37-015-23278

Well Details

Well ID: 37-015-23278
Loading map...
Country: United States
State: Pennsylvania
County: Bradford
Municipality: Franklin Township
Operator Name: CHIEF OIL & GAS LLC
Well Pad ID: 153898
Farm/Lease Name: JACOBSON UNIT 1H
License Status:
Spud Date:
Permit Date: 2016-08-24
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: No
Latitude: 41.708833
Longitude: -76.527022

For data sources see[1][2][3]

Well History

Date Event
2016-08-24 New Permit Application
2016-10-26 Performed Spud Operation

For data sources see[4]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 2017-07-24 2017-08-01 6,839 11,196,200 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand Sargent/Unimin Proppant Listed Below
Hydrotreated light petroleum distillate 64742-47-8 30 0.0202 21955
Acetophenone 98-86-2 1 0.00001000 1
Water 7732-18-5 100 85.961 93,432,600.0
Water 7732-18-5 40 0.00214 2325
Ammonium acetate 631-61-8 13 0.00875 9514
Quaternary ammonium compound 68424-85-1 10 0.00251 2731
Ethylene glycol 107-21-1 30 0.0016 1744
Ethanol 64-17-5 5 0.00126 1366
Ethoxylated (C10-16) alcohols 68002-97-1 35 0.00004000 47
Diethylene glycol mono-n-butyl ether 112-34-5 60 0.00007000 80
Methanol 67-56-1 5 0.00001000 7
Water 7732-18-5 85 0.12386 134622
Alcohols, C12-14, ethoxylated 68439-50-9 5 0.00337 3659
Formaldehyde 50-00-0 1 0.00001000 1
Crystallilne silica 14808-60-7 100 13.7953 14,994,400.0
Thiourea 62-56-6 1 0.00001000 1
Water 7732-18-5 80 0.0201 21851
Hydrochloric acid 7647-01-0 15 0.02186 23757
Ethanol, 2,2',2-nitrilotris-,
1,1',1
-tris(dihydrogen phosphate), sodium salt
68171-29-9 30 0.0016 1744
Alcohols, (C10-16), ethoxylated 68002-97-1 5 0.00337 3659
Glutaraldehyde 111-30-8 5 0.00126 1366
Alcohols, C12-16, ethoxylated 68551-12-2 5 0.00337 3659
BIOC11139A Nalco Champion Biocide Listed Below
Unislick ST-50 CESI Chemical Friction Reducer Listed Below
SCAL6484A Nalco Champion Scale Inhibitor Listed Below
Unihib G GeoSafe Acid Inhibitor Listed Below
Hydrochloric Acid PVS Acidizing Listed Below
Water Chief Oil & Gas LLC Carrier/Base Fluid Listed Below

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2016 CHIEF OIL & GAS LLC 0.00 0 0.00 0 0.00 0
2017 CHIEF OIL & GAS LLC 1,663,916.85 123 0.00 0 0.00 0
2018 CHIEF OIL & GAS LLC 3,798,405.19 364 0.00 0 0.00 0
2019 CHIEF OIL & GAS LLC 1,948,036.53 326 0.00 0 0.00 0

For data sources see[6]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2016 CHIEF OIL & GAS LLC Drill Cuttings 91.18 Tons LANDFILL 301358
2017 CHIEF OIL & GAS LLC Drilling Fluid Waste 578.65 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2017 CHIEF OIL & GAS LLC Drill Cuttings 1,352.92 Tons LANDFILL 301358
2017 CHIEF OIL & GAS LLC Drilling Fluid Waste 46.76 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NC010
2017 CHIEF OIL & GAS LLC Produced Fluid 1,850.42 Bbl REUSE (AT WELL PAD)
2017 CHIEF OIL & GAS LLC Produced Fluid 360.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123
2018 CHIEF OIL & GAS LLC Produced Fluid 2,227.09 Bbl REUSE (AT WELL PAD)
2018 CHIEF OIL & GAS LLC Soil Contaminated by Oil 24.21 Tons LANDFILL 301358
2018 CHIEF OIL & GAS LLC Soil Contaminated by Oil & Gas Related Spills 24.21 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Synthetic Liner Materials 10.48 Tons LANDFILL 301358
2019 CHIEF OIL & GAS LLC Produced Fluid 216.25 Bbl REUSE (AT WELL PAD)

For data sources see[7]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2526880 Primary Facility 2016-10-11 Preoperation Inspection No Violations Noted
2549410 Primary Facility 2017-01-05 Routine/Complete Inspection No Violations Noted The rig is drilling the 2H well at this time. The 1H will be drilled once the 2H is complete. No violations noted.
2565807 Primary Facility 2017-02-27 Routine/Complete Inspection No Violations Noted The 1H and 2H wells have been drilled. No drilling equipment on location. A coil tubing rig and associated fracking equipment arrived on location during the DEP inspection. No violations noted. Site stable.
2619371 Primary Facility 2017-07-26 Routine/Complete Inspection No Violations Noted The 1H well is on the 9th stage of the frack. Secondary and primary containment sufficient and staged correctly. No leaks from baker tanks or hoses. Universal is conducting operations. Two production tanks within containment.

Site Forman: Brent Fowelr.

2623446 Primary Facility 2017-08-08 Routine/Complete Inspection No Violations Noted I met Floyd Roberts and Eric McClure of Chief when I arrived. A coil tubing rig was on site drilling out plugs on the 2H well. Puddles were widespread on the site. Small puddles of 6.1 and 8.3 mS/cm were present on containment near the Baker tank battery; puddles on the pad nearby showed low conductance (.45-.76 mS/cm). On the far side of the pad from the entrance, I found 3 small volume puddles (all less than 5 gallons) near the edge of the liner that showed conductance of 2.2-2.4 mS/cm; other puddles nearby showed low conductance (.48-.87 mS/cm). I informed Eric and Floyd, who had been joined by Gib Blevins of Chief; Gib immediately got a vac truck that was on location to vac these areas.
2655238 Primary Facility 2017-11-01 Routine/Complete Inspection No Violations Noted Arrived at 12:00. Weather: cold rain. 2 producing wells on site. Annuli for both wells are plumbed into one 550-gallon poly tank. There is a small amount of oil-base and water in the tank. Monitoring with an Altair 5X gas meter (calibrated on 11/1/17) gives 10 % methane/ volume at the tank opening. NO combustible gas was detected at the 13-3/8" x 9-5/8" annuli of either well. No violations were noted during this inspection.
2710518 Primary Facility 2018-03-26 Incident- Response to Accident or Event Viol(s) Noted & Immediately Corrected I arrived onsite to follow up on a reported incident. DEP was notified by PEMA at 07:00 hrs. on 3/25 that one of the GPUs on the site caught fire, damaging both GPUs. When I arrived, Cuthbertson Construction Inc. was on the site; the damaged GPUs had both been removed and replaced, and Cuthbertson was hooking up the new units. I met Darren Mundrick of Chief; as he is with Chief's construction group, he was not privy to all of the details of the incident. At that time, Rebecca Renner, OGI for the DEP Oil & Gas program arrived. In order to get us details regarding the incident, Darren called Peg Farrell, and Becky and I both spoke to her and Tyler Berkey about the incident. Ray Miller of Chief arrived while Becky was speaking to Peg; he informed me that the fire and explosion had been reported to 911 at 06:00 hrs. on Sunday morning, and he arrived at 06:30 and secured the site. I then spoke to Peg and Tyler. They told me that once the fire was out and the equipment cooled off, the glycol was vacced out
2710596 Primary Facility 2018-03-26 Follow-up Inspection No Violations Noted Arrived at 11:00. Weather: sunny. The purpose of this inspection was to follow-up on a GPU fire which occurred on 3/25. Crew and staff were onsite. Among the personnel present at the time of my inspection were: Sean Van Fleet (DEP), Ray Miller (Chief-Safety), and Greg Roher (Chief-Completions). Peg Farrell (Chief) was also in phone contact during the inspection. There were 2 gas wells capable of production on location. These were shut-in at the time of my inspection. Two new GPU¿s (Energy Weldfab) were being set up on new containment when I arrived. The large shut-off valve at the front of the 2H GPU washed out (see photos), providing the gas source for the fire. The 2H well did not automatically shut-in. Pressure in the above ground pipe behind the GPU ruptured the pipe. The fire destroyed the communications cables so that it was not possible to shut-in the 2H from Chief¿s control center. The 1H well apparently did shut-in automatically. Ray Miller arrived on site approximately 30 minutes after the problem
2791414 Primary Facility 2018-10-18 Administrative/File Review Violation(s) Noted Administrative Inspection created to cite a violation against a well in which Chief entered the wellbore less than eight hours after cementing the casing. This inspection/violation is part of a CACP found under Enforcement Record ID #368514.
2845007 Primary Facility 2019-02-21 Routine/Complete Inspection No Violations Noted On February 21, 2019, Department representative Brad Kline conducted a routine site inspection at Chief Oil & Gas LLC. Jacobson Pad. Weekly inspection log was onsite for review. No E&S issues were observed during the time of inspection. The site is stable and well vegetated meeting the 70% uniform, perennial, vegetative cover.

There are a total of 2 producing wells located on this well pad. All wells are tagged with API/well permit numbers. Cellars are filled in with gravel. There are 2 GPU’s and 2 steel vertical production fluids tanks onsite. Both GPUs and production fluid tanks were stationed in secondary containment.

No violations noted.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2710518 811978 2018-03-25 2018-03-25 CSL 402(b) Environmental Health & Safety For glycol release
2710518 811979 2018-03-25 2018-03-25 78a56(a) Environmental Health & Safety For glycol release
2710518 811980 2018-03-25 2018-03-25 SWMA 301 Environmental Health & Safety For glycol release
2791414 831069 2018-10-18 2018-10-18 78a85(c)4 Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
831069 368514 CACP - Consent Assessment of Civil Penalty COMP - Completed 2018-10-18 2018-10-18 $220,000.00 $220,000.00

For data sources see[8]

References