If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-067-21559 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.3,"lon":-81.05,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Harrison | |
Municipality: Archer Township | |
Operator Name: EAP OHIO LLC | |
Well Pad ID: US-OH-001585 | |
Farm/Lease Name: DAVIS TRUST 19-11-5 | |
License Status: Producing | |
License Date: 2018-10-30 | |
Spud Date: 2018-10-30 | |
Spud Drilling Contractor: PATTERSON DRILLING | |
Final Drill Date: 2018-12-05 | |
Well Total Depth: 23356.00 ft | |
Configuration: Horizontal | |
Latitude: 40.300000 | |
Longitude: -81.050000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2018-10-30 | Proposed Formations:POINT PLEASANT, Issued Date:10/30/2018, Expired Date:10/29/2020 12:00:00 PM, Drilling unit acres:343.72, Proposed Well Type:OG, Proposed Well Class:POOL |
Reached Total Depth | 2018-12-05 | |
Correction to Well | 2019-04-05 | AS-DRILLED CHANGE TAKE TARGET |
Record Last Modified | 2019-04-05 | |
Construction Permit Expires | 2020-10-29 |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
23102 | 23194 | 0 | |
9004 | 9125 | 0 | |
9004 | 9125 | 0 |
For data sources see[3]
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1079183579 | 2019-6-19 0:00: | CT | No Violations | 1.00 |
-1118512279 | 2019-6-25 0:00: | CT | No Violations | 1.00 |
-1271805928 | 2019-6-5 0:00:0 | CT | No Violations | 1.00 |
-1555408607 | 2019-5-14 0:00: | CT | No Violations | 1.00 |
-364744699 | 2019-5-6 0:00:0 | CT | No Violations | 1.00 |
-517105908 | 2018-11-28 0:00 | DD | No Violations | 1.00 |
-537564367 | 2019-5-23 0:00: | CT | No Violations | 1.00 |
-81851066 | 2019-9-17 0:00: | PL | No Violations | 1.00 |
-853803899 | 2018-11-28 0:00 | DD | No Violations | 0.90 |
-871095259 | 2019-4-8 0:00:0 | CT | No Violations | 2.00 |
0269062650 | 2019-04-24 | Completion Testing | No Violations | On the day of my inspection I witnessed Profrac crew on location tied into the 201H and the 5H well. This well has not been opened up to frac yet. The 13.375x9.625 annular pressure is 0 psi and the 9.625x5.5 annular pressure is 140 psi. |
0348163134 | 2018-10-31 | Drill / Deepen / Reopen | No Violations | On the day of my inspection I witnessed Express Energy has drilled this hole to 50 feet with a 36 inch diameter auger bit and cemented a 30 inch diameter casing in with 9 yards of grout. The hole kept falling in. Identified myself to Superintenant David Newman. |
0364744699 | 2019-05-06 | Completion Testing | No Violations | On the day of my inspection I witnessed a Profrac frac crew onsite. Profrac is currently tied into the 1H, 3H, 5H and the 201H wells. Profrac is pumping stage 15/95. Stage 15 plug set at 21140 feet, with bottom perforation at 21123 feet and top perforation at 21004 feet. Profrac pumped 71.4 barrels of 7.5% HCl, 10166.6 barrels of clean fluid, 198,360 lbs of 100 mesh sand, 132,260 lbs of 40/70 mesh sand, and 420 barrels of produced water. Total sand pumped was 330620 lbs. Maximum treating pressure was 10714 psi and average treating pressure was 10370 psi. Maximum rate was 96.3 barrels per minute (BPM) and average rate was 93.4 bpm. Break down pressure was 8198 psi. Initial shut in pressure (ISIP) was 5827 psi. Frac gradient on 1.15 psi/ft. The 13.375x9.625 annular pressure is 13 psi and the 9.625x5.5 annular pressure is 0 psi. |
0517105908 | 2018-11-28 | Drill / Deepen / Reopen | No Violations | On the day of my inspection I witnessed Patterson 580 drilling an 8.75 inch diameter hole at 6028 feet. Rig is currently drilling on air and hole is not making water or gas. 9.625 inch diameter casing was set at 2001 feet and 13.375 inch diameter casing was set at 685 feet. Estimated total depth is 23391 feet. I was accompanied on this inspection by Inspector Jeff Adams. Identified ourselves to company man Joe Foerste. |
0537564367 | 2019-05-23 | Completion Testing | No Violations | On the day of my inspection I was accompanied by Inspector Jeff Adams. We witnessed a Profrac frac crew onsite tied into the 1H, 3H, and 201H wells. Stage 73/95 is awaiting frac. Stage 73 plug set at 12434, with bottom perforation at 12419 and top perforation at 12304. This is next stage on pad to be fracked. Twelve 350 barrel steel produced water tanks are on location, within their own containment. Tanks had <50 barrels each remaining in them. |
0745296769 | 2019-04-15 | Completion Testing | No Violations | On the day of my inspection I witnessed Procfrac on location tied into the 5H and the 201H. This well has not been opened up yet. 13.375x9.625 annular pressure is zero psi and the 9.625x5.5 annular pressure is 120 psi. |
0853803899 | 2018-11-28 | Drill / Deepen / Reopen | No Violations | |
0871095259 | 2019-04-08 | Completion Testing | No Violations | On the day of my inspection I met with Blake James, Eric Visky, and Dan Imlay, all consultants for Encino. Profrac is onsite tied into the 5H well and the 201H well. This well has not been opened up for frac yet.13.375x9.625 annular pressure is 0 and 9.625 x 5.5 annular pressure is 103. |
1038791516 | 2018-12-04 | Drill / Deepen / Reopen | No Violations | On the day of my inspection I was accompanied by Inspector Jeff Adams. We witnessed the Patterson 571 was drilling an 8.5 inch diameter hole at a depth of 19540. The rig drilled an 8.75 inch diameter hole from 2001 to 7720. Kick off point was at 7822 and curve landed at 9092. They are drilling on 11 ppg oil based mud with no water or gas. Estimated total depth is 23492. |
1271805928 | 2019-06-05 | Completion Testing | No Violations | On the day of my inspection I was accompanied by Supervisor Eric Conrad. During the inspection we witnessed Stone Rig 15 onsite. This well has not been opened up for drill out. The 13.375x9.625 annular pressure was zero and the 9.625x5.5 annular pressure is zero. |
1378544682 | 2018-11-01 | Casing String Witnessed | No Violations | PAD ADDRESS:83690 Bargar Road, Cadiz. On the day of my inspection I witnessed Express had augured a 36 inch diameter hole to 50 feet and sleeved in with 30 inch diameter casing. That casing was previously grouted with 9 yards. Express then drilled a 26 inch diameter hole to 120 feet. 120 feet of 20 inch diameter, 94# conductor casing was run. Express was onsite with 216 sacks of class A cement. Additives include 2% CaCl and .5 lb./sack cello-flake. Cement weighed with mudscale at 15.6 ppg and yield of 1.18. Cement was displaced with 39 barrels of fresh water. Cement returned to surface. |
1544019405 | 2018-12-04 | Drill / Deepen / Reopen | No Violations | |
1555408607 | 2019-05-14 | Completion Testing | No Violations | On the day of my inspection I was accompanied by Inspector Jeff Adams. A Profrac frac crew is on location tied into the 1H, 3H, and 201H wells. Stage 41/95 is perforated on this well. Plug set at 17228, with bottom perforation at 17218 and top perforation at 17140. Stage desgin calls for 330000 lbs of sand and approximately 10000 barrels of fluid. The 13.375x9.625 annular pressure is 30 psi and the 9.625x5.5 annular pressure is zero. |
269062650 | 2019-4-24 0:00: | CT | No Violations | 1.00 |
348163134 | 2018-10-31 0:00 | DD | No Violations | 1.00 |
745296769 | 2019-4-15 0:00: | CT | No Violations | 1.00 |
For data sources see[4]