34-055-22052

Well Details

Well ID: 34-055-22052
Loading map...
Country: United States
State: Ohio
County: Geauga
Municipality: Chester Township
Operator Name: PIN OAK ENERGY PARTNERS LLC
Well Pad ID:
Farm/Lease Name: LANDIS UNIT
License Status: Producing
License Date: 2008-06-25
Spud Date: 2009-02-25
Spud Drilling Contractor: POULSON DRILLING
Final Drill Date: 2009-03-03
Well Total Depth: 3799.00 ft
Configuration: Vertical
Latitude: 41.510000
Longitude: -81.370000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2008-06-25 Proposed Formations:CLINTON, Issued Date:6/25/2008, Expired Date:6/25/2009 6:00:00 AM, Drilling unit acres:20.12, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2009-03-03
Completion Report Received 2009-05-11
Construction Permit Expires 2009-06-25
Change of Owner 2019-04-29 Operator changed from 169, JAMES R SMAIL INC to 9722, PIN OAK ENERGY PARTNERS LLC
Record Last Modified 2019-04-29

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2009-07-20 3626 3645 20
3626 3645 20
3626 3645 20

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
H2O 0 67500 Gal 50000

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2009 CUTTER EXPLORATION INC 3891.00 56.00 365
2010 CUTTER EXPLORATION INC 15027.00 105.00 365
2011 CUTTER EXPLORATION INC 16543.00 131.00 0
2012 JAMES R SMAIL INC 11157.00 60.00 366
2013 JAMES R SMAIL INC 13497.00 107.00 365
2014 JAMES R SMAIL INC 45646.00 175.00 365
2015 JAMES R SMAIL INC 19860.00 110.00 365
2016 JAMES R SMAIL INC 17707.00 68.00 365
2017 JAMES R SMAIL INC 17240.00 56.00 365
2018 JAMES R SMAIL INC 14216.00 117.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2009 CUTTER EXPLORATION INC Brine 1030 365
2010 CUTTER EXPLORATION INC Brine 33 365
2011 CUTTER EXPLORATION INC Brine 80
2012 JAMES R SMAIL INC Brine 70 366
2013 JAMES R SMAIL INC Brine 152 365
2014 JAMES R SMAIL INC Brine 30 365
2015 JAMES R SMAIL INC Brine 100 365
2016 JAMES R SMAIL INC Brine 31 365
2017 JAMES R SMAIL INC Brine 37 365
2018 JAMES R SMAIL INC Brine 73 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1156535620 2019-1-16 0:00: UP No Violations 0.40
-1441646122 2017-1-24 0:00: UP No Violations
-1528165032 2011-12-13 0:00 UP No Violations
-1786793692 2009-5-15 0:00: PW No Violations
-1816763388 2010-8-20 0:00: PL No Violations
-1959939857 2009-2-25 0:00: DD No Violations
0052706841 2013-05-28 UrbanProduction Wells No Violations My inspection found the well to be equipped with a plunger lift unit. The annulus valve is open to a pop off valve. The tank battery and well are in good repair and surrounded by a chain link fence. The tank battery consists of a 100 BBL production tank, a 50 BBL poly brine tank, and a mechanical separator. The vent stack on the production tank is plumbed into a 5 gallon charcoal filter. The vent stack is then plumbed up and topped with a spark arrestor. The proper identification is located on the tank battery. The lease road is in stable condition.
1156535620 2019-01-16 UrbanProduction Wells No Violations I conducted an inspection on this well. At the time of this inspection, the well was equipped with a plunger lift assembly and in production. The well was fenced with legible identification and a locked man door. The tank battery consisted of one 100 BBL production tank, one 50 BBL poly brine tank, and a mechanical separator. The valves on the separator were open and the chart showed production. The vent stack on the production tank was plumbed into a 5 gallon charcoal filter and topped with a spark arrestor The tank valves and pick-up lines were equipped with flat plugs. The tank battery was diked and fenced with a locked man door and legible identification. There was a Dominion East Ohio master meter present inside the diked tank battery. The lease access was stable.
1236108805 2009-03-03 Drill / Deepen / Reopen No Violations Operator has completed drilling well. Well was TD at 3799 No shows of gas during drilling, per driller. Top of the Lockport was at 3100. Operator ran 210 sacks of class A cement during the cementing of the long string. Good circulation during cement job. Pits were in good repair. Site was in good repair.
1238177249 2009-03-27 Drill / Deepen / Reopen No Violations Pits have been closed. 2psi on annulus gauge. Site is stable and drainage controls are in place.
1441646122 2017-01-24 UrbanProduction Wells No Violations During this inspection, it was observed that the well was equipped with a plunger lift assembly and the valves on the wellhead were open. The last reported production for this well was submitted in 2015. The well was fenced. The tank battery consisted of one 100 BBL production tank, one 50 BBL poly brine tank, and a mechanical separator. The valves on the separator were open and the chart showed production. The vent stack on the production tank was plumbed into a 5 gallon charcoal filter and topped with a spark arrestor The tank valves were equipped with flat plugs. The tank battery was diked and fenced with a locked man door. The proper, legible signage was located at the well and tank battery locations. The lease access was stable. No violations were observed.
1528165032 2011-12-13 UrbanProduction Wells No Violations Vegetation is established on this site. The lease road is stable. The silt fence can be removed from around the site. Proper identification has been posted. The well is in production and there is 36 PSI on the annulus. Tank battery is fenced properly, the dike is in good repair, equipment spacing is correct and the man doors are locked. The separator is iced over. Contacted Warren Shoenfelt and informed him of the icing issue.
1786793692 2009-05-15 Production Wells No Violations Well annulus is zero. Site is in good repair.
1816763388 2010-08-20 Preliminary Restoration No Violations Annulus pressure 32psi. Spacing is within 1509 limits. Charcoal filter is installed. Silt fence needs pulled. Man door latch needs repaired.
1959939857 2009-02-25 Drill / Deepen / Reopen No Violations Rig moving on site at the time of inspection. Pits are in good repair. Clay sides, small amount of water in the bottom of the pits, less than 2 inches in depth. No water seeping into the pits was noted during inspection. Reminded Hugh Palmer that sides of the pits need to be sloped, not dug near vertical. Drainage controls are in place north of the site. Safety fence was up on the west side of the pits. Permit ID sign was up. Permit was in the dog house.
2015822908 2009-02-26 Drill / Deepen / Reopen No Violations On site for surface cement job. Operator had ran pipe before I was on site. No loss of circulation during drilling. Fine black film was noted in the pit and coming up during circulation. Rig hand and Eric Poulson gathered a sample, sample had no odor. There was not enough to gather a sample for testing. No oil smell to substance, it appeared to be shale fines. Eric stated that they get this substance about every other well, in the area. Cement job went well. Cement held at surface.
52706841 2013-5-28 0:00: UP No Violations

For data sources see[9]

References