37-005-31181

Well Details

Well ID: 37-005-31181
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: East Franklin Township
Operator Name: SNYDER BROS INC
Well Pad ID: 150514
Farm/Lease Name: LEWIS M WOLFE ETUX 1M-30
License Status:
Spud Date:
Permit Date: 2013-11-07
Well Type: GAS
Unconventional Well: Y
Configuration: Vertical Well
Conservation: Yes
Latitude: 40.888469
Longitude: -79.502486

For data sources see[1][2][3]

Well History

Date Event
2013-11-07 New Permit Application
2014-09-04 Performed Spud Operation

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2014 SNYDER BROS INC 1,343.00 66 0.00 0 0.00 0
2015 SNYDER BROS INC 5,821.00 338 0.00 0 0.00 0
2016 SNYDER BROS INC 3,971.00 343 0.00 0 0.00 0
2017 SNYDER BROS INC 4,160.00 348 0.00 0 0.00 0
2018 SNYDER BROS INC 3,007.00 317 0.00 0 0.00 0
2019 SNYDER BROS INC 2,591.00 244 0.00 0 0.00 0

For data sources see[5]

Waste Data

Period Operator Waste Type Quantity Disposal Method Waste Facility ID
2014 SNYDER BROS INC Drilling Fluid Waste 110.00 Bbl INJECTION DISPOSAL WELL 34-155-23732
2014 SNYDER BROS INC Drill Cuttings 112.00 Tons ON SITE ENCAPSULATION
2014 SNYDER BROS INC Drilling Fluid Waste 120.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123NW009
2014 SNYDER BROS INC Drilling Fluid Waste 620.00 Bbl RESIDUAL WASTE PROC FAC (GENERAL PERMIT) WMGR123SW005
2014 SNYDER BROS INC Drilling Fluid Waste 681.00 Bbl REUSE OTHER THAN ROAD SPREADING

For data sources see[6]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2216862 Primary Facility 2013-10-24 Routine/Complete Inspection No Violations Noted Inspection performed as part of the OG-57 waiver review process. The E&S plan as compiled should effectively minimize accelerated erosion and sedimentation provided it is implemented and maintained properly. It was noted in the E&S plan that the area for the drill pit will be evaluated to insure the bottom of the drill pit is at least 20 inches above the seasonal high groundwater table. When this evaluation is performed the Department requests that the operator forward a copy of this report for inclusion with the approved E&S plan. In addition should the evaluation show that the encapsulation of the drill cuttings and/or the utilization of a below grade drill pit is not feasbile the operator should forward this documentation and a revised E&S plan as a result of this evaluation.
2233347 Primary Facility 2014-01-02 Routine/Complete Inspection No Violations Noted Site construction had been completed, drilling had not commenced at the time of the inspection. SIte and access road E&S controls had been implemented as outlined in the E&S plan. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2250418 Primary Facility 2014-03-04 Routine/Complete Inspection No Violations Noted Drilling had not commenced at the time of the inspection. E&S controls had been implemented as outlined in the E&S plan. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2266929 Primary Facility 2014-04-29 Routine/Complete Inspection No Violations Noted Drilling had not commenced at the time of the inspection. E&S controls had been implemented as outlined in the E&S plan. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2293469 Primary Facility 2014-08-07 Routine/Complete Inspection No Violations Noted Drilling had not commenced at the time of the inspection. E&S controls had been implemented as outlined in the E&S plan. There was no observed accelerated erosion or sedimentation in relation to the site or access road. It was noted that the cut slope required additional seeding and mulching to achieve temporary stabilization. If the cut slope is left as is a more significant erosion issue could develop.
2304233 Primary Facility 2014-09-16 Routine/Complete Inspection No Violations Noted Dril rig onsite, drilling was ongoing at the time of the inspection. Lined drill pit located onsite and it contained drill cuttings and fluids. Drill pit had more than two feet of lined freeboard. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2306674 Primary Facility 2014-09-12 Drilling/Alteration No Violations Noted First Class Energy rig#10 RD20 shut down at time of inspection. No reps on location. Pit lined and freeboard maintained.
2320425 Primary Facility 2014-11-05 Routine/Complete Inspection No Violations Noted Drilling appeared to have been completed, well appeared to be equipped for production. Drill pit located onsite and it contained cuttings and fluids. Pit had more than two feet of lined freeboard. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2357493 Primary Facility 2015-03-31 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production, brine tanks located onsite and they appeared to be in sound condition. Site had been regraded, seeded & mulched. There was no observed accelerated erosion or sedimentation in relation to the site or access road.
2394450 Primary Facility 2015-07-31 Site Restoration No Violations Noted Well appeared to be equipped for production, however it did not appear to have been stimulated. The site had been effectively stabilized and there was no observed accelerated erosion or sedimentation in relation to the site or access road.
2520854 Primary Facility 2016-09-21 Routine/Complete Inspection No Violations Noted Well appeared to be equipped for production, however it did not appear to have been stimulated. The site had been effectively stabilized and there was no observed accelerated erosion or sedimentation in relation to the site or access road.

For data sources see[7]

References