X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

34-029-21896

Well Details

Well ID: 34-029-21896
Loading map...
Country: United States
State: Ohio
County: Columbiana
Municipality: Franklin Township
Operator Name: EAP OHIO LLC
Well Pad ID: US-OH-001234
Farm/Lease Name: PAIGE 35-14-4
License Status: Producing
License Date: 2017-11-08
Spud Date: 2017-11-17
Spud Drilling Contractor: PATTERSON DRILLING
Final Drill Date: 2017-12-03
Well Total Depth: 18627.00 ft
Configuration: Horizontal
Latitude: 40.650000
Longitude: -80.880000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2017-11-08 Proposed Formations:POINT PLEASANT, Issued Date:11/8/2017, Expired Date:11/8/2019 12:00:00 PM, Drilling unit acres:362.44, Proposed Well Type:OG, Proposed Well Class:POOL
Original Spud 2017-11-17
Reached Total Depth 2017-12-03
Correction to Well 2018-02-23 UPDATE TARGET/TAKE PER AS-DRILLED PLAT
Correction to Well 2018-04-13 UPDATE TAKE/ACREAGE PER AS-DRILLED PLAT
Completion Report Received 2018-05-16
Record Last Modified 2018-09-28
Construction Permit Expires 2019-11-08

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2018-05-18 8438 8556 30
2018-05-18 18375 18478 18
18375 18478 18
8438 8556 30
8438 8556 30

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 01/22/2018 03/07/2018 8071.4 19,586,600.0 1,587,680.0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 HAI-OS HALLIBURTON Corrosion Inhibitor Propargyl Alcohol (2-Propynol) 000107-19-7 0.1 0 0
Methanol (Methyl Alcohol) 000067-56-1 0.6 0.00001000 0
FE-2A, FR-76, HAI-OS, OptiKleen-WF HALLIBURTON Breaker, Corrosion Inhibitor, Friction Reducer, Iron Control Agent Non-MSDS Components Not Provided by Supplier Not Assigned 0 0 0
Polyacrylamide copolymer Trade Secret 0.3 0.00024 0
SC-30 FOUNTAIN QUAIL Scale Inhibitor Sodium Hydroxide 1310-73-2 0.02 0 0
15% HCl Acid HALLIBURTON Acid Hydrochloric Acid 7647-01-0 0.3 0.00308 0
Fresh Water CHESAPEAKE ENERGY Carrier/Base Fluid Water 007732-18-5 1 0.7874 0
OptiKleen-WF HALLIBURTON Breaker Sodium perborate tetrahydrate 010486-00-7 1 0 0
FR-76 HALLIBURTON Friction Reducer Proprietary Inorganic Salt Trade Secret 0.3 0.0002 0
Petroleum Distillate Hydrotreated Light 064742-47-8 0.3 0.0002 0
Northern White Sand HALLIBURTON Proppant - Natural Crystalline Silica (Quartz Sand, Silicon Dioxide) 014808-60-7 1 0.12848 0
FE-2A HALLIBURTON Iron Control Agent Citric Acid 000077-92-9 0.6 0.00004000 0
Recycled Produced Water CHESAPEAKE ENERGY Carrier/Base Fluid Water 007732-18-5 1 0.05193 0
Chlorine Dioxide FOUNTAIN QUAIL Anti-Bacterial Agent Chlorine Dioxide 10049-04-4 0.01 0 0

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2018-01-22 H2O 15 6955 Bbl 151472 STAGE 1/69

STAGES 2-68 SEE IMAGES

2018-03-07 H2O 15 6342 Bbl 333577 Halliburton STAGE 69/69

STAGE 2-68 SEE IMAGES

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 CHESAPEAKE EXPLORATION LLC 2116162 2 271
2019 CHESAPEAKE EXPLORATION LLC 479985 4 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 CHESAPEAKE EXPLORATION LLC Brine 60704 271
2019 CHESAPEAKE EXPLORATION LLC Brine 8185 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1489161770 2018-1-4 0:00:0 DD No Violations 0.30
-176645994 2017-11-27 0:00 DD No Violations 3.00
-1894319771 2017-11-29 0:00 DD No Violations 3.50
-1998563357 2018-3-1 0:00:0 PW No Violations 0.50
-964850688 2017-11-20 0:00 DD No Violations 1.00
0176645994 2017-11-27 Drill / Deepen / Reopen No Violations The purpose of my inspection was to conduct a status check on drilling operations on well #2-1896. Upon arrival I met with company representative Kris Gonzales. Mr. Gonzales accompanied me during the inspection. At the time of inspection, the drilling rig was drilling the 8.75 borehole section on air. A closed loop system solids control system was in operation. No dust was observed on location from the operation. No spills or leaks were observed. During the inspection I discussed the ODNR-DOGRM notification requirements. Mr. Gonzales sent an E-mail on 11/25/2017 reporting that cementing intermediate casing would occur on 11/26/2017. No direct notification occurred. I communicated to Mr. Gonzales that in the future, E-mail notification was sufficient during the course of normal business hours, however during weekends and evenings direct notification would be required to ensure a representative of ODNR-DOGRM could be present to witness operations. No violations were observed during this inspection.
0519854927 2017-01-22 Production Wells No Violations The purpose of my inspection was to witness stimulation activities on well #2-1896. Chesapeake Exploration called ODNR-DOGRM emergency response coordinator Fred Romeo to give notice that stimulation work was to commence. Identification posted at the entrance indicated the incorrect township and county. Halliburton was the pressure pumping contractor. Fluid handling equipment was located on containment. No leaks were observed. At the time of my inspection stage 2 of 74 was being pumped in well 2-1895 while 9 Energy Services perforated the next stage in well #2-1896. The 5.5 production casing annular pressure gauge indicated 43 psi. While on location I met with Chesapeake representative Ryan Boggs to discuss notification. Mr. Boggs stated that job binder issued to the location was not updated from the office. While on location I called and spoke with Chesapeake Regulatory Manager Jody Jones regarding the location identification and notification. Mr. Jones stated that he would have corrected identification ordered and posted. He continued that he would discuss updating the contacts list internally with the responsible party and reach out to ODNR-DOGRM for clarification. I will schedule to re-inspect the location prior to conclusion of stimulation work.
0962542687 2018-03-04 Drill / Deepen / Reopen No Violations I was on location to observe the fracing of the above location. Halliburton was the contractor performing the operation and O-9 Well Service performing the perforating. As they were preparing to start their next stage they discovered a leak in one of there high pressure pump lines. The operation was shut down until a new section of line could replaced. I walked the area of operation all contianment was in place. No violations were noted at this time.
0964850688 2017-11-20 Drill / Deepen / Reopen No Violations The purpose of my inspection was to document the status of the conductor cement on well #2-1896. Access to the well location remained in good repair. At the time of my inspection the conductor cement had held at surface. The cellar contained freshwater from recent precipitation. A mousehole had been drilled and cemented adjacent to the cellar. Contractors were on location installing containment and setting up the backyard in conjunction with moving the bottom hole rig onto location. Drill cuttings from the conductor section were being loaded onto a truck for disposal. No violations were observed during this inspection.
1110395611 2018-04-05 Production Wells No Violations The purpose of my inspection was to conduct a status check of well #2-1896. I met Chesapeake representative and location supervisor Bryan Waid on location. Flowback operations for well 2-1896 were occurring at the time of inspection. Correct identification was present at the well head. The intermediate and production casing annular gauges remained labeled and plumbed above grade. Valves were in the open position. Each gauge indicated 0 psi. No evidence of leaks were observed. Recovered fluid was transferred to steel 500 barel tanks that were positioned inside of containment. I did not witness any evidence of leaks. No violations were observed during this inspection.
1281175315 2017-12-04 Casing String Witnessed No Violations The purpose of my inspection was to conduct a pre production casing cement inspection and witness the installation of 5.5 production casing. I arrived on location and observed Wyoming Casing installing new 5.5 P-110 23 lb./ft. casing into the well. I walked the location and did not witness any evidence of spills or leaks off of containment. No odors were detected. I met with company representative Will Doby to discuss the cement plan. Mr. Doby stated that O-Tex pumping would be the production casing cement contractor. At the time of inspection Mr. Doby did not have a formal pump schedule for the job, but stated the plan called to cement with 15.6 ppg Class H cement that would be circulated back to surface. No violations were observed during this inspection.
1489161770 2018-01-04 Drill / Deepen / Reopen No Violations The purpose of my inspection was to document the status of well #2-1896. Drilling activities had concluded. The 5.5 production casing was equipped with a pressure gauge that indicated 0 psi. The 9.625 and 5.5 annular pressure gauges had not been plumbed above grade and identified. The well cellar was covered with steel grating to prevent falls. I was unable to document the status of the mousehole due to ice and snow on the surface. No leaks were observed. No violations were observed during this inspection.
1840484718 2018-05-10 Production Wells No Violations The purpose of my inspection was to conduct a status check on well #2-1896. The well is one of four production wells on the pad. Correct identification was present at the well entrance. The lease road and pad remained in good repair. I met production consultant Bryan Waid at the pad entrance. Mr. Waid reported the newly completed wells were being monitored due to sanding issues at surface. At the time of my inspection the 9.625 annular valve was open and the installed gauge indicated 0 psi. The 5.5 annular valve was open and the installed gauge indicated 0 psi. The cellar remained open and contained meteoric water. No sheen was observed. No audible or visual leaks were observed. The mousehole was cemented. While on location a Stallion vacuum truck arrived on location and was loading production fluid from the tank battery. I did not observe any leaks, spills or malodors. No violations were observed during this inspection.
1894319771 2017-11-29 Drill / Deepen / Reopen No Violations The purpose of my inspection was to conduct a status check inspection on well #2-1896. Access to the well site remained stable. At the time of my inspection KLX was on location rigging up to perform a cement bond log on the 9.625 intermediate casing. I walked around the perimeter of the drilling equipment and found no evidence of leaks or spills. The cement bond log indicated acceptable bonding in the entire annular space from casing seat to surface. While on location I met with drilling consultant Danny Lambert and discussed notification requirements. No violations were observed during this inspection.
1998563357 2018-03-01 Production Wells No Violations The purpose of my inspection was to witness stimulation activities on well #2-1896. Stimulation work on the well was postponed due to issues with downhole wireline perforating equipment. At the time of my inspection stage 47 of 74 was being pumped away while 9 Energy was perforating the next stage in well 2-1895. Stage 47 treated at an average of 8561 psi with an average rate of 85 barrels per minute. No violations were observed during this inspection.
519854927 2017-1-22 0:00: PW No Violations 2.00
962542687 2018-3-4 0:00:0 DD No Violations 2.50

For data sources see[10]

References