34-031-27210

Well Details

Well ID: 34-031-27210
Loading map...
Country: United States
State: Ohio
County: Coshocton
Municipality: Oxford Township
Operator Name: DIVERSIFIED PRODUCTION LLC
Well Pad ID:
Farm/Lease Name: APPLE
License Status: Producing
License Date: 2013-01-11
Spud Date: 2013-08-13
Spud Drilling Contractor: KILBARGER DRLG
Final Drill Date: 2014-02-15
Well Total Depth: 6319.00 ft
Configuration: Vertical
Latitude: 40.240000
Longitude: -81.710000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2013-01-11 Proposed Formations:BEREA-TREMPEALEAU, Issued Date:1/11/2013, Expired Date:1/11/2015 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:EDPW
Correction to Well 2013-08-02 REMOVED TARGET INFORMATION FROM RECORD. THIS IS A VERTICAL WELL, TARGET INFORMATION WAS FROM A DIFFERENT WELL LOCATION.
Plugged Back 2013-10-01 RR-DRY; PB TO CL
Reached Total Depth 2014-02-15 RR-DRY; PB TO CL
Construction Permit Expires 2015-01-11 RR-DRY; PB TO CL
Completion Report Received 2015-08-20 RR-DRY; PB TO CL
Change of Owner 2018-03-08 Operator changed from 98, to 8685,
Record Last Modified 2018-03-08 RR-DRY; PB TO CL

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 10/28/2013 10/28/2013 6709 89767

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Pro Hib II Producers Service Corp Inhibitor propargyl alcohol 107-19-7 30 0.00015 1
ethoxylated nonylphenol 68412-54-4 10 0.00005000 0.405
ethylene glycol 107-21-1 40 0.0002 2
glycol ethers 111-76-2 40 0.0002 2
methanol 67-56-1 30 0.00015 1
dimethylcocoamine, bis(chloroethyl)ether,

diquaternary ammonium salt

68607-28-3 60 0.00031 2
water NGO Development treatment carrier water 7732-18-5 100 94.2897 749106
Pro Clay Firm LP Producers Service Corp clay control ethylene glycol 107-21-1 40 0.00437 35
2-propen-1-aminium, N, N-dimethyl-N-2propenyl 26062-79-3 20 0.00218 17
Pro Gel 4 Producers Serivce Corp gel Guar Gum Blend 9000-30-0 100 0.23634 1878
Silica Sand Producers Service Corp proppant Crystalline Silica (quartz 14808-60-7 100 5.03479 40000
Pro Breaker 4 Producers Service Corp breaker Sucrose 57-50-1 46 0.00015 1
Ethylene Glycol 107-21-1 14 0.00005000 0
Buffer 1 Producers Service Corp pH Control Sulfamic Acid 5329-14-6 100 0.00629 50
Irontrol Producers Service Corp iron control sulfamic acid 5329-14-6 70 0.00881 70
IC Acid Producers Service Corp acid Hydrochloric Acid 7647-01-0 15 0.0536352 402
Pro NE-21 Producers Service Corp surfactant alchohols, C12-16, ethoxylated 68551-12-2 70 0.01434 114
2-butoxyethanol 111-76-2 40 0.00819 65
methanol 67-56-1 30 0.00614 49
Pro Clear Slik-2 Producers Service Corp Friction Reducer methanol 67-56-1 5 0.00066 5
2-butoxyethanol 111-76-2 10 0.00131 10
alchols, C12-16, ethoxylated 68551-12-2 70 0.00918 73
FLC Producers Service Corp fluid loss modified polysaccaride 9005-25-8 50 0.01888 150
crystalline silica in form of quartz 14808-60-7 65 0.02454 195

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2014 NGO DEVELOPMENT CORP. 1227.00 212.00 365
2015 NGO DEVELOPMENT CORP. 1318.00 122.00 365
2016 NGO DEVELOPMENT CORP. 991.00 72.00 365
2017 NGO DEVELOPMENT CORP. 838.00 79.00 365
2018 NGO DEVELOPMENT CORP. 186.00 0.00 0

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2014 NGO DEVELOPMENT CORP. Brine 204 365
2015 NGO DEVELOPMENT CORP. Brine 45 365
2016 NGO DEVELOPMENT CORP. Brine 40 365
2017 NGO DEVELOPMENT CORP. Brine 14 365
2018 NGO DEVELOPMENT CORP. Brine 0 0

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1165067684 2013-9-4 0:00:0 DD No Violations
-1190985989 2013-12-4 0:00: PL No Violations
-1216311830 2013-11-4 0:00: PL No Violations
-1493010880 2014-6-6 0:00:0 PL No Violations
-1988673619 2020-4-1 0:00:0 PW No Violations 0.70
-738941300 2013-9-27 0:00: DD No Violations
-846815972 2019-1-29 0:00: PW No Violations 0.40
-877132376 2013-10-1 0:00: PB No Violations
0036396903 2015-09-29 Production Wells No Violations On the day of my inspection I found that the well head was equipped with a plunger lift system. The valves were open and there was pressure on the gauge. The tank battery consisted of one 100 barrel tank, one 50 barrel tank, one separator and an earthen dike. Proper identification was posted and I found no leaks or spills.
0155261948 2013-09-19 Drill / Deepen / Reopen No Violations On the day of my inspection Kilbarger Drilling Rig #1 was rigged up and ready to start drilling. The permit was on location, there were no sags or tears in the pit liners and there were no leaks or spills.
0492057334 2019-02-25 Production Wells No Violations On the day of my inspection I found that there were no changes at the well site. I called Dale Smith to ask if he had any new information on their plans to produce the well. Dale said that once he looked into it he discovered that this well was not in his area of responsibility. He said that Chris Belch was responsible for that well and he passed my concerns on to him. I called Chris and he confirmed that there was some dispute between MFC and M&R Investments (Diversified) concerning the gas sales line. Chris said that there has not been any recent discussion about the well. He said that he would discuss the situation with his administration and get back to me with a tentative plan.
0738941300 2013-09-27 Drill / Deepen / Reopen No Violations On the day of my inspection I found that Kilbarger Drilling Rig #1 was drilling on air at a depth of 6068. The permit was on display in the dog house, there were no sags or tears in the pit liners and there were no leaks or spills.
0846815972 2019-01-29 Production Wells No Violations On the day of my inspection I found that the well was equipped with a plunger lift. The flow lines were connected and the valves were open. There were no leaks around the wellhead. The production equipment consisted of one 100 barrel steel tank, one 50 barrel steel tank and one horizontal separator in an earthen dike. The load valve was equipped with a bull plug. Correct, legible identification was posted and there were no leaks around the tanks.
0877132376 2013-10-01 Plug / Plug Back No Violations On the day of my inspection I found that Petroset and Kilbarger Drilling set a 250 isolation plug above the Rose Run, a 420 plug through the Utica Shale and a 50 plug through the Queenston.
0892614733 2013-09-30 Plug / Plug Back No Violations On the day of my inspection Kilbarger Drilling Rig 1 reported encountering an obstruction at approximately 6541 when attempting to run drill pipe in for the bottom plug. The pipe was hung briefly, but they were able to get it free. At that point they lost circulation due to the open end of the drill pipe being plugged. Petroset made and unsuccessful attempt to pump on the drill pipe to dislodge the material. Kilbarger Drilling then made the decision to trip out of the hole, clear the plugged drill pipe and run back in.
1011389569 2013-08-07 Drill / Deepen / Reopen No Violations On the day of my inspection I found that the site was under construction.
1165067684 2013-09-04 Drill / Deepen / Reopen No Violations On the day of my inspection I found that the pits were open. There were no sags or tears in the pit liners and the blow pit was fenced with temporary fencing. There were no leaks or spills.
1181609609 2013-10-02 Casing String Witnessed No Violations On the day of my inspection I found that Kilbarger Drilling Rig 1 ran new 10.5 lbs/ft 4.5 casing to 4440 Petroset broke circulation and pumped 150 sacks of class A cement. Good circulation was maintained throughout the job.
1190985989 2013-12-04 Preliminary Restoration No Violations On the day of my inspection I found that the drilling pits were closed, but the site was not reclaimed. The well was shut in and there was no production equipment in place.
1216311830 2013-11-04 Preliminary Restoration No Violations On the day of my inspection I found that the drilling pits were closed.
1376404242 2013-08-13 Drill / Deepen / Reopen No Violations On the day of my inspection I found that FMS Drilling was drilling a 17 conductor hole on fluid. They were at a depth of 61 and were preparing to run 60 of new 11.75 conductor casing. The permit was in the doghouse, there were no sags or tears in the pit liner and there were no leaks or spills.
1376423530 2013-08-13 Casing String Witnessed No Violations On the day of my inspection I found that FMS Drilling had drilled a 17.25 conductor hole on fluid to 62. They ran 60 of new 11.75 conductor casing. Petroset broke circulation and pumped 90 barrels of cement. Good circulation was maintained throughout the job, with 7 barrels of cement returns.
1376578893 2013-08-15 Drill / Deepen / Reopen No Violations I received notification from Scott Kees of NGO, that a fatal accident occurred on the drilling rig at or around midnight. He reported that FMS Drilling was at a depth of 289 drilling on air when they encountered a high volume of water. According to Kees, FMS Drilling was in the process of switching to fluid drilling when the derrick hand fell from the finger boards sustaining fatal injuries. The crew was sent home and drilling operations are suspended until further notice.
1376921156 2013-08-19 Drill / Deepen / Reopen No Violations On the day of my inspection I found that FMS Drilling was still shut down. The drilling rig was rigged up, the derrick was upright, and all of the drilling equipment was still on location. There were no sags or tears in the pit liners and there were no leaks or spills around the drilling rig.
1377522741 2013-08-26 Drill / Deepen / Reopen No Violations On the day of my inspection I found that FMS Drilling was rigged down and moved off of the location. The drilling pits remained and were full of fluid. There were no sags or tears in the pit liners, and there was orange temporary fencing around the blow pit.
1379338481 2013-09-16 Drill / Deepen / Reopen No Violations On the day of my inspection I found that the mud pit had been closed. The blow pit remained open. There were no sags or tears in the pit liner, the fluid level was down 12 to 24 and the entire pit was fenced. The conductor casing was temporarily capped. There were no leaks or spills.
1379946649 2013-09-20 Casing String Witnessed No Violations On the day of my inspection I found that Kilbarger Drilling rig 1 had drilled an 11 surface hole to 730 on fluid, and ran new 24# 8.625 casing equipped with two centralizers. They were circulating the hole with the mud pump upon my arrival. Petroset broke circulation and ran 235 sacks of cement. Good circulation was maintained throughout the job, with 5 barrels of cement returns.
1380026657 2013-09-24 Drill / Deepen / Reopen No Violations On the day of my inspection I found that Kilbarger Drilling Rig #1 was at a depth of 4673. They were tripping out to change bits while I was on location. The geolograph records showed that the blow out preventer and surface casing were pressure tested at 600 psi, both passed. The permit was on display in the dog house, there were no sags or tears in the pit liners and there were no leaks or spills.
1380204824 2013-09-26 Drill / Deepen / Reopen No Violations On the day of my inspection I found that Kilbarger Drilling Rig #1 was drilling on air at a depth of 5354. The permit was on display in the dog house, there were no sags or tears in the pit liners and there were no leaks or spills.
1380543281 2013-09-28 Drill / Deepen / Reopen No Violations Scott Kees of NGO called to report that they encountered a dry hole upon drilling into the Rose Run. He then proposed a plan to plug the well back to the Clinton.
1382448899 2013-10-22 Drill / Deepen / Reopen No Violations On the day of my inspection I found that all of the drilling equipment was removed from the location. The mud pit was closed and the blow pit was solidified but still open. The well head was shut in. There were four 500 barrel frac tanks staged on the location. There were no leaks or spills.
1388412574 2013-12-30 Preliminary Restoration No Violations On the day of my inspection I found that the well head was equipped with a plunger lift system. A crew was on site constructing a tank battery that consisted of one 100 barrel stock tank, one separator and an earthen dike. The ground was snow covered. The site still needs to be seeded.
1493010880 2014-06-06 Preliminary Restoration No Violations On the day of my inspection I found that the drill site was graded out to the approximate original contour and the pits were closed. The wellhead was equipped with a plunger lift system and the tank battery was in place with dike. The site is planted with agricultural crops. I found no signs of erosion.
155261948 2013-9-19 0:00: DD No Violations
1859036441 2019-02-14 Production Wells No Violations I was contacted by the landowner David Apple to request and inspection on a well that he believed to be idle. Mr. Apple claimed that the well has not been produced since sometime in 2017. He claimed that he sales line that NGO used to sell gas into is owned by MFC, and they do not have an agreement with M&R Investments. On the day of my inspection I found that the Demco valve was open, but the flow line valves were closed. The gauge on the tubing showed 520 pounds and the casing gauge showed 22 pounds. There were no leaks around the wellhead. I called Dale Smith to ask what was going on with the well. Dale said that he thought they were trying to work something out with MFC, but he did not have any solid information on the well. He said that they have a staff meeting tomorrow and he would bring it up and get back to me.
1905724944 2017-02-14 Production Wells No Violations On the day of my inspection I found that the well was being produced with a plunger lift system. The flow lines were connected and the valves were open. The tank battery consisted of one 100 barrel steel tank, one 50 barrel steel tank and one horizontal separator in an earthen dike. Correct, legible identification was posted and I found no leaks or spills.
2136205511 2013-09-30 Plug / Plug Back No Violations On the day of my inspection I found that Kilbarger Drilling Rig #1 was running in the hole with drill pipe to 6600 in order to set a bottom plug through the Rose Run.
36396903 2015-9-29 0:00: PW No Violations
492057334 2019-2-25 0:00: PW No Violations 0.30
892614733 2013-9-30 0:00: PB No Violations

For data sources see[8]