987-30-8 20 0.01409 21967
Crystallilne silica 14808-60-7 100 13.6247 21,234,100.0
Water 7732-18-5 40 0.0094 14650
Methanol 67-56-1 45 0.01058 16481
Water 7732-18-5 40 0.00213 3325
Water 7732-18-5 100 86.1323 134,237,000.0
Ethylene glycol 107-21-1 30 0.0016 2494
Acetophenone 98-86-2 1 0.00001000 2
Diethylene glycol mono-n-butyl ether 112-34-5 60 0.00007000 113
Distillate, petroleum, hydrotreated, light 64742-47-8 20 0.01409 21967
Quaternary ammonium compound 68424-85-1 10 0.00235 3663
Unislick CST-LA Chemplex, Solvay Group Friction Reducer Listed Below
Water Chief Oil & Gas Carrier/Base Fluid Listed Below
BIOC11219A Nalco Champion Biocide Listed Below
SCAL16486A Nalco Champion Scale Inhibitor Listed Below
Hydrochloric Acid PVS Acidizing Listed Below

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2017 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2018 CHIEF OIL & GAS LLC 961,609.61 50 0.00 0 0.00 0
2019 CHIEF OIL & GAS LLC 3,760,887.74 333 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2017 CHIEF OIL & GAS LLC Drilling Fluid Waste 249.48 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2017 CHIEF OIL & GAS LLC Drill Cuttings 2,213.20 Tons LANDFILL 301358
2017 CHIEF OIL & GAS LLC Drilling Fluid Waste 212.72 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2018 CHIEF OIL & GAS LLC Produced Fluid 6,577.69 Bbl REUSE (AT WELL PAD)
2018 CHIEF OIL & GAS LLC Drill Cuttings 158.68 Tons LANDFILL 301358
2018 CHIEF OIL & GAS LLC Synthetic Liner Materials 14.01 Tons LANDFILL 301358
2018 CHIEF OIL & GAS LLC Produced Fluid 360.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2019 CHIEF OIL & GAS LLC Synthetic Liner Materials 9.00 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Soil Contaminated by Oil 0.34 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 37,952.09 Bbl REUSE (AT WELL PAD)
2019 CHIEF OIL & GAS LLC Soil Contaminated by Oil & Gas Related Spills 0.34 Tons LANDFILL 301358

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2595551 Primary Facility 2017-05-18 Routine/Partial Inspection No Violations Noted Logging and clearing operations underway. One well pad to be built. BMP's to be installed after major tree clearing.
2632280 Primary Facility 2017-09-05 Drilling/Alteration No Violations Noted No well spudded at this time. The rig containment and rig mats are in place. Secondary containment for equipment and tanks was being constructed.
2650174 Primary Facility 2017-10-20 Drilling/Alteration No Violations Noted The 1H well is drilled. A coil tubing rig moved onto location during the DEP's inspection. No violations noted.
2657054 Primary Facility 2017-11-01 Routine/Complete Inspection Pending Cold/raining at time of inspection. Cellar was full of water when i arrived on location. Jon haffer with chief oil and gas accompanied me during the inspection. There were vac trucks on location used to suck the water from the cellar, once the water level was lowered in the cellar there was bubbling observed outside the conductor pipe. Jon haffer was present at the time and had observed the bubbling as well. It should be noted that jon and myself discussed the bubbling and agreed that the bubbling will be monitored on a weekly basis, and that jon will get a Methane/LEL reading from the cellar as soon as he has the chance. I was unable to get. A picture at time of inspection due to rain.
2674673 Primary Facility 2017-12-22 Drilling/Alteration No Violations Noted Inspection in response to resumption in drilling notification. O rig on location at this time. The 1H well was drilled. No leaks detected from prior rig activity. No violations noted.
2717526 Primary Facility 2018-04-12 Drilling/Alteration No Violations Noted Universal conducting stimulation activities. No leaks detected.
2730028 Primary Facility 2018-05-15 Routine/Complete Inspection No Violations Noted Arrived at 11:30. Weather: windy but nice. There were one shut in well and three conductor only spuds on location. There were six empty oil based mud tanks. Rig mats and liner were still down. No violations were observed at the time of this inspection.
2739663 Primary Facility 2018-06-11 Routine/Complete Inspection No Violations Noted On 6/10/18 a drilling resumption after break of 30 days or more notification was submitted to the Department. The date and time of this action will occur on 6/12/2018 at 10 pm.

The Department arrived on 6/11/2018 for a inspection of containment and E&S controls. All conditions on the well pad were acceptable. The setup of Precision Rig 569 and equipment is underway. No violations noted.

2770346 Primary Facility 2018-09-04 Routine/Complete Inspection No Violations Noted The weather was 71° and partly sunny at time inspection. There were no Chief representatives on location at time of inspection. Well had a 0-5k psi gauge attached above the swab valve on of the the wing valves off the well head. The gauge off the swab valve appeared to be closed in and read 0 psi. The gauge on the wing valve was open and read approximately 1550 psi at time of inspection. There was also a digital gauge on the same wing valve that read 1555 psi at time of inspection. This well also had a pay line plumbed to it above the swab valve with a 0-5k psi gauge attached to it. It was closed in and read 0 psi at time of inspection. There were 2 annulus vents plumbed to surface at time of inspection. One the the vents was the 9x5 annulus vent and the other was the 13x9 annulus vent. Both vents were closed in with bull plugs at the well then plumbed together into a poly vent tank at time of inspection. Vents were open to the poly vent at time of inspection. The poly vent tank had 100% LEL and 15% methan
2850915 Primary Facility 2019-03-08 Routine/Complete Inspection No Violations Noted Inspection conducted in response to a request for a well site restoration extension and to assess overall site conditions. Four wells are staged for production. Two wells are appropriately labeled with their respective well permit numbers and two are not. Two unlabeled white plastic containers are staged near the well heads. The Department recommends labeling the containers. A battery of frac tanks is set-up within secondary containment. The tanks and containment appear to be in good condition. Four roll-off boxes, a tractor trailer, and a vac tank were also present on the pad. One steel produced water tank is present within steel containment with spray-in lining. There is minor corrosion on the produced water tank and the thief hatch on the tank appears to be open. The containment is in good condition. Four GPUs are present within secondary containment. The GPUs and containment are in good condition overall.

Site was snow-covered at the time of inspection. PCSM structures are installed according to the

For data sources see[8]

References