Well Details

Well ID: 34-059-24420
Loading map...
Country: United States
State: Ohio
County: Noble
Municipality: Wayne Township
Operator Name: ASCENT RESOURCES UTICA LLC
Well Pad ID: US-OH-000835
Farm/Lease Name: MOHOROVICH E RCH GR
License Status: Producing
License Date: 2018-05-25
Spud Date: 2014-09-03
Spud Drilling Contractor: HIGHLAND DRLG
Final Drill Date: 2018-07-17
Well Total Depth: 19288.00 ft
Configuration: Horizontal
Latitude: 39.950000
Longitude: -81.370000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-08-25 Proposed Formations:POINT PLEASANT, Issued Date:8/25/2014, Expired Date:8/24/2016 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
APP 2014-12-24 Proposed Formations:POINT PLEASANT, Issued Date:12/24/2014, Expired Date:12/23/2016 12:00:00 PM, Drilling unit acres:641.3, Proposed Well Type:OG, Proposed Well Class:POOL
APP 2016-10-24 Proposed Formations:POINT PLEASANT, Issued Date:10/24/2016, Expired Date:10/24/2018 12:00:00 PM, Drilling unit acres:641.3, Proposed Well Type:OG, Proposed Well Class:TI
Change of Owner 2017-12-14 Operator changed from 8928, CARRIZO (UTICA) LLC to 9520, ASCENT RESOURCES UTICA LLC
APP 2018-05-25 Proposed Formations:UTICA THROUGH POINT PLEASANT, Issued Date:5/25/2018, Expired Date:5/24/2020 12:00:00 PM, Drilling unit acres:673.546, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2018-07-17
Correction to Well 2018-12-21 UPDATE TAKE/TARGET PER AS-DRILLED PLAT
Completion Report Received 2019-06-04
Record Last Modified 2019-06-06
Construction Permit Expires 2020-05-24

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 08/14/2018 09/17/2018 7677 16,204,200.0 216875

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 FE-200A FTSI Iron Control Listed Below Green Line Listed Below 0 0 0
FRW-1450 FTSI Friction Reducer Listed Below Green Line Listed Below 0 0 0
100 Mesh Sand FTSI Proppant Listed Below Green Line Listed Below 0 0 0
Bactron K-139 FTSI Biocide Listed Below Green Line Listed Below 0 0 0
Other Chemical(s) Listed Above See Trade Name(s) List Water 7732-18-5 85 0.0537898 0
Water 7732-18-5 92.5 0.96534 0
Water 7732-18-5 55 0.0134947 0
Water 7732-18-5 100 0.021801 0
Water 7732-18-5 50 0.0294759 0
Water 7732-18-5 45 0.00292916 0
0.1%-7.5% HCL FTSI Acid Listed Below Green Line Listed Below 0 0 0
Silica, Quartz 14808-60-7 100 10.0224 0
Alcohols, C11-14-iso-, C13-rich, ethoxylated 78330-21-9 5 0.00294759 0
Hydrogen Chloride 7647-01-0 7.5 0.0782708 0
Thiourea-formaldehyde Copolymer 68527-49-1 10 0.000104099 0
Citric Acid 77-92-9 30 0.00195277 0
Alcohol Ethoxylate Surfactants Proprietary 10 0.000104099 0
Orthophosphoric acid 7664-38-2 0.75 0.000184018 0
Quaternary ammonium compound 68424-85-1 10 0.0021801 0
Acetic acid 64-19-7 40 0.0026037 0
Cationic Polyacrylamide 9003-05-8 30 0.0176855 0
Glutaraldehyde 111-30-8 5 0.00109005 0
Phosphorous Acid 10294-56-1 2 0.000490715 0
Fatty Acids, Tall Oil 61790-12-3 10 0.000104099 0
Distillates (petroleum), hydrotreated light 64742-47-8 30 0.0176855 0
Methanol 67-56-1 90 0.000936891 0
Propargyl Alcohol 107-19-7 5 0.00005205 0
Silica, Quartz 14808-60-7 100 1.88978 0
Hydrochloric acid 7647-01-0 0.005 0.00000123 0
Ethanol 64-17-5 5 0.00109005 0
N-olefins Proprietary 3 0.00003123 0
Phosphonic Acid, {Nitrilotris (methylene)} Tris 6419-19-8 35 0.00858751 0
Hydrogen Chloride 7647-01-0 15 0.00949233 0
Phosphonic Acid, {(Dimethylamino) Methylene} Bis - 29712-30-9 5 0.00122679 0
10.1%-15.0% HCL FTSI Acid Listed Below Green Line Listed Below 0 0 0
40/70 White FTSI Proppant Listed Below Green Line Listed Below 0 0 0
CS-1000 SI FTSI Scale Inhibitor Listed Below Green Line Listed Below 0 0 0
CI-150 FTSI Acid Corrosion Inhibitor Listed Below Green Line Listed Below 0 0 0
Water Supplied by Operator Base Fluid Water 7732-18-5 100 86.8681 135,143,000.0

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
0 0 0

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 ASCENT RESOURCES UTICA LLC 19115 5069 8
2019 ASCENT RESOURCES UTICA LLC 253614 62239 90

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 ASCENT RESOURCES UTICA LLC Brine 2050 8
2019 ASCENT RESOURCES UTICA LLC Brine 16035 90

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1004808649 2015-4-29 0:00: PL No Violations 0.50
-1025559438 2018-10-3 0:00: CT No Violations 0.60
-1187977011 2017-8-7 0:00:0 DD No Violations 0.50
-2082762409 2018-11-9 0:00: CT No Violations
-420142187 2020-9-11 0:00: PW No Violations 1.00
-635555627 2019-12-13 0:00 PW No Violations 0.10
0252625450 2015-01-11 Drill / Deepen / Reopen No Violations On the day of my inspection I received a phone call from Carrizo Company Man Leon Hall stating that during the night due to the temperature the fluid levels fluctuated inside the high pressure separator and with the high winds a fine mist of soap and dust left primary containment. Upon arrival I witnessed that 100 feet by 230 feet of snow covered area off the well pad had been impacted with a light coating of dust and soap. A 30 foot by 30 foot area inside secondary containment around the high pressure separator was also impacted. Crews were onsite beginning to power wash the area and suck up the resulting fluid. Area outside containment will be remediated by the end of the day. Upon completion crews will begin cleaning up area inside containment. ODNR will be contacted when clean-up is completed.
0639294196 2014-09-03 Casing String Witnessed No Violations On the date of inspection I was informed my the company man on duty that a 30 inch diameter hole was drilled by Lightning Energy Services to a depth of 65 feet. Lightning then set 24 inch casing with a weight of 94.62lbs/ft on bottom. Allied Oil and Gas Services pumped 135sk of Class A cement weighing 15.6ppg, with a yield of 1.18, 2% CaCl, and 0.25lbs/sk of flake. They displaced with 29bbl of fresh water. 5bbl of cement returned to surface. While I was on site the cement sank to approximately 10 inches below the bottom of the cellar and was topped off with cement. The cement sank to approximately 8 inches below the bottom of the cellar while I was on site.
1004808649 2015-04-29 Preliminary Restoration No Violations On the day of my inspection accompanied by Southeast Regional Supervisor Brent Bear, the site passed preliminary restoration according to ORC 1509.072A.
1025559438 2018-10-03 Completion Testing No Violations During my inspection Frac Tech Services was on location and they have completed hydraulic stimulation operations on stage 76 of 76.
1187977011 2017-08-07 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed there was no change in the status of the well since the last inspection on September 19, 2016 with the 9.625 inch diameter intermediate secured with a bolted night cap. There is no production equipment, flowline or salesline in place and the location is shared with the Mohorovich 1S, 2S, 4S, 8H and Rector 14H.
1362521689 2016-09-07 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed no current activity and the drilling permit expired on 8/24/16. The last activity was on 1/14/15 with the 9.625 inch intermediate being set at 6718 feet. The cellar has been filled with pea gravel to the surface with a 6 inch polyvinyl chloride snorkel for water extraction.
1412577686 2014-10-06 Casing String Witnessed No Violations On the day of my inspection I witnessed that Highlands Drilling Rig #10 had drilled a 23 inch diameter hole to the depth of 550 feet. Wyoming Casing Crew ran 517 feet of 18.625 inch 87.5#/ft. J-55 casing having trouble with the last two joints. Highlands Drilling Rig #10 stabbed the float shoe with 4.5 inch diameter drill pipe. Baker Hughes was on site and broke circulation with 40bbls of fresh water and pumped 35bbls of gel, 10bbls of fresh water. During batching of cement the cement manifold plugged up and cement could not get to the correct weight. Water from the pump truck backed up to the bulk truck resulting in the job being shut down. Company Man requested new cementing equipment and would notify ODNR when it would be on site.
1412647655 2014-10-06 Drill / Deepen / Reopen No Violations Returning to site my inspection revealed that Baker Hughes had swapped out equipment and after gaining circulation pumped 35bbls of gel, 10bbls of fresh water and cemented casing with 480 sacks of Class A lead cement with 0.05% Static Free, 1% CaCl, 0.5% EC-1, 0.125#/sk. Cello Flake, 0.75gals/sk. FP-6L, 0.5% BA-10A. Lead cement was followed 125 sacks of Class A tail cement with 0.05% Static Free, 3% CaCl, 0.5% EC-1, 0.125#/sk. Cello Flake, 0.75gals/sk. FP-6L, and 0.5% BA-10A. Displaced cement with 6.8bbls of fresh water. Had good cement returns of 25bbls to surface.
1421176999 2015-01-13 Drill / Deepen / Reopen No Violations On the day of my inspection following up from release on Sunday, clean up was satisfactorily completed outside containment and almost complete around high pressure separator. Patterson UTI Drilling Rig #334 had reached td on the 12.25 inch diameter hole at 6800 feet and was running 9.625 inch 40#/ft. L- 80 casing with 2-Stage cement job to follow.
1532003856 2018-07-13 Drill / Deepen / Reopen No Violations The purpose of my inspection was a status check on drilling operations. During my inspection Patterson 577 was drilling at a measured depth of 13245 feet within the lateral. Ascent Company man stated that they expect to reach a total depth on Monday morning.
1771667846 2019-04-30 Production Wells No Violations The purpose of my inspection was a status check. During my inspection the well was equipped with a production tree style wellhead. Production tubing valves were in the open position. Pressure monitoring was present the 13.375-inch diameter intermediate casing had 200 pounds per square inch, 9.625-inch diameter intermediate had 160 pounds per square inch, 5.5-inch diameter production casing had 2000 pounds per square inch, and the production tubing had 1550 pounds per square inch. The production equipment consisted of ten 400-barrel tanks, two vapor recovery towers, six sand traps, six gas production units, three horizontal heater treaters, one compressor, and one combustor. The identification was posted at the well, tank battery, and entry. Laminated copies of the Drilling permits were posted at entry.
1783045265 2019-02-04 Production Wells No Violations The purpose of my inspection was a status check. During my inspection the well was equipped with a production tree style wellhead and a plunger lift system. The plunger lift system was plumbed up, but the wells were flowing without the assistance of the plunger. Production tubing valves were in the open position. Gauges were present on all casing strings and they read as follows, 13.375-inch diameter surface casing had 190 pounds per square inch, 9.625-inch diameter intermediate had 380 pounds per square inch, 5.5-inch diameter production casing had 2780 pounds per square inch, and the production tubing had 2800 pounds per square inch. The production equipment consisted of ten 400-barrel tanks, two vapor recovery towers, six sand traps, six gas production units, three horizontal heater treaters, one compressor, and one combustor. The identification was posted at the well, tank battery, and entry. Laminated copies of the Drilling permits were posted at entry. Wise tanker truck, USA Compressions, and Ascent Company well tender were all on location. I called Jarod Cogar with Ascents production to make him aware of the pressures found on the 9.625-inch diameter by 5.5-inch diameter annulus on the 1H well and stated that our records indicate that 18.625-inch diameter surface casing was ran on these wells and there were not any gauges present at surface to monitor pressures. I asked that Ascent look into getting a gauge and pressure relief valve assembled on the 18.625-inch casing.
1902291037 2018-09-10 Completion Testing No Violations The purpose of my inspection was a status check on hydraulic stimulation operations. During my inspection Frac Tech Services and Nine Energy Wireline was on location. 57 stages of 74 have been completed.
1903747611 2016-09-19 Drill / Deepen / Reopen No Violations
2082762409 2018-11-09 Completion Testing No Violations Status check inspection found the well drilling and completion process is now complete. The well was stimulated in 74 stages of 151 total stage length average. The 5.5 diameter casing has a bottom toe sleeve that was set at 19,108. There is a 7.0625 primary master valve on the well. A service rig is on location and rigged up on the # 14 well drilling out the completion plugs and running the production tubing. Crews are on site installing the production equipment, 2 tank batteries are being constructed on site. Annular pressure monitoring is in place.
252625450 2015-1-11 0:00: DD No Violations 2.00
639294196 2014-9-3 0:00:0 CS No Violations 2.00
856709626 2020-6-3 0:00:0 PW No Violations 1.00

For data sources see[9]