37-005-31227

Well Details

Well ID: 37-005-31227
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: West Franklin Township
Operator Name: EQT PROD CO
Well Pad ID: 152319
Farm/Lease Name: CENTURY HILL 593542
License Status: Plugged and Abandoned
Spud Date:
Permit Date: 2015-03-05
Well Type: GAS
Unconventional Well: Y
Configuration: Horizontal Well
Conservation: Yes
Latitude: 40.814742
Longitude: -79.614244

For data sources see[1][2][3]

Well History

Date Event
2015-03-05 New Permit Application
2015-03-23 Performed Spud Operation
2016-05-18 New Permit Application
2018-05-04 Begin Plugging
2018-05-07 Finished Plugging
2018-08-23 Fully Plugged

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2015 EQT PROD CO 0.00 0 0.00 0 0.00 0
2016 EQT PROD CO 0.00 0 0.00 0 0.00 0
2017 EQT PROD CO 0.00 0 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2015 EQT PROD CO Drilling Fluid Waste 350.00 Bbl REUSE OTHER THAN ROAD SPREADING
2015 EQT PROD CO Drill Cuttings 96.00 Tons LANDFILL 100585
2018 EQT PROD CO Other Oil & Gas Wastes 65.00 Bbl RESIDUAL WASTE PROCESSING FACILITY WMGR123NW009
2018 EQT PROD CO Other Oil & Gas Wastes 70.00 Bbl RESIDUAL WASTE PROCESSING FACILITY ORDER 2016-29
2018 EQT PROD CO Other Oil & Gas Wastes 7.74 Tons LANDFILL 06-08438

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2354312 Primary Facility 2015-03-24 Preoperation Inspection Viol(s) Noted & Immediately Corrected Drilling had commenced, but was not ongoing at the time of the inspection. Site and access road erosion controls had been implemented as outlined in the E&S plan located onsite. All cut and fill slopes had been temporarily stabilized and there was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that drilling had commenced prior to completion of a pre-operational inspection.
2354602 Primary Facility 2015-03-24 Drilling/Alteration No Violations Noted Waiting on rig to commence tophole drilling.
2357509 Primary Facility 2015-04-02 Routine/Complete Inspection No Violations Noted Drilling had commenced but was not ongoing at the time of the inspection. All cut and fill slopes had been temporarily stabilized with seed and mulch. All site and access road controls had been properly installed and there was no observed accelerated erosion or sedimentation in relation to the site or access road.
2357598 Primary Facility 2015-03-30 Drilling/Alteration No Violations Noted Waiting on rig to continue tophole drilling.
2377411 Primary Facility 2015-06-09 Routine/Complete Inspection No Violations Noted Drilling had commenced but was not ongoing at the time of the inspection. All cut and fill slopes had been temporarily stabilized, although these areas were minimal due to the cultivated agricultural fields around the well pad.. All site and access road controls had been properly installed and there was no observed accelerated erosion or sedimentation in relation to the site or access road.
2377835 Primary Facility 2015-06-08 Drilling/Alteration No Violations Noted Waiting on rig to continue tophole drilling.
2406058 Primary Facility 2015-09-09 Routine/Complete Inspection No Violations Noted Drilling had commenced but was not ongoing at the time of the inspection. All cut and fill slopes had been temporarily stabilized, although these areas were minimal due to the cultivated agricultural fields around the well pad. All site and access road erosion controls had been properly installed and there was no observed accelerated erosion or sedimentation in relation to the site or access road.
2484832 Primary Facility 2016-05-17 Routine/Complete Inspection No Violations Noted Drilling was not ongoing at the time of the inspection. All cut and fill slopes had been temporarily stabilized, although these areas were minimal due to the cultivated agricultural fields around the well pad. All site and access road erosion controls had been properly installed and there was no observed accelerated erosion or sedimentation in relation to the site or access road.
2566734 Primary Facility 2017-03-02 Routine/Complete Inspection No Violations Noted There was no activity ongoing at the site at the time of the inspection. There was no observed accelerated erosion or sedimentation in relation to the site or access road. The site had been effectively stabilized and agricultural fields were noted adjacent to the well site.
2726907 Primary Facility 2018-05-07 Plugging(Includes Plugged/Mined Through) No Violations Noted This well was only drilled to 682' and was not finished. The plugging rig cemented the well solid from the TD of 682' to surface. A monument plate with the required well information was permanently affixed to the top of the cemented casing and buried 5' below the surface. All equipment on site looked ok.
2748411 Primary Facility 2018-07-03 Routine/Complete Inspection No Violations Noted At time of inspection, both wells on this pad have been plugged. Plugging was completed for Well 593542 on 5/7/2018.

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
2354312 718325 03/24/2015 2015-03-24 OGA3258(A.1) - Drilling commenced without preoperation inspection. Environmental Health & Safety

Penalties Applied

Violation ID Penalty ID Penalty Code Penalty Status Penalty Date Enforcement Date Penalty Amount Amount Collected
718325 321184 NOV - Notice of Violation Comply/Closed 2015-03-24

For data sources see[7]

References