37-005-30771

Well Details

Well ID: 37-005-30771
Loading map...
Country: United States
State: Pennsylvania
County: Armstrong
Municipality: South Bend Township
Operator Name: US ENERGY EXPLORATION CORP
Well Pad ID:
Farm/Lease Name: D SHEARER 5
License Status:
Spud Date:
Permit Date: 2011-01-27
Well Type: GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.578078
Longitude: -79.405575

For data sources see[1][2][3]

Well History

Date Event
2011-01-27 New Permit Application
2011-11-09 Performed Spud Operation
2011-11-22 Drilling Completion
2011-12-15 Perforation
2012-03-23 NEWLY DRILLED

For data sources see[4]


Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2011 US ENERGY EXPLORATION CORP 0.00 0 0.00 0 0.00 0
2012 US ENERGY EXPLORATION CORP 10,485.00 270 0.00 0 0.00 0
2013 US ENERGY EXPLORATION CORP 3,650.00 360 0.00 0 0.00 0
2014 US ENERGY EXPLORATION CORP 3,650.00 365 0.00 0 0.00 0
2015 US ENERGY EXPLORATION CORP 3,650.00 365 0.00 0 0.00 0
2016 US ENERGY EXPLORATION CORP 1,259.00 305 0.00 0 0.00 0
2017 US ENERGY EXPLORATION CORP 695.00 185 0.00 0 0.00 0
2018 US ENERGY EXPLORATION CORP 609.00 210 0.00 0 0.00 0
2019 US ENERGY EXPLORATION CORP 1,036.00 365 0.00 0 0.00 0

For data sources see[5]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2017986 Primary Facility 2011-11-08 Routine/Complete Inspection No Violations Noted Site construction had been completed, drilling had not commenced at the time of the inspection. All E&S controls had been implemented as outlined in the E&S plan located onsite. It was noted that the silt fencing installed would result in the concentration of runoff flow to the lowest spot along the fence near township road 629. This area should be monitored closely to insure that the silt fencing functions properly during well development activities.
2125612 Primary Facility 2012-12-26 Site Restoration No Violations Noted Drilling was completed on 11/22/11. Well appeared to be equipped for production. Brine tank located onsite and it appeared to be in sound condition. Well-site had been properly restored and there were no erosion issues observed in relation to the site or access road.
2748898 Primary Facility 2018-07-05 Routine/Complete Inspection No Violations Noted This well is tagged and in production. The annulus is shut. The well head casing, piping, equipment and 50 bbl fiberglass fluid collection tank look ok.

For data sources see[6]

References