X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

34-173-20573

Well Details

Well ID: 34-173-20573
Loading map...
Country: United States
State: Ohio
County: Wood
Municipality: Montgomery Township
Operator Name: SEIBERT JAMES G
Well Pad ID:
Farm/Lease Name: TODY
License Status: Producing
License Date: 2018-04-03
Spud Date: 2013-07-18
Spud Drilling Contractor:
Final Drill Date: 2013-09-19
Well Total Depth: 1258.00 ft
Configuration: Vertical
Latitude: 41.310000
Longitude: -83.440000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2013-07-17 Proposed Formations:TRENTON, Issued Date:7/17/2013, Expired Date:7/17/2015 12:00:00 PM, Drilling unit acres:10, Proposed Well Type:OG, Proposed Well Class:POOL
Completion Report Received 2013-09-19 DRILLER: BLACK SWAMP OIL UPDATE COORDAINTES PER DOGRNM SURVEYOR
Reached Total Depth 2013-09-19 DRILLER: BLACK SWAMP OIL UPDATE COORDAINTES PER DOGRNM SURVEYOR
APP 2018-04-03 Proposed Formations:TRENTON, Issued Date:4/3/2018, Expired Date:4/2/2020 12:00:00 PM, Drilling unit acres:5, Proposed Well Type:OG, Proposed Well Class:
Record Last Modified 2018-07-06 DRILLER: BLACK SWAMP OIL UPDATE COORDAINTES PER DOGRNM SURVEYOR
Construction Permit Expires 2020-04-02 DRILLER: BLACK SWAMP OIL UPDATE COORDAINTES PER DOGRNM SURVEYOR

For data sources see[2]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2013-09-19 NITR 0 80 Qts 0 OTHER Mike Patrick of Torpedo Services Inc. of Beattyville, Ky. Shot the well. Jim Sibert and Mike Coyer were on site.

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2013 SEIBERT JAMES G 0.00 17.00 30
2014 SEIBERT JAMES G 0.00 65.00 360
2016 SEIBERT JAMES G 0.00 0.00 365

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2013 SEIBERT JAMES G Brine 0 30
2014 SEIBERT JAMES G Brine 0 360
2016 SEIBERT JAMES G Brine 0 365

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-482047278 2018-7-17 0:00: PW No Violations
-64391472 2013-7-19 0:00: DD No Violations
-851881982 2013-9-19 0:00: DD No Violations
0064391472 2013-07-19 Drill / Deepen / Reopen No Violations Move in and hook up mud pump. Unable to gain circulation pressure up to 800 psi. 15 clay layer may have swelled and locked in pipe. Move in Holman drilling, go in hole with air hammer and drive conductor to total depth. Decision made to grout conductor hole from the top. Mix and gravity feed 12 sacks Type 1 portland cement to surface which held.
0482047278 2018-07-17 Production Wells No Violations FOLLOWUP TO CHIEFS ORDER # 2018-116. Well currently is not capable of production. The well consist of a seven inch surface casing reduced to two inch. There is currently 2 two inch manual valve on the well. There is currently a plugging permit for this well and at the current time there is no activity to plug this well. No identification is posted at this well.
0602681211 2017-06-19 Production Wells No Violations Rods have been pulled from well and lying next to well at the present time. Pump jack with gasoline engine is pulled from well and disconnected from wellhead. Identification is posted on tank and one 100 BBL tank is presently on site connected to well with one inch plastic line.
0851881982 2013-09-19 Drill / Deepen / Reopen No Violations Inspect well and location. Operator stimulate well with equivalent of 80 quarts of nitro methane.
0888457722 2014-05-08 Preliminary Restoration No Violations At the time of the inspection there was a dirt lease road leading back to the well. An approximately 200 barrel production tank was set up on 6 by 6 beams with no containment dike. Identification for the well has been painted on the tank. There was a 1.5 plastic flow line on top of the ground from the well to the top of the tank. The well has a pumping unit with a gasoline powered motor. A service rig was set up on the well and a 4 bailer was laying off to the east of the well. A 4 by 6 by 4 half tank is just west of the well half full of oil and water. Any pits have been closed and the area has been graded. Vegetation has been reestablished enough to maintain erosion control but sandy soil conditions are inhibiting growth in some areas. The contractor and the landowner will continue attempts to establish vegetation throughout the summer. Preliminary Restoration Passed.
0932389643 2013-07-24 Drill / Deepen / Reopen No Violations Black Swamp Oilfield Services has begun drilling the surface hole with 8.75 bit on air, current depth 97 (Big Lime). Air pit is lined, flowline staked. Status: ok.
1374259819 2013-07-18 Casing String Witnessed No Violations Holman Drilling (water well driller) spudded conductor hole on the Tody #1 (#573) with a 9.75 bit on fresh water mud. Drilled 14 yellow sand, 15 brown clay, top of the Lime at 38. Total depth 47. Pull out of hole and ream with 12.25 bit to total depth, circulate hole clean. Ran three joints (47) of new 26# 9.625 conductor centralized on bottom. Ran pvc tremme tube on the backside to cement the conductor. Unable to move tremme tube with a chain and back hoe. Lift up on casing 2, unable to remove tremme tube and casing. After several attempts decision was made to shut down for the day due to heat and move mud pump for cementing.
1376047824 2013-08-05 Drill / Deepen / Reopen No Violations Inspect drill site. Set and cement surface casing. Hole 8.75 inches at 414 feet deep. Set new 7 inch 20 lb/ft pipe to 401 feet. Mike Coyer drilled hole. Erin Huwer pumped cement delivered by Palmer brothers. Pump 75 sacks of Type 1 cement. Good returns. Three centralizers 380 feet, 200 feet, 24 feet.
1376061933 2013-08-09 Drill / Deepen / Reopen No Violations Blackswamp drilling ahead on air at 630.Status: ok.
1383054604 2013-10-28 Preliminary Restoration No Violations Inspected the Tody #1 (#573) as part of a standard preliminary restoration inspection. Drilling equipment removed, pits are closed and the well is pumping by a Churchill gas powered pumpjack. The well is currently pumping into temporary storage. A permanent storage tank and well identification labels are ordered according to the operator. Erosion control has not been established. Status: preliminary restoration is complete except for erosion control being established. Operator is planning on seeding. Will continue to monitor.
1401734744 2014-06-02 Preliminary Restoration No Violations The operator has added one steel 100 barrel tank and the well identification and emergency contact information is marked on the storage. Erosion control has been established around the well site. Status: preliminary restoration complete.
1541004775 2018-10-31 Production Wells No Violations Checked on status of well. There is an active plugging permit on this well. Operator has removed pumpjack from the well and will be plugging this well in the near future.
602681211 2017-6-19 0:00: PW No Violations
888457722 2014-5-8 0:00:0 PL No Violations
932389643 2013-7-24 0:00: DD No Violations

For data sources see[8]

References