34-111-24284

Well Details

Well ID: 34-111-24284
Loading map...
Country: United States
State: Ohio
County: Monroe
Municipality: Jackson Township
Operator Name: BECK ENERGY CORPORATION
Well Pad ID:
Farm/Lease Name: LEASURE
License Status: Producing
License Date: 2010-10-18
Spud Date: 2010-10-21
Spud Drilling Contractor: MONROE DRILLING OPERATION, LLC
Final Drill Date: 2010-10-26
Well Total Depth: 3090.00 ft
Configuration: Vertical
Latitude: 39.600000
Longitude: -80.990000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2010-10-18 Proposed Formations:BEREA/30 FOOT/GORDON, Issued Date:10/18/2010, Expired Date:10/17/2012 12:00:00 PM, Drilling unit acres:20, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2010-10-26
Construction Permit Expires 2012-10-17
Completion Report Received 2013-10-21
Record Last Modified 2014-01-07

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2013-10-24 2629 2999 75
2629 2999 75
2629 2999 75

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2011-04-20 H2O 15 217900 Gal 21000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2011 BECK ENERGY CORPORATION 1646.00 50.00 365
2012 BECK ENERGY CORPORATION 1692.00 81.00 366
2013 BECK ENERGY CORPORATION 4643.00 162.00 365
2014 BECK ENERGY CORPORATION 2390.00 19.00 365
2015 BECK ENERGY CORPORATION 1596.00 25.00 365
2016 BECK ENERGY CORPORATION 1530.00 15.00 365
2017 BECK ENERGY CORPORATION 1313.00 44.00 365
2018 BECK ENERGY CORPORATION 995.00 5.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2011 BECK ENERGY CORPORATION Brine 30 365
2012 BECK ENERGY CORPORATION Brine 0 366
2013 BECK ENERGY CORPORATION Brine 931 365
2014 BECK ENERGY CORPORATION Brine 155 365
2015 BECK ENERGY CORPORATION Brine 159 365
2016 BECK ENERGY CORPORATION Brine 80 365
2017 BECK ENERGY CORPORATION Brine 50 365
2018 BECK ENERGY CORPORATION Brine 83 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-192527297 2010-10-22 0:00 DD No Violations 5.00
-682046669 2011-4-20 0:00: CT No Violations 12.00
0192527297 2010-10-22 Drill / Deepen / Reopen No Violations On day of inspection Monroe drilling is setting surface pipe. Universal is cementing casing. The pit is substantial to contain all drilling fluids. Set 22of 11open hole and pulled 22of 9 5/8casing. Set 1215of 8 3/4open hole. Set 1184 of 17lb/ft 7casing.Good returns. Red was from 900-1170.
0682046669 2011-04-20 Completion Testing No Violations Beck called on short notice telling me they are fracing this afternoon and tomorrow. This day doing Gordon Sand with perfs from 2998-2629 - not all of this but sections. Acid was dumped in the Fall - 200 gall of 20% HCl and swabbed off. Today, fracing with 190 sks sand, 3280 bbl water (taken from Ohio River). Well treated at 2700 psi and 48 bbl/min. Shut in at 1500#. Will flow back all night, then use water again for Berea frac on 4/21/11. 4/21-Weir/Berea was fracted this day. 2349-2494. Well treated with 500 gal 20% HCl, 1900 bbl water, no sand. Well broke down at 2325#, treated at 2500#, shut in at 1550#. Used Quantabs to check 2 fract tanks containing 1-1.5 of fresh water from the frac. - tested clean and operator was allowed to slowly drain water on the ground so as to remove tanks this day - big rain coming. 3rd tank tested bad and they were told to haul water from it before moving.
0861805345 2010-11-06 Completion Testing No Violations On this day of inspection at 10:30am arrived on location. Jet wireline was on location. They just got done running a correlation log. They were getting ready to make three runs in to perforate casing in bottom. We ran into problems with not firing all charges. We had to make additional runs. Universal was at location at 12:00noon.I told ray he needed a frac valve .We are not pumping a breakdown through a 600psi brass valve. Break down pressure is at 2800psi.Armstrong brought a frac valve.at 3:00pm.At 4:00pm JT Wireline is leaving location and universal is getting ready to hook up to well head.2800 psibreakdown pressure.Displaced with 32bbl of water.
0905945115 2010-10-26 Drill / Deepen / Reopen No Violations On day of inspection stopped at rig to check status. Rig still drilling almost to 2700.Talked with Kerry Brown and he stated that he would be cementing 4 1/2casing at 7:00pm.Beck will open hole log.
1652133602 2016-02-16 Preliminary Restoration No Violations Preliminary Restoration status check inspection found the following equipment at the well head 4.5 production casing -1.5 production tubing and pumping rods with the production valves in the open position and the well set up to be produced by the means of pumping unit. 2-100 barrel production tanks are located inside an established dike area along with a mechanical separator and gas sales meter with a current sales chart inside the meter. Proper well identification is posted.
861805345 2010-11-6 0:00: CT No Violations 6.50
905945115 2010-10-26 0:00 DD No Violations 1.00
937463312 2020-2-26 0:00: PW No Violations 0.50

For data sources see[9]

References